Show Job Controls
Bid Cobra

WILLIAMSON FM 1660 (1566-02-028)

Items: 39

County: WILLIAMSON
Length: 0.0000 MILES
Highway: FM 1660
District: AUSTIN
Control Number: 1566-02-028
DBE Goal: 0.0%
Project: C 1566-2-28
Guaranty: $100,000.00
Time: 89 WORKING DAYS
Engineer's Estimate: $5,710,807.33
Date: 03/05/2025 (1 year ago)
Contract Number: 3253210
Type: PREVENTIVE MAINTENANCE
Project ID: A00209808
Project Description: FDR, LEVEL UP, BONDING COURSE AND TOM
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE RUSSELL
JEREMY MIKES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$5,710,807.33
$3,853,029.88
Over/Under Est: -32.53% -$1,857,777.45
Over/Under Est: -20.05% -$1,145,183.63
Amt Left: 18.49% $712,593.82
Over/Under Est: -18.34% -$1,047,496.45
Amt Left: 21.03% $810,281.00
Delta: -2.14% -$97,687.18
Over/Under Est: -12.34% -$704,807.93
Amt Left: 29.92% $1,152,969.52
Delta: -7.35% -$342,688.52
$6,525,635.10
Over/Under Est: 14.27% $814,827.77
Amt Left: 69.36% $2,672,605.22
Delta: -30.36% -$1,519,635.70
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 9.81% $377,982.23
Total: 9.81% $377,982.23

Bid Items & Bid Tabulations

39 Total 0 of 39
WILLIAMSON  |  FM 1660  |  AUSTIN  |  1566-02-028  |  03/05/2025  |  $5,710,807.33  |  C 1566-2-28  |  PREVENT MAINT  |  89 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
ALLEN KELLER COMPANY
BACKFILL (TY B)
STA 514.000 $191.130 $145.500 $150.000 $137.500 $337.000 $119.500
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 10,581.000 $135.000 $114.500 $120.000 $113.300 $131.000 $153.750
TOM-C PG76-22 SAC-B
TON 10,914.000 $169.000 $120.500 $133.000 $138.600 $144.310 $172.750
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 14,880.000 $40.000 $28.500 $38.000 $32.200 $41.120 $50.800
PLANE ASPH CONC PAV(1")
SY 193,015.000 $1.800 $0.690 $1.200 $1.320 $1.010 $1.250
MOBILIZATION
LS 1.000 $372,375.610 $34,075.000 $85,000.000 $359,008.410 $170,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $7,500.000 $2,800.000 $10,000.000 $4,190.720 $2,400.000 $57,780.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 360.000 $60.000 $15.000 $65.000 $151.110 $100.000 $122.750
TMA (STATIONARY)
DAY 180.000 $250.000 $15.000 $190.000 $302.230 $100.000 $155.750
TMA (MOBILE OPERATION)
DAY 24.000 $450.000 $15.000 $50.000 $755.570 $100.000 $1,560.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $8.400 $6.000 $12.000 $12.240 $12.000 $9.650
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $3.550 $3.000 $6.000 $8.250 $8.000 $12.050
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 3,806.000 $38.500 $21.750 $40.000 $15.400 $35.860 $72.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 640.000 $1.690 $1.000 $2.000 $1.630 $1.000 $1.550
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,280.000 $1.600 $1.000 $2.000 $1.630 $1.000 $1.550
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 115.000 $1.750 $1.600 $2.150 $1.600 $1.500 $1.600
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,224.000 $1.430 $0.700 $1.400 $0.700 $0.950 $0.700
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 268.000 $10.980 $6.710 $10.600 $6.710 $5.000 $6.700
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 9.000 $220.000 $160.000 $170.000 $160.000 $150.000 $160.250
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 5.000 $295.000 $250.000 $190.000 $250.000 $175.000 $250.500
REFL PAV MRK TY I (Y)24"(SLD)(090MIL)
LF 52.000 $12.200 $7.000 $10.550 $7.000 $5.000 $7.000
RE PM TY II (W) 6" (SLD)
LF 101,550.000 $0.370 $0.210 $0.190 $0.210 $0.400 $0.250
RE PM TY II (W) 8" (DOT)
LF 95.000 $4.750 $0.250 $0.860 $0.250 $0.500 $0.300
RE PM TY II (W) 8" (SLD)
LF 1,200.000 $0.660 $0.250 $0.460 $0.250 $0.500 $0.300
RE PM TY II (W) 24" (SLD)
LF 268.000 $3.980 $3.000 $3.050 $3.000 $2.500 $3.400
RE PM TY II (W) (ARROW)
EA 5.000 $88.900 $52.000 $80.000 $52.000 $75.000 $52.100
RE PM TY II (W) (WORD)
EA 5.000 $95.000 $70.000 $85.000 $70.000 $75.000 $70.100
RE PM TY II (Y) 6" (BRK)
LF 5,725.000 $0.600 $0.210 $0.280 $0.210 $0.500 $0.300
RE PM TY II (Y) 6" (SLD)
LF 84,550.000 $0.370 $0.210 $0.270 $0.210 $0.500 $0.300
RE PM TY II (Y) 24" (SLD)
LF 52.000 $1.750 $3.400 $3.100 $3.400 $2.500 $3.400
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 101,550.000 $1.230 $0.700 $0.850 $0.700 $0.950 $0.700
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 84,550.000 $1.320 $0.770 $0.850 $0.770 $0.950 $0.750
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 5,725.000 $1.330 $0.770 $0.880 $0.770 $0.950 $0.750
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 9,280.000 $5.000 $5.720 $5.000 $5.720 $5.000 $5.750
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 20,320.000 $5.000 $5.720 $5.000 $5.720 $5.000 $5.750
REFL PAV MRKR TY I-C
EA 63.000 $1.550 $5.200 $7.250 $5.200 $5.000 $5.200
REFL PAV MRKR TY II-A-A
EA 1,390.000 $1.550 $5.200 $5.750 $5.200 $5.000 $5.200
UNDERSEAL COURSE
GAL 38,614.000 $5.000 $3.150 $3.850 $3.850 $4.650 $6.200
BONDING COURSE
GAL 17,372.000 $4.200 $3.350 $4.500 $2.970 $4.000 $5.500
Totals: $5,710,807.330 $3,853,029.880 $4,565,623.700 $4,663,310.880 $5,005,999.400 $6,525,635.100
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $30,000.00
Total: $36,000.00