ZAVALA FM 393 (1937-02-032)

Items: 72

County: ZAVALA
Length: N/A
Highway: FM 393
District: LAREDO
Control Number: 1937-02-032
DBE Goal: N/A
Project: BR 2021(297)
Guaranty: N/A
Time: 275 WORKING DAYS
Engineer's Estimate: $9,587,228.70
Date: 01/07/2021 (5 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (4)
E
Engineer's Estimate
$9,587,228.70
$8,978,775.55
Over/Under Est: -6.35% -$608,453.15
$9,136,779.45
Over/Under Est: -4.7% -$450,449.25
Amt Left: 1.76% $158,003.90
Over/Under Est: -3.33% -$319,199.85
Amt Left: 3.22% $289,253.30
Delta: -1.44% -$131,249.40
Over/Under Est: 1.79% $171,758.88
Amt Left: 8.69% $780,212.03
Delta: -5.30% -$490,958.73

Bid Items & Bid Tabulations

72 Total 0 of 72
ZAVALA  |  FM 393  |  LAREDO  |  1937-02-032  |  01/07/2021  |  $9,587,228.70  |  BR 2021(297)  |  BRIDGE REPL  |  275 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
RELMCO, INC.
ANDERSON COLUMBIA CO., INC.
ANGEL BROTHERS HOLDINGS CORP.
PREPARING ROW
STA 52.550 $750.000 $496.170 $7,000.000 $520.000 $8,500.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 8,822.000 $3.000 $3.490 $1.500 $2.400 $1.500
REMOVING STAB BASE & ASPH PAV (12")
SY 6,580.000 $5.000 $7.000 $3.000 $5.000 $5.000
EXCAVATION (ROADWAY)
CY 7,317.000 $9.000 $12.180 $9.000 $8.000 $5.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 19,133.000 $15.000 $14.280 $18.000 $16.000 $18.500
FURNISHING AND PLACING TOPSOIL (4")
SY 22,928.000 $0.990 $1.090 $4.000 $1.000 $1.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 30,868.000 $0.120 $0.190 $0.209 $0.200 $0.350
DRILL SEEDING (TEMP) (WARM)
SY 30,868.000 $0.100 $0.150 $0.170 $0.150 $0.260
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 5,208.000 $50.000 $50.930 $52.000 $52.000 $50.000
LIME (HYD, COM, OR QK(SLURRY))
TON 251.000 $194.070 $173.250 $175.000 $188.000 $155.000
LIME TRT (SUBGRADE)(6")
SY 16,838.000 $2.500 $1.940 $3.000 $5.000 $4.500
PRIME COAT (MC-30)
GAL 3,054.000 $5.000 $4.470 $3.760 $4.000 $5.000
CEM STABIL BKFL
CY 332.200 $100.000 $240.910 $200.000 $150.000 $165.000
DRILL SHAFT (24 IN)
LF 1,754.000 $200.000 $202.650 $170.000 $210.000 $200.000
DRILL SHAFT (36 IN)
LF 3,312.000 $225.000 $254.320 $250.000 $250.000 $300.000
CL C CONC (ABUT)
CY 125.400 $950.000 $1,000.000 $1,148.000 $1,200.000 $1,200.000
CL C CONC (CAP)
CY 399.200 $900.000 $1,000.000 $1,129.620 $1,300.000 $1,200.000
CL C CONC (COLUMN)
CY 139.800 $950.000 $1,000.000 $1,211.520 $1,600.000 $1,200.000
REINF CONC SLAB
SF 59,850.000 $25.000 $22.000 $22.000 $22.000 $20.000
REINF CONC SLAB (SLAB BEAM)
SF 14,700.000 $20.000 $22.000 $13.650 $17.000 $17.500
APPROACH SLAB
CY 192.600 $550.000 $600.000 $821.800 $780.000 $600.000
RETAINING WALL (CONC BLOCK)
SF 11,912.000 $42.000 $30.000 $29.000 $39.300 $50.000
PRESTR CONC SLAB BEAM (4SB12)
LF 1,382.000 $160.000 $135.000 $115.000 $140.000 $130.000
PRESTR CONC SLAB BEAM (5SB12)
LF 1,727.500 $160.000 $135.000 $115.000 $135.000 $130.000
PRESTR CONC GIRDER (TX28)
LF 8,493.120 $150.000 $135.000 $115.000 $140.000 $125.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 2,154.000 $14.000 $4.930 $5.000 $5.000 $12.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 565.000 $160.000 $235.000 $105.000 $130.000 $285.000
RIPRAP (CONC)(FLUME)
CY 164.000 $492.830 $500.000 $425.000 $490.000 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 189.000 $436.000 $600.000 $450.000 $490.000 $525.000
RAIL (TY T223)
LF 3,670.000 $120.000 $100.000 $72.000 $103.000 $115.000
ARMOR JOINT (SEALED)
LF 228.000 $95.000 $100.000 $65.000 $115.000 $100.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 373.000 $130.000 $125.000 $90.000 $107.000 $120.000
