Show Job Controls
Bid Cobra

WILLIAMSON RM 2338 (2211-01-026)

Items: 134

County: WILLIAMSON
Length: N/A
Highway: RM 2338
District: AUSTIN
Control Number: 2211-01-026
DBE Goal: N/A
Project: STP 2021(620)HES
Guaranty: N/A
Time: 171 WORKING DAYS
Engineer's Estimate: $8,296,923.05
Date: 06/03/2021 (5 years ago)
Contract Number: N/A
Type: CONSTRUCT BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (8)
E
Engineer's Estimate
$8,296,923.05
$7,570,067.83
Over/Under Est: -8.76% -$726,855.22
$7,994,999.95
Over/Under Est: -3.64% -$301,923.10
Amt Left: 5.61% $424,932.12
Over/Under Est: -3.05% -$252,790.05
Amt Left: 6.26% $474,065.17
Delta: -0.61% -$49,133.05
Over/Under Est: 0% $306.10
Amt Left: 9.61% $727,161.32
Delta: -3.15% -$253,096.15
Over/Under Est: 1.21% $100,466.90
Amt Left: 10.93% $827,322.12
Delta: -1.21% -$100,160.80
Over/Under Est: 2.7% $223,611.18
Amt Left: 12.56% $950,466.40
Delta: -1.47% -$123,144.28
Over/Under Est: 4.77% $395,857.52
Amt Left: 14.83% $1,122,712.74
Delta: -2.02% -$172,246.34
$10,709,264.75
Over/Under Est: 29.08% $2,412,341.70
Amt Left: 41.47% $3,139,196.92
Delta: -23.20% -$2,016,484.18

Bid Items & Bid Tabulations

134 Total 0 of 134
WILLIAMSON  |  RM 2338  |  AUSTIN  |  2211-01-026  |  06/03/2021  |  $8,296,923.05  |  STP 2021(620)HES  |  CONSTRUCT BRIDGE  |  171 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J.D. ABRAMS, L.P.
CHASCO CONSTRUCTORS
JAMES CONSTRUCTION GROUP, LLC
ANGEL BROTHERS HOLDINGS CORP.
CAPITAL EXCAVATION COMPANY
HUNTER INDUSTRIES, LTD.
JORDAN FOSTER CONSTRUCTION, LLC
COPASA INC
PREPARING ROW
STA 51.500 $1,800.000 $7,350.000 $2,500.000 $14,500.000 $300.000 $920.000 $1,115.250 $5,115.000 $10,200.000
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 12,200.000 $5.000 $1.500 $2.500 $1.740 $5.000 $4.900 $5.000 $3.750 $2.520
EXCAVATION (ROADWAY)
CY 6,250.000 $9.000 $4.000 $10.000 $4.870 $8.000 $14.300 $9.990 $13.200 $7.540
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 60,030.000 $12.000 $12.000 $13.500 $17.780 $16.000 $15.750 $25.910 $17.250 $21.680
FURNISHING AND PLACING TOPSOIL (4")
SY 33,101.000 $1.500 $1.250 $2.000 $0.190 $2.000 $2.700 $1.370 $1.800 $2.870
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 33,101.000 $0.150 $0.170 $0.200 $0.260 $0.260 $0.150 $0.190 $0.150 $0.190
DRILL SEEDING (TEMP) (WARM)
SY 33,101.000 $0.150 $0.080 $0.100 $0.220 $0.230 $0.100 $0.150 $0.100 $0.150
VEGETATIVE WATERING
MG 1,500.000 $14.620 $18.000 $20.000 $18.520 $14.000 $19.950 $16.650 $20.000 $33.470
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,000.000 $1.000 $3.000 $2.100 $1.570 $1.600 $2.000 $3.650 $2.100 $3.650
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 14,470.000 $45.000 $35.000 $37.000 $31.940 $35.000 $32.750 $38.070 $32.500 $30.000
PRIME COAT (MULTI OPTION)
GAL 8,695.000 $4.000 $3.250 $3.100 $3.000 $3.800 $3.100 $3.830 $3.100 $3.000
TOM (ASPHALT) PG 76-22
TON 132.000 $150.000 $125.000 $125.000 $121.000 $98.000 $126.000 $107.490 $124.000 $121.000
TOM - C (AGGREGATE) SAC - B
