PREPARING ROW
|
STA
|
8.000
|
$7,000.000
|
$10,000.000
|
$5,000.000
|
$3,692.640
|
$10,000.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
15,821.000
|
$15.000
|
$15.000
|
$20.000
|
$24.360
|
$10.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
1,618.400
|
$40.000
|
$40.000
|
$35.000
|
$10.060
|
$33.500
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
31,189.000
|
$20.000
|
$29.000
|
$51.000
|
$31.680
|
$32.000
|
|
|
BACKFILL (TY B)
|
STA
|
10.000
|
$250.000
|
$750.000
|
$350.000
|
$3,357.570
|
$845.000
|
|
|
BLADING
|
HR
|
100.000
|
$100.000
|
$175.000
|
$250.000
|
$464.080
|
$595.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
188,297.000
|
$0.200
|
$0.180
|
$0.120
|
$0.210
|
$0.110
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
94,149.000
|
$0.150
|
$0.150
|
$0.080
|
$0.220
|
$0.080
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
94,149.000
|
$0.150
|
$0.150
|
$0.110
|
$0.220
|
$0.110
|
|
|
VEGETATIVE WATERING
|
MG
|
1,650.000
|
$46.500
|
$5.000
|
$65.000
|
$251.380
|
$41.500
|
|
|
PROOF ROLLING
|
HR
|
100.000
|
$100.000
|
$150.000
|
$100.000
|
$161.060
|
$205.000
|
|
|
CEMENT
|
TON
|
2,365.000
|
$267.500
|
$300.000
|
$349.100
|
$392.500
|
$305.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
165,531.000
|
$3.000
|
$2.750
|
$7.250
|
$2.390
|
$6.100
|
|
|
PRIME COAT (MC-30)
|
GAL
|
41,400.000
|
$5.650
|
$6.000
|
$6.100
|
$5.740
|
$5.350
|
|
|
FLEX PAVEMENT STRUCTURE REPAIR (2-8")
|
SY
|
9,084.000
|
$55.000
|
$80.000
|
$80.000
|
$108.030
|
$99.000
|
|
|
PLANE ASPH CONC PAV (0"- 2 1/2")
|
SY
|
12,553.000
|
$3.250
|
$5.000
|
$4.000
|
$5.020
|
$10.500
|
|
|
CEM STABIL BKFL
|
CY
|
79.600
|
$500.000
|
$231.000
|
$257.400
|
$346.110
|
$245.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
90.000
|
$125.000
|
$47.000
|
$52.650
|
$70.800
|
$72.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
88.000
|
$6.500
|
$26.000
|
$29.250
|
$37.570
|
$28.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
3,007.000
|
$30.000
|
$42.000
|
$52.650
|
$60.110
|
$50.000
|
|
|
CL A CONC (PLUG)
|
EA
|
1.000
|
$4,000.000
|
$1,575.000
|
$1,755.000
|
$2,254.030
|
$1,700.000
|
|
|
CL B CONC (MISC)
|
CY
|
28.000
|
$1,000.000
|
$1,050.000
|
$1,170.000
|
$1,502.690
|
$1,100.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
100.100
|
$600.000
|
$630.000
|
$702.000
|
$901.620
|
$665.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
21.300
|
$125.000
|
$263.000
|
$292.500
|
$375.660
|
$280.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
150.000
|
$515.000
|
$735.000
|
$760.500
|
$1,051.880
|
$780.000
|
|
|
RAIL (TY T551)
|
LF
|
66.000
|
$100.000
|
$368.000
|
$409.500
|
$551.910
|
$390.000
|
|
|
RETROFIT RAIL (TY T551)
|
LF
|
744.000
|
$275.000
|
$368.000
|
$409.500
|
$495.350
|
$390.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
60.000
|
$330.000
|
$237.000
|
$292.500
|
$338.110
|
$280.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
119.000
|
$570.000
|
$368.000
|
$409.500
|
$525.940
|
$390.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
111.000
|
$790.000
|
$735.000
|
$854.100
|
$1,051.880
|
$810.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
|
LF
|
14.000
|
$690.000
|
$897.000
|
$1,000.350
|
$1,284.790
|
$950.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
|
LF
|
38.000
|
$990.000
|
$1,024.000
|
$1,140.750
|
$1,465.110
|
$1,100.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
|
LF
|
9.000
|
$1,041.000
|
$1,260.000
|
$1,404.000
|
$1,803.220
|
$1,300.000
|
|
|
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
|
LF
|
19.000
|
$1,215.000