INLET (COMPL) (DROP) (SPL)
EA 2.000 $5,758.000 $2,000.000 $6,500.000 $4,060.000 $7,500.000
REMOV STR (WINGWALL)
EA 28.000 $1,600.000 $25.000 $900.000 $485.000 $100.000
REMOV STR (BOX CULVERT)
LF 483.000 $60.000 $115.000 $60.000 $80.000 $75.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $60,000.000 $45,000.000 $45,000.000 $37,300.000 $25,000.000
REMOVE STR (RAIL)
LF 216.000 $38.130 $10.000 $50.000 $40.000 $10.000
MOBILIZATION
LS 1.000 $912,359.940 $868,449.970 $825,000.000 $827,000.000 $795,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $7,500.000 $3,277.170 $7,500.000 $1,700.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 1,911.000 $42.390 $56.650 $67.180 $61.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 1,911.000 $19.630 $16.480 $24.180 $14.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 222.000 $17.380 $17.510 $38.700 $37.000 $31.000
CONSTRUCTION EXITS (REMOVE)
SY 222.000 $5.310 $2.060 $19.350 $19.000 $10.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 810.000 $2.500 $3.600 $4.250 $3.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 810.000 $0.820 $1.030 $2.090 $2.000 $0.750
DRIVEWAYS (ACP)
SY 131.000 $31.000 $48.180 $65.000 $50.000 $45.000
RUMBLE STRIPS (SHOULDER)
LF 6,115.000 $0.170 $0.420 $0.380 $0.250 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 1,900.000 $0.190 $0.470 $0.380 $0.300 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 2,837.500 $22.000 $19.500 $20.970 $20.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 12.000 $1,800.000 $1,450.000 $1,558.750 $2,000.000 $1,800.000
REMOVE METAL BEAM GUARD FENCE
LF 1,000.000 $1.700 $1.750 $1.880 $1.800 $1.000
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $174.420 $175.000 $188.250 $180.000 $150.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $275.000 $115.000 $123.620 $118.000 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $3,000.000 $2,550.000 $2,741.250 $2,600.000 $2,600.000
ALUMINUM SIGNS (TY A)
SF 211.000 $22.450 $16.000 $30.100 $29.000 $17.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 21.000 $425.770 $568.000 $483.750 $460.000 $575.000
REMOVE SM RD SN SUP&AM
EA 8.000 $70.960 $85.000 $91.370 $87.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 44.000 $22.490 $26.000 $17.200 $16.000 $25.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 12.000 $72.000 $68.000 $161.250 $154.000 $70.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 26.000 $33.280 $32.000 $34.400 $33.000 $30.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 6,710.000 $0.220 $0.480 $0.520 $0.500 $0.300
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 6,710.000 $0.220 $0.480 $0.520 $0.500 $0.300
PAVEMENT SEALER 4"
LF 1,560.000 $0.100 $0.350 $0.370 $0.400 $0.520
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 10,410.000 $0.310 $0.600 $0.650 $0.600 $0.520
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 138.000 $0.220 $0.650 $0.700 $0.700 $2.100
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 9,560.000 $0.380 $0.600 $0.650 $0.600 $0.520
REFL PAV MRKR TY II-A-A
EA 139.000 $3.000 $6.000 $6.450 $6.000 $12.000
PAV SURF PREP FOR MRK (4")
LF 1,560.000 $0.050 $0.150 $0.160 $0.150 $0.520
SP MIXES SP-B SAC-B PG70-22
TON 2,536.000 $120.000 $74.160 $96.600 $80.000 $100.000
SP MIXES SP-C SAC-A PG76-22
TON 1,661.000 $130.000 $90.360 $120.750 $100.000 $115.000
BONDING COURSE
GAL 2,287.000 $3.000 $3.060 $5.250 $3.000 $3.250
PORTABLE CHANGEABLE MESSAGE SIGN
EA 9.000 $8,500.000 $7,500.000 $16,000.000 $9,300.000 $5,000.000
Totals: $9,587,228.700 $8,978,775.556 $9,136,779.467 $9,268,028.850 $9,758,987.580