TON 2,040.000 $100.000 $125.000 $125.000 $121.000 $98.000 $135.000 $107.490 $124.000 $121.000
TACK COAT
GAL 3,050.000 $3.300 $2.600 $2.600 $2.500 $2.500 $2.600 $2.960 $2.600 $2.500
STRUCT EXCAV
CY 4,359.000 $5.000 $0.010 $2.500 $9.500 $5.500 $10.600 $5.000 $2.700 $15.000
CEM STABIL BKFL
CY 2,773.000 $120.000 $50.000 $114.000 $107.310 $125.000 $162.000 $126.010 $138.000 $120.000
CUT & RESTORING PAV
SY 100.000 $110.000 $65.000 $50.000 $44.780 $110.000 $87.100 $186.650 $160.000 $109.960
CUT & RESTORE ASPH PAVING
SY 140.000 $120.000 $65.000 $50.000 $43.470 $115.000 $112.000 $107.890 $155.000 $120.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 249.000 $120.000 $50.000 $160.000 $106.700 $125.000 $154.000 $126.010 $136.000 $120.000
FLOWABLE BACKFILL
CY 60.000 $260.000 $125.000 $220.000 $106.700 $220.000 $155.000 $148.590 $135.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 1,298.000 $7.000 $3.000 $3.000 $0.960 $10.000 $7.100 $5.250 $2.200 $25.000
TEMPORARY SPL SHORING
SF 270.000 $22.000 $0.010 $1.000 $30.000 $50.000 $24.400 $17.210 $62.000 $25.000
DRILL SHAFT (18 IN)
LF 64.000 $100.000 $125.000 $100.000 $87.850 $120.000 $131.000 $124.700 $105.000 $148.030
DRILL SHAFT (36 IN)
LF 480.000 $200.000 $200.000 $220.000 $172.470 $220.000 $182.000 $250.960 $232.000 $379.860
CL C CONC (ABUT)
CY 61.000 $1,100.000 $1,200.000 $1,000.000 $531.850 $930.000 $800.000 $1,278.570 $900.000 $1,272.950
CL C CONC (BENT)
CY 41.000 $1,300.000 $1,200.000 $1,100.000 $754.780 $1,100.000 $1,140.000 $1,462.410 $1,300.000 $1,886.210
CL C CONC (COLUMN)
CY 34.600 $1,100.000 $1,200.000 $1,050.000 $844.820 $1,070.000 $1,080.000 $1,203.000 $1,200.000 $1,338.930
REINF CONC SLAB
SF 16,560.000 $15.000 $18.000 $16.500 $16.870 $17.500 $16.550 $21.580 $18.450 $25.290
APPROACH SLAB
CY 91.500 $500.000 $500.000 $465.000 $434.680 $600.000 $540.000 $515.880 $385.000 $443.720
RETAINING WALL (MSE)
SF 28,400.000 $51.000 $45.000 $46.000 $28.120 $48.000 $52.500 $32.490 $45.000 $65.000
PRESTR CONC GIRDER (TX54)
LF 2,151.000 $125.000 $148.000 $170.000 $140.680 $151.000 $156.000 $156.440 $140.000 $170.000
RIPRAP (CONC)(4 IN)
CY 364.000 $500.000 $500.000 $500.000 $304.350 $460.000 $470.000 $441.030 $355.000 $419.290
RIPRAP (CONC)(5 IN)
CY 131.000 $440.000 $500.000 $500.000 $311.820 $460.000 $470.000 $412.680 $380.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 35.000 $400.000 $525.000 $550.000 $450.000 $480.000 $630.000 $435.780 $630.000 $433.140
RAIL (TY SSTR)
LF 2,758.000 $45.000 $50.000 $57.000 $45.000 $52.000 $48.900 $47.250 $46.000 $43.160
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 96.000 $108.000 $130.000 $130.000 $103.860 $130.000 $146.000 $171.880 $132.000 $135.000
CONC BOX CULV (5 FT X 4 FT)
LF 224.000 $360.000 $400.000 $345.000 $292.330 $365.000 $420.000 $430.530 $405.000 $409.440
RC PIPE (CL III)(18 IN)
LF 391.000 $60.000 $65.000 $50.000 $57.340 $75.000 $72.200 $75.610 $98.000 $63.540
RC PIPE (CL III)(24 IN)
LF 3,927.000 $80.000 $70.000 $55.000 $47.570 $60.000 $82.200 $81.910 $71.000 $81.070
RC PIPE (CL III)(30 IN)
LF 894.000 $95.000 $85.000 $72.000 $62.740 $87.000 $105.000 $126.010 $110.000 $93.100
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 12.000 $4,000.000 $3,750.000 $3,900.000 $4,722.480 $3,000.000 $4,330.000 $4,200.290 $3,500.000 $3,983.760
INLET (COMPL)(PCO)(3FT)(NONE)
EA 3.000 $4,050.000 $3,800.000 $3,900.000 $3,030.010 $4,000.000 $5,100.000 $4,830.330 $4,400.000 $6,020.620
INLET (COMPL)(POD)(FG)(3FTX3FT)
EA 9.000 $4,000.000 $3,500.000 $3,800.000 $4,261.730 $5,700.000 $4,370.000 $6,090.420 $5,100.000 $5,161.180
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 6.000 $4,000.000 $3,800.000 $3,500.000 $3,456.600 $3,600.000 $4,470.000 $4,515.310 $3,700.000 $5,245.470
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $15,000.000 $30,000.000 $14,000.000 $16,275.080 $24,000.000 $10,600.000 $13,640.440 $21,000.000 $18,229.630
SET (TY I)(S= 5 FT)(HW= 6 FT)(6:1) (C)
EA 1.000 $10,000.000 $26,000.000 $12,123.000 $16,342.910 $21,000.000 $13,900.000 $15,215.550 $21,000.000 $20,429.630
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 1.000 $1,100.000 $1,100.000 $1,500.000 $1,147.840 $1,600.000 $1,680.000 $1,995.140 $1,300.000 $1,094.520
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 1.000 $1,500.000 $1,200.000 $1,800.000 $1,594.380 $1,800.000 $1,720.000 $1,995.140 $1,800.000 $1,586.350
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 3.000 $1,600.000 $1,900.000 $2,700.000 $1,942.020 $2,000.000 $1,820.000 $2,100.140 $1,900.000 $1,045.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,600.000 $1,900.000 $2,700.000 $1,708.220 $2,100.000 $1,820.000 $2,100.140 $1,900.000 $1,690.100
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $2,100.000 $2,500.000 $3,300.000 $2,198.590 $4,200.000 $2,480.000 $4,620.320 $5,100.000 $2,145.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 2.000 $2,300.000 $3,500.000 $4,400.000 $4,736.100 $4,500.000 $5,500.000 $4,620.320 $5,700.000 $2,963.820
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $2,000.000 $3,500.000 $5,400.000 $4,737.100 $4,800.000 $1,160.000 $4,620.320 $3,100.000 $2,367.780
REMOV STR (SET)
EA 5.000 $400.000 $800.000 $2,500.000 $427.550 $1,600.000 $450.000 $472.530 $250.000 $453.350
REMOV STR (PIPE)
LF 668.000 $14.000 $12.000 $20.000 $8.790 $14.000 $5.650 $26.250 $19.000 $16.910
REMOV STR (BOX CULVERT)
LF 155.000 $90.000 $50.000 $60.000 $27.820 $30.000 $8.850 $52.500 $57.000 $75.680
MOBILIZATION
LS 1.000 $744,522.190 $325,000.000 $400,000.000 $767,552.530 $710,000.000 $400,000.000 $600,239.890 $860,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $4,000.000 $7,750.000 $3,000.000 $3,342.550 $5,000.000 $5,500.000 $2,271.040 $8,000.000 $12,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 400.000 $28.000 $28.000 $26.000 $22.600 $24.000 $25.000 $32.460 $26.000 $32.460
ROCK FILTER DAMS (REMOVE)
LF 400.000 $10.000 $5.000 $9.000 $6.940 $7.000 $9.000 $12.950 $9.250 $12.950
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 50.000 $20.000 $35.000 $21.000 $31.020 $31.000 $20.000 $42.560 $21.000 $42.560
CONSTRUCTION EXITS (REMOVE)
