WHARTON VARIOUS (0913-09-132)
Items: 83
County: WHARTON
Length: 1.2660 MILES
Highway: VARIOUS
District: YOAKUM
Control Number: 0913-09-132
DBE Goal: 6.0%
Project: STP 2B24(465)TAPS
Guaranty: $51,000.00
Time: 158 WORKING DAYS
Engineer's Estimate: $2,558,830.58
Date: 06/05/2025 (1 year ago)
Contract Number: 6253225
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00206896
Contract Type: Federal
Project Description: THE PROJECT WILL CONSTRUCT MORE THAN 1-MILE OF 6-FOOT-WIDE SIDEWALKS WITHIN THE EXISTING RIGHT-OF-WAY. IT WILL REMOVE EXISTING SUBSTANDARD SIDEWALKS, ADA RAMPS AND DRIVEWAYS TO CONSTRUCT THE IMPROVED PEDESTRIAN PATWAYS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RYAN SIMPER
PAUL RODRIGUEZ
WHARTON VARIOUS (0913-09-132)
Project Name: N/A
Project: STP 2B24(465)TAPS
Length: 1.2660 MILES
Project Type: CONSTRUCTION
Limits From: FIRST ST/RAILROAD ST (ADJACENT TO SH 71)
Limits To: MAIN ST/NORTH LIBERTY ST (ON BU 59S)
Project Description: THE PROJECT WILL CONSTRUCT MORE THAN 1-MILE OF 6-FOOT-WIDE SIDEWALKS WITHIN THE EXISTING RIGHT-OF-WAY. IT WILL REMOVE EXISTING SUBSTANDARD SIDEWALKS, ADA RAMPS AND DRIVEWAYS TO CONSTