WICHITA US0082 (6304-34-001)

Items: 21

County: WICHITA
Length: N/A
Highway: US0082
District: WICHITA FALLS
Control Number: 6304-34-001
DBE Goal: N/A
Project: BPM - 630434001
Guaranty: N/A
Time: 75 W
Engineer's Estimate: $679,269.60
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$679,269.60
1
$589,293.70
Over/Under Est: -13.25% -$89,975.90
Over/Under Est: -4.89% -$33,205.70
Amt Left: 9.63% $56,770.20
Over/Under Est: 1.16% $7,849.35
Amt Left: 16.6% $97,825.25
Delta: -6.35% -$41,055.05
Over/Under Est: 11.91% $80,910.80
Amt Left: 29% $170,886.70
Delta: -10.63% -$73,061.45
Over/Under Est: 19.23% $130,601.90
Amt Left: 37.43% $220,577.80
Delta: -6.54% -$49,691.10

Bid Items & Bid Tabulations

21 Total 0 of 21
WICHITA  |  US0082  |  WICHITA FALLS  |  6304-34-001  |  01/05/2017  |  $679,269.60  |  BPM - 630434001  |  BRIDGE MAINT  |  75 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
RESTEK, INC.
SCR CIVIL CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
DRS CONSTRUCTION, INC.
SJ&J CONSTRUCTION, LLC
PREPARING ROW
STA 2.000 $5,000.000 $750.000 $1,000.000 $2,500.000 $2,000.000 $2,000.000
REMOVING CONC (RIPRAP)
SY 14.000 $25.000 $125.000 $75.000 $100.000 $50.000 $100.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 25.000 $25.000 $125.000 $80.000 $65.000 $25.000 $30.000
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 39.000 $400.000 $1,250.000 $1,000.000 $1,200.000 $400.000 $300.000
FLOWABLE BACKFILL
CY 20.000 $250.000 $350.000 $800.000 $350.000 $200.000 $250.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 13,287.000 $5.000 $4.750 $5.700 $5.000 $7.200 $6.500
CONC STR REPAIR (EPOXY MORTAR)
SF 5.000 $200.000 $250.000 $195.000 $210.000 $120.000 $250.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 60.000 $100.000 $75.000 $210.000 $240.000 $90.000 $60.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 15.000 $150.000 $250.000 $280.000 $600.000 $170.000 $200.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 385.000 $200.000 $125.000 $185.000 $160.000 $90.000 $120.000
CONC STR REPAIR (STANDARD)
SF 4.000 $300.000 $100.000 $185.000 $140.000 $140.000 $110.000
RIPRAP (CONC)(4 IN)
CY 7.000 $500.000 $500.000 $1,400.000 $800.000 $600.000 $1,200.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 460.000 $150.000 $195.000 $270.000 $320.000 $150.000 $165.000
CLEANING AND SEALING EXISTING JOINTS
LF 2,526.000 $35.000 $25.000 $26.000 $50.000 $20.000 $40.000
MOBILIZATION
LS 1.000 $59,933.600 $50,000.000 $64,000.000 $40,000.000 $75,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $9,000.000 $4,200.000 $4,000.000 $6,000.000 $6,000.000
DITCH CLEAN/RESHAPING(CU YD IN VEHICLE)
CY 25.000 $50.000 $150.000 $100.000 $120.000 $50.000 $40.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 136.000 $50.000 $60.000 $89.000 $95.000 $60.000 $60.000
CNC CRACK REPAIR (FLOOD)(GRAVITY)
SF 119,583.000 $2.000 $1.150 $1.000 $0.650 $3.000 $2.000
REP STL BRDG MEMB (ANCHOR BOLT NUT)
EA 20.000 $25.000 $150.000 $200.000 $1,200.000 $60.000 $50.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 75.000 $70.000 $150.000 $25.000 $260.000 $50.000 $100.000
Totals: $679,269.600 $589,293.700 $646,063.900 $687,118.950 $760,180.400 $809,871.500