WOOD US 80 (0096-02-049)

Items: 10

County: WOOD
Length: N/A
Highway: US 80
District: TYLER
Control Number: 0096-02-049
DBE Goal: N/A
Project: STP 2018(196)HES
Guaranty: N/A
Time: 49 WORKING DAYS
Engineer's Estimate: $201,570.00
Date: 10/04/2017 (8 years ago)
Contract Number: N/A
Type: INSTALL SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$201,570.00
Over/Under Est: -20.62% -$41,565.00
Over/Under Est: -4.89% -$9,850.00
Amt Left: 19.82% $31,715.00
Over/Under Est: -1.27% -$2,566.25
Amt Left: 24.37% $38,998.75
Delta: -3.80% -$7,283.75
Over/Under Est: 1.76% $3,540.00
Amt Left: 28.19% $45,105.00
Delta: -3.07% -$6,106.25
Over/Under Est: 23.77% $47,920.00
Amt Left: 55.93% $89,485.00
Delta: -21.64% -$44,380.00

Bid Items & Bid Tabulations

10 Total 0 of 10
WOOD  |  US 80  |  TYLER  |  0096-02-049  |  10/04/2017  |  $201,570.00  |  STP 2018(196)HES  |  INSTL SAFETY LIGHTING  |  49 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SIGNAL SERVICES GROUP INC.
AMERICAN LIGHTING AND SIGNALIZATION, LLC
STRIPING TECHNOLOGY, L.P.
FNH CONSTRUCTION, LLC
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 104.000 $220.000 $150.000 $500.000 $277.740 $185.000 $310.000
MOBILIZATION
LS 1.000 $15,000.000 $15,000.000 $5,000.000 $18,389.020 $7,500.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,500.000 $4,000.000 $3,000.000 $2,901.360 $3,200.000 $8,500.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 13.000 $4,000.000 $3,500.000 $3,000.000 $4,051.690 $4,500.000 $3,100.000
CONDT (PVC) (SCH 40) (2")
LF 1,180.000 $8.000 $6.500 $4.000 $11.890 $14.000 $15.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 820.000 $25.000 $18.000 $30.000 $22.770 $25.000 $40.000
ELEC CONDR (NO.8) BARE
LF 2,000.000 $1.500 $1.000 $1.250 $1.430 $3.500 $2.000
ELEC CONDR (NO.8) INSULATED
LF 4,000.000 $1.600 $1.000 $1.250 $1.490 $4.000 $2.000
GROUND BOX TY A (122311)W/APRON
EA 13.000 $950.000 $575.000 $1,300.000 $962.380 $750.000 $650.000
ELC SRV TY T 120/240 000(NS)GS(L)SP(O)
EA 6.000 $6,500.000 $4,000.000 $4,000.000 $4,602.850 $5,150.000 $5,000.000
Totals: $201,570.000 $160,005.000 $191,720.000 $199,003.750 $205,110.000 $249,490.000