WILSON US 181 (0100-03-094)
Items: 57
County: WILSON
Length: 0.1950 MILES
Highway: US 181
District: SAN ANTONIO
Control Number: 0100-03-094
DBE Goal: 0.0%
Project: STP 2B25(170)HES
Guaranty: $6,000.00
Time: 17 WORKING DAYS
Engineer's Estimate: $163,511.74
Date: 12/03/2025 (6 months ago)
Contract Number: 12253229
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206784
Contract Type: Federal
Project Description: LENGTHEN LEFT TURN LANE TO INCREASE STORAGE CAPACITY
Mail/Deliver Bids To: N/A
JEB SMITH
LUKE STORY
WILSON US 181 (0100-03-094)
Project Name: N/A
Project: STP 2B25(170)HES
Length: 0.1950 MILES
Project Type: CONSTRUCTION
Limits From: AT SHANNON RIDGE DRIVE
Limits To: .
Project Description: LENGTHEN LEFT TURN LANE TO INCREASE STORAGE CAPACITY
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$163,511.74 | |||
| $184,257.74 |
12.69%
$20,746.00
|
|||
| $247,421.45 |
51.32%
$83,909.71
|
34.28%
$63,163.71
|
||
| $257,700.53 |
57.6%
$94,188.79
|
39.86%
$73,442.79
|
-4.15%
-$10,279.08
|
|
| $288,000.00 |
76.13%
$124,488.26
|
56.3%
$103,742.26
|
-11.76%
-$30,299.47
|
E
Engineer's Estimate
$163,511.74
1
Awarded
$184,257.74
Over/Under Est:
12.69%
$20,746.00
$247,421.45
Over/Under Est:
51.32%
$83,909.71
Amt Left:
34.28%
$63,163.71
$257,700.53
Over/Under Est:
57.6%
$94,188.79
Amt Left:
39.86%
$73,442.79
Delta:
-4.15%
-$10,279.08
$288,000.00
Over/Under Est:
76.13%
$124,488.26
Amt Left:
56.3%
$103,742.26
Delta:
-11.76%
-$30,299.47
Bid Items & Bid Tabulations
57
Total
0 of 57