|
$1,365.000
|
$1,521.000
|
$1,953.500
|
$1,400.000
|
|
|
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
|
LF
|
60.000
|
$1,108.000
|
$1,680.000
|
$2,047.500
|
$2,404.290
|
$1,900.000
|
|
|
CONC BOX CULV (8 FT X 7 FT)(EXTEND)
|
LF
|
15.000
|
$800.000
|
$1,890.000
|
$2,106.000
|
$2,704.840
|
$2,000.000
|
|
|
CONC BOX CULV (8 FT X 8 FT)(EXTEND)
|
LF
|
8.000
|
$1,425.000
|
$1,995.000
|
$2,223.000
|
$2,855.100
|
$2,100.000
|
|
|
CONC BOX CULV (10 FT X 5 FT)(EXTEND)
|
LF
|
17.000
|
$1,400.000
|
$1,995.000
|
$2,223.000
|
$2,855.100
|
$2,100.000
|
|
|
CONC BOX CULVERT (10 FT X 4 FT)(EXTEND)
|
LF
|
30.000
|
$2,750.000
|
$1,680.000
|
$1,872.000
|
$2,404.290
|
$1,800.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
480.000
|
$160.000
|
$74.000
|
$81.900
|
$105.190
|
$78.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
535.000
|
$175.000
|
$100.000
|
$111.150
|
$142.750
|
$105.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
117.000
|
$240.000
|
$137.000
|
$152.100
|
$195.360
|
$145.000
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
174.000
|
$230.000
|
$121.000
|
$134.110
|
$172.810
|
$130.000
|
|
|
HEADWALL (CH - FW - 0) (DIA= 24 IN)
|
EA
|
4.000
|
$10,000.000
|
$9,713.000
|
$10,822.500
|
$13,899.830
|
$10,500.000
|
|
|
WINGWALL (FW - 0) (HW=10 FT)
|
EA
|
2.000
|
$23,000.000
|
$29,400.000
|
$32,760.000
|
$42,075.170
|
$31,000.000
|
|
|
WINGWALL (FW - 0) (HW=3 FT)
|
EA
|
19.000
|
$8,200.000
|
$7,350.000
|
$8,775.000
|
$10,518.790
|
$8,300.000
|
|
|
WINGWALL (FW - 0) (HW=4 FT)
|
EA
|
2.000
|
$11,500.000
|
$10,763.000
|
$11,992.500
|
$15,402.520
|
$11,500.000
|
|
|
WINGWALL (FW - 0) (HW=6 FT)
|
EA
|
2.000
|
$31,200.000
|
$18,638.000
|
$20,767.500
|
$26,672.660
|
$19,500.000
|
|
|
WINGWALL (FW - 0) (HW=7 FT)
|
EA
|
1.000
|
$23,240.000
|
$26,250.000
|
$29,250.000
|
$37,567.110
|
$28,000.000
|
|
|
WINGWALL (FW - S) (HW=3 FT)
|
EA
|
1.000
|
$8,500.000
|
$7,613.000
|
$8,482.500
|
$10,894.460
|
$8,100.000
|
|
|
WINGWALL (FW - S) (HW=6 FT)
|
EA
|
1.000
|
$21,000.000
|
$23,625.000
|
$26,325.000
|
$33,810.400
|
$25,000.000
|
|
|
WINGWALL (PW - 2) (HW=4 FT)
|
EA
|
1.000
|
$17,000.000
|
$13,650.000
|
$15,210.000
|
$19,534.900
|
$14,500.000
|
|
|
WINGWALL (PW - 2) (HW=5 FT)
|
EA
|
2.000
|
$23,000.000
|
$20,475.000
|
$22,815.000
|
$29,302.350
|
$21,500.000
|
|
|
WINGWALL (PW - 2) (HW=7 FT)
|
EA
|
6.000
|
$31,000.000
|
$39,900.000
|
$47,092.500
|
$57,102.010
|
$44,500.000
|
|
|
WINGWALL (PW - 2) (HW=8 FT)
|
EA
|
1.000
|
$33,000.000
|
$54,338.000
|
$60,547.500
|
$77,763.920
|
$57,500.000
|
|
|
WINGWALL (PW - 2) (HW=9 FT)
|
EA
|
1.000
|
$34,000.000
|
$57,750.000
|
$66,690.000
|
$82,647.650
|
$63,500.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
1.000
|
$7,000.000
|
$11,130.000
|
$12,402.000
|
$15,928.460
|
$12,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
28.000
|
$3,100.000
|
$1,575.000
|
$1,755.000
|
$2,254.030
|
$1,700.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
28.000
|
$1,800.000
|
$2,100.000
|
$2,340.000
|
$3,005.370
|
$2,200.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$4,150.000
|
$3,413.000
|
$3,802.500
|
$4,883.720
|
$3,600.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
21.000
|
$1,700.000
|
$2,625.000
|
$5,000.000
|
$3,756.720
|
$5,600.000
|
|
|
REMOV STR (SET)
|
EA
|
14.000
|
$1,150.000
|
$525.000
|
$585.000
|
$751.340
|
$555.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
46.000
|
$1,100.000
|
$525.000
|
$1,170.000
|
$751.340
|
$1,100.000
|
|
|
REMOV STR (PIPE)
|
LF
|
491.000
|
$40.000
|
$16.000
|
$17.550
|
$22.540
|
$16.500