SY 50.000 $9.000 $10.000 $2.000 $18.000 $18.000 $2.000 $8.620 $2.000 $8.620
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,070.000 $2.900 $4.000 $2.500 $2.000 $2.000 $2.150 $2.140 $2.200 $2.140
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,070.000 $0.800 $0.500 $1.000 $0.610 $0.600 $1.000 $0.460 $1.050 $0.460
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 2,750.000 $10.000 $2.000 $10.000 $1.060 $12.000 $6.000 $6.820 $6.000 $7.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 5,010.000 $20.000 $6.000 $11.000 $5.290 $11.000 $10.750 $8.970 $13.000 $15.000
PCTB FUR&INSTL(F-SHAPE OR SNGL SLP)TY1
LF 5,010.000 $40.000 $25.000 $35.000 $34.410 $25.000 $10.750 $20.770 $17.000 $38.000
PERM CTB (F-SHAPE) (TY 1)
LF 2,200.000 $73.000 $50.000 $100.000 $56.000 $60.000 $78.800 $58.800 $58.000 $68.500
COLORED TEXTURED CONC (5")
SY 712.000 $64.000 $75.000 $110.000 $48.980 $92.000 $90.800 $63.530 $85.000 $120.000
CONC CURB & GUTTER (TY II)
LF 2,500.000 $21.000 $20.000 $17.000 $30.900 $23.000 $15.000 $19.320 $20.000 $19.190
DRIVEWAYS (SURF TREAT)
SY 470.000 $28.000 $40.000 $21.000 $32.710 $42.000 $44.800 $48.180 $25.000 $20.290
RUMBLE STRIPS (CENTERLINE)
LF 4,550.000 $0.170 $0.800 $1.300 $0.220 $0.750 $0.800 $0.220 $0.780 $0.180
CONC DIRECTIONAL ISLAND
SY 340.000 $61.000 $65.000 $66.000 $37.540 $120.000 $82.100 $84.530 $70.000 $85.660
MTL W-BEAM GD FEN (TIM POST)
LF 700.000 $21.500 $25.000 $25.000 $24.600 $20.000 $25.250 $24.600 $25.000 $21.550
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,450.000 $1,250.000 $1,350.000 $1,301.760 $1,300.000 $1,340.000 $1,301.760 $1,300.000 $1,520.460
MTL BM GD FEN TRANS (NON - SYM)
EA 4.000 $1,200.000 $725.000 $800.000 $767.870 $700.000 $790.000 $767.870 $800.000 $1,392.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,650.000 $2,500.000 $2,950.000 $2,868.000 $2,400.000 $2,940.000 $2,868.000 $3,000.000 $2,623.500
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,400.000 $1,000.000 $1,300.000 $1,250.000 $1,000.000 $1,280.000 $1,250.000 $1,300.000 $2,623.500
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $760.000 $500.000 $800.000 $750.000 $500.000 $770.000 $750.000 $800.000 $661.220
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $19,000.000 $25,000.000 $22,000.000 $21,100.000 $23,000.000 $23,400.000 $21,100.000 $22,000.000 $18,209.080
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 2.000 $16,000.000 $25,000.000 $22,000.000 $21,100.000 $24,000.000 $22,700.000 $21,100.000 $22,000.000 $18,209.080
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $8,000.000 $8,500.000 $7,200.000 $7,000.000 $10,000.000 $8,200.000 $7,000.000 $7,200.000 $7,037.260
PIPE UNDERDRAINS (TY 6) (6")
LF 2,000.000 $8.500 $0.010 $25.000 $24.680 $26.000 $16.400 $17.480 $18.500 $18.270
RELOCATE RD IL ASM (SHOE-BASE)
EA 2.000 $5,000.000 $5,100.000 $5,200.000 $4,785.000 $5,000.000 $5,200.000 $4,785.000 $5,000.000 $2,100.000
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 4.000 $2,500.000 $1,700.000 $1,700.000 $1,590.000 $1,700.000 $1,730.000 $1,590.000 $1,700.000 $2,700.000
