TxDOT Subcontracts for BROOKE PAVING AND CONSTRUCTION LLC
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0507-01-021 | SAN PATRICIO | SH 234 | 03/05/2024 | J. CARROLL WEAVER, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 5.18% | $310,952.36 | 83.00% | $6,002,941.36 |
| 3596-01-009 | NUECES | SS 3 | 02/02/2024 | ANDERSON COLUMBIA CO., INC. | 02/26 | 12/25 | 11/25 | 10/25 | 09/25 | 10.89% | $735,634.85 | 105.00% | $6,755,140.97 |
| 0101-04-131 | SAN PATRICIO | US 181 | 01/05/2024 | ANDERSON COLUMBIA CO., INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.30% | $39,626.29 | 99.00% | $13,208,761.86 |
| 0617-01-207 | NUECES | SH 358 | 06/27/2023 | ANDERSON COLUMBIA CO., INC. | 03/26 | 02/26 | 01/26 | 12/25 | 11/25 | 1.59% | $80,189.53 | 101.00% | $5,043,366.79 |
| 0916-02-021 | KLEBERG | CR | 04/05/2023 | CROSS PLUS CONSTRUCTION, LLC | 10/25 | 09/25 | 08/25 | 07/25 | 06/25 | 2.72% | $50,014.82 | 80.00% | $1,838,780.05 |
| 0180-04-120 | ARANSAS | SH 35 | 03/08/2023 | ANDERSON COLUMBIA CO., INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.18% | $41,013.60 | 99.00% | $22,785,332.97 |
| 0916-28-071 | SAN PATRICIO | PR 25A | 03/07/2023 | J. CARROLL WEAVER, INC. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 13.96% | $340,720.14 | 99.00% | $2,440,688.70 |
| 0989-02-054 | NUECES | FM 624 | 08/03/2022 | HAAS-ANDERSON CONSTRUCTION, LTD. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.07% | $7,583.33 | 97.00% | $10,833,322.67 |