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
44.000
|
$141.000
|
$105.000
|
$117.000
|
$150.270
|
$110.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,746,317.920
|
$1,400,000.000
|
$1,100,000.000
|
$2,512,812.420
|
$2,750,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
35.000
|
$7,000.000
|
$8,050.000
|
$500.000
|
$35,000.000
|
$25,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
660.000
|
$40.000
|
$46.000
|
$20.000
|
$84.510
|
$51.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
660.000
|
$10.000
|
$16.000
|
$5.000
|
$31.360
|
$22.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
40,827.000
|
$2.300
|
$4.000
|
$3.740
|
$6.700
|
$3.550
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
40,827.000
|
$1.000
|
$0.550
|
$1.760
|
$2.180
|
$1.650
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
5,650.000
|
$4.400
|
$5.250
|
$5.970
|
$13.160
|
$5.650
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
5,650.000
|
$1.000
|
$0.550
|
$1.760
|
$2.610
|
$1.650
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
2.000
|
$5,000.000
|
$3,508.000
|
$5,265.000
|
$17,995.860
|
$8,500.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
500.000
|
$120.000
|
$105.000
|
$46.800
|
$155.970
|
$135.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$140.000
|
$175.000
|
$46.800
|
$110.590
|
$155.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,500.000
|
$8.000
|
$17.000
|
$29.250
|
$13.090
|
$37.500
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
120.000
|
$10.000
|
$35.000
|
$29.250
|
$14.220
|
$48.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
500.000
|
$74.000
|
$36.000
|
$23.400
|
$43.320
|
$33.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$190.000
|
$148.000
|
$23.400
|
$66.230
|
$45.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
2,330.000
|
$15.000
|
$85.000
|
$45.000
|
$91.760
|
$125.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
230.000
|
$90.000
|
$136.000
|
$152.100
|
$291.200
|
$210.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
856.000
|
$40.000
|
$90.000
|
$45.000
|
$89.590
|
$90.500
|
|
|
DRIVEWAYS (BASE)
|
SY
|
7,172.000
|
$20.000
|
$22.000
|
$33.000
|
$50.900
|
$34.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
148,323.000
|
$0.220
|
$0.310
|
$0.330
|
$0.100
|
$0.080
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
73,501.000
|
$0.250
|
$0.310
|
$0.330
|
$0.080
|
$0.070
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,000.000
|
$24.500
|
$27.000
|
$35.100
|
$41.950
|
$28.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
12.000
|
$2,000.000
|
$2,243.000
|
$2,925.000
|
$3,495.730
|
$2,300.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
2.000
|
$1,200.000
|
$1,300.000
|
$1,755.000
|
$2,097.440
|
$1,300.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
400.000
|
$5.000
|
$5.500
|
$4.680
|
$22.230
|
$5.550
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$300.000
|
$433.000
|
$468.000
|
$559.320
|
$445.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
16.000
|
$3,200.000
|
$3,243.000
|
$3,978.000
|
$4,754.190
|
$3,300.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
7.000
|
$1,000.000
|
$305.000
|
$468.000
|
$405.500
|
$320.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
32.000
|
$700.000
|
$672.000
|
$1,041.300
|
$894.910
|
$710.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
14.000
|
$852.500
|
$672.000
|
$1,070.550
|
$894.910
|
$710.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$750.000
|
$735.000
|
$1,140.750
|
$978.800
|
$780.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