CONDT (PVC) (SCH 40) (2")
LF 140.000 $10.000 $16.000 $16.000 $14.850 $15.000 $16.200 $14.850 $16.000 $9.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 540.000 $30.000 $35.000 $35.000 $32.750 $33.000 $35.700 $32.750 $35.000 $23.000
CONDT (RM) (1")
LF 90.000 $1.300 $52.000 $53.000 $48.500 $50.000 $52.900 $48.500 $52.000 $26.000
ELEC CONDR (NO.12) BARE
LF 90.000 $1.200 $1.300 $1.500 $1.200 $1.200 $1.300 $1.200 $1.250 $1.000
ELEC CONDR (NO.12) INSULATED
LF 180.000 $1.200 $1.450 $1.500 $1.350 $1.400 $1.450 $1.350 $1.400 $1.000
ELEC CONDR (NO.8) BARE
LF 680.000 $1.300 $1.530 $1.600 $1.450 $1.500 $1.600 $1.450 $1.500 $1.250
ELEC CONDR (NO.8) INSULATED
LF 1,360.000 $1.350 $1.700 $1.700 $1.600 $1.650 $1.750 $1.600 $1.700 $1.500
GROUND BOX TY A (122311)W/APRON
EA 8.000 $990.000 $1,300.000 $1,300.000 $1,175.000 $1,200.000 $1,280.000 $1,175.000 $1,200.000 $950.000
REMOVE GROUND BOX
EA 3.000 $330.000 $310.000 $310.000 $290.000 $300.000 $320.000 $290.000 $300.000 $165.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 10.000 $535.000 $550.000 $550.000 $529.360 $600.000 $540.000 $529.360 $550.000 $550.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 13.000 $550.000 $600.000 $600.000 $589.350 $640.000 $600.000 $589.350 $620.000 $660.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 15.000 $550.000 $625.000 $625.000 $614.930 $680.000 $630.000 $614.930 $645.000 $710.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 7.000 $700.000 $675.000 $675.000 $666.990 $700.000 $680.000 $666.990 $700.000 $785.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 9.000 $730.000 $800.000 $800.000 $780.300 $900.000 $800.000 $780.300 $820.000 $785.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $800.000 $825.000 $825.000 $803.740 $930.000 $820.000 $803.740 $845.000 $825.000
IN SM RD SN SUP&AM TYS80(1)SA(U-EXAL)
EA 2.000 $950.000 $1,200.000 $1,200.000 $1,182.820 $1,300.000 $1,210.000 $1,182.820 $1,250.000 $1,190.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 4.000 $2,000.000 $2,750.000 $2,450.000 $2,400.000 $2,900.000 $2,570.000 $1,405.000 $2,700.000 $1,190.000
REMOVE SM RD SN SUP&AM
EA 31.000 $90.000 $85.000 $90.000 $85.930 $100.000 $88.100 $85.930 $90.000 $85.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 14.000 $50.000 $21.000 $20.000 $19.450 $22.000 $19.950 $19.450 $20.000 $33.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 14.000 $30.000 $17.000 $16.000 $15.500 $17.000 $15.900 $15.500 $16.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 31.000 $60.000 $50.000 $50.000 $47.950 $52.000 $49.200 $47.950 $50.000 $77.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