|
EA
|
3.000
|
$1,000.000
|
$762.000
|
$1,579.500
|
$1,013.760
|
$805.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
13.000
|
$1,000.000
|
$856.000
|
$1,316.250
|
$1,139.610
|
$905.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
4.000
|
$1,200.000
|
$966.000
|
$1,444.950
|
$1,286.430
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
3.000
|
$1,500.000
|
$966.000
|
$1,462.500
|
$1,286.430
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
12.000
|
$1,452.000
|
$1,040.000
|
$1,579.500
|
$1,384.310
|
$1,100.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
51.000
|
$610.500
|
$473.000
|
$702.000
|
$629.230
|
$500.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
22.000
|
$2,750.000
|
$494.000
|
$819.000
|
$657.200
|
$520.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
109.000
|
$550.000
|
$105.000
|
$117.000
|
$139.830
|
$110.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
16.000
|
$24.200
|
$38.000
|
$35.100
|
$41.950
|
$39.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
32.000
|
$45.000
|
$45.000
|
$46.800
|
$55.930
|
$46.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
|
EA
|
186.000
|
$77.000
|
$68.000
|
$146.250
|
$90.890
|
$72.000
|
|
|
INSTL OM ASSN (OM-2Z)(WFLX)(WAP)
|
EA
|
49.000
|
$200.000
|
$100.000
|
$175.500
|
$209.740
|
$155.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
4,032.000
|
$1.250
|
$0.760
|
$1.760
|
$2.100
|
$1.650
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
2,000.000
|
$1.450
|
$0.760
|
$1.760
|
$2.100
|
$1.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
51.000
|
$1.600
|
$2.200
|
$1.200
|
$2.930
|
$1.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
7,465.000
|
$1.750
|
$0.850
|
$1.200
|
$2.930
|
$1.650
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
682.000
|
$0.770
|
$2.350
|
$2.160
|
$2.590
|
$2.050
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
221.000
|
$7.000
|
$23.500
|
$9.240
|
$11.050
|
$8.800
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
255.000
|
$0.500
|
$0.810
|
$0.820
|
$0.980
|
$0.780
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
148,963.000
|
$0.500
|
$0.810
|
$0.820
|
$0.980
|
$0.780
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
11,074.000
|
$0.500
|
$0.810
|
$0.820
|
$0.980
|
$0.780
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
77,989.000
|
$0.500
|
$0.810
|
$0.820
|
$0.980
|
$0.780
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
4.000
|
$600.000
|
$1,051.000
|
$654.030
|
$781.640
|
$620.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
11.000
|
$5.000
|
$6.000
|
$5.850
|
$6.990
|
$5.550
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,546.000
|
$5.000
|
$5.250
|
$5.850
|
$6.990
|
$5.550
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
4,000.000
|
$0.580
|
$0.750
|
$2.340
|
$2.800
|
$2.200
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
52,123.000
|
$110.000
|
$116.000
|
$120.000
|
$140.190
|
$164.000
|
|
|
D-GR HMA TY-B PG64-22 (LEVEL-UP)
|
TON
|
2,303.000
|
$156.000
|
$155.000
|
$140.000
|
$127.790
|
$215.000
|
|
|
D-GR HMA TY-D PG70-28
|
TON
|
37,840.000
|
$120.000
|
$133.000
|
$126.000
|
$155.410
|
$168.000
|
|
|
BONDING COURSE
|
GAL
|
30,551.000
|
$3.800
|
$4.000
|
$6.150
|
$6.530
|
$2.200
|
|
|
TMA (STATIONARY)
|
DAY
|
500.000
|
$150.000
|
$165.000
|
$267.000
|
$663.690
|
$280.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
50.000
|
$195.000
|
$550.000
|
$1.000
|
$1,244.590
|
$1,100.000
|
|
Totals: |
$19,223,497.170
|
$20,570,032.280
|
$22,103,225.170
|
$27,699,120.830
|
$27,906,243.120
|