EA 22.000 $80.000 $50.000 $50.000 $47.950 $56.000 $49.200 $47.950 $50.000 $73.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 6.000 $70.000 $56.000 $55.000 $54.030 $60.000 $55.400 $54.030 $55.000 $70.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 12,000.000 $0.600 $0.560 $0.600 $0.550 $0.620 $0.550 $0.550 $0.580 $2.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 4,200.000 $0.600 $0.560 $0.600 $0.550 $0.950 $0.550 $0.550 $0.580 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,956.000 $0.800 $0.710 $0.750 $0.700 $0.900 $0.700 $0.700 $0.740 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 244.000 $7.500 $5.750 $6.250 $5.720 $7.500 $6.150 $5.720 $6.020 $6.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 74.000 $40.000 $33.000 $40.000 $32.000 $31.000 $38.950 $32.000 $33.600 $40.000
REFL PAV MRK TY I (W)(BIKE DOT)(100MIL)
EA 1,278.000 $4.000 $0.560 $1.100 $0.550 $3.100 $1.050 $0.550 $0.580 $1.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 388.000 $6.200 $5.750 $6.250 $5.720 $7.200 $6.150 $5.720 $6.020 $6.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 2,048.000 $0.350 $0.150 $0.200 $0.140 $0.220 $0.150 $0.140 $0.150 $1.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 15,927.000 $0.120 $0.150 $0.150 $0.140 $0.200 $0.150 $0.140 $0.150 $1.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 17,928.000 $0.140 $0.150 $0.150 $0.140 $0.200 $0.150 $0.140 $0.150 $1.000
PREFAB PAV MRK TY B (W)(BIKE ARROW)
EA 13.000 $193.400 $179.000 $465.000 $176.000 $110.000 $460.000 $176.000 $185.000 $100.000
PREFAB PAV MRK TY B (W)(BIKE SYMBOL)
EA 13.000 $228.800 $285.000 $465.000 $275.000 $155.000 $460.000 $275.000 $290.000 $200.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 35.000 $200.000 $200.000 $220.000 $199.000 $140.000 $216.000 $199.000 $210.000 $190.000
PREFAB PAV MRK TY C (W) (WORD)
EA 26.000 $240.000 $270.000 $220.000 $260.000 $130.000 $216.000 $260.000 $270.000 $235.000
REFL PAV MRKR TY I-C
EA 223.000 $3.400 $3.500 $4.500 $3.470 $3.500 $4.100 $3.470 $3.650 $350.000
REFL PAV MRKR TY II-A-A
EA 398.000 $3.300 $3.500 $4.500 $3.470 $3.600 $4.100 $3.470 $3.650 $350.000
ELIM EXT PAV MRK & MRKS (4")
LF 3,000.000 $0.300 $0.560 $1.000 $0.550 $1.900 $0.650 $0.550 $0.580 $0.340
REMOVAL OF GROUND BOXES
EA 1.000 $260.000 $310.000 $315.000 $290.000 $300.000 $320.000 $290.000 $305.000 $200.000
REMOVE TRAFFIC SIGNAL
EA 4.000 $1,000.000 $900.000 $900.000 $825.000 $840.000 $900.000 $825.000 $865.000 $6,500.000
D-GR HMA TY-B PG64-22
TON 7,306.000 $66.000 $73.000 $72.000 $70.000 $70.000 $72.700 $68.460 $73.000 $70.000
D-GR HMA TY-D PG76-22
TON 3,665.000 $76.000 $84.000 $82.000 $80.000 $82.000 $83.100 $81.240 $82.000 $80.000
TACK COAT
GAL 6,970.000 $3.000 $2.650 $2.600 $2.500 $2.500 $2.600 $3.170 $2.600 $2.500
UNDERSEAL COURSE
GAL 120.000 $3.000 $2.650 $2.600 $2.500 $5.000 $2.600 $6.480 $5.000 $2.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $10,000.000 $5,000.000 $500.000 $11,000.000 $9,800.000 $7,500.000 $8,000.000 $10,500.000
TMA (STATIONARY)
DAY 180.000 $190.000 $125.000 $180.000 $387.500 $150.000 $400.000 $150.000 $0.010 $180.000
TMA (MOBILE OPERATION)
DAY 60.000 $350.000 $200.000 $450.000 $680.110 $150.000 $400.000 $150.000 $785.000 $300.000
Totals: $8,296,923.050 $7,570,067.830 $7,994,999.950 $8,044,133.002 $8,297,229.150 $8,397,389.950 $8,520,534.235 $8,692,780.570 $10,709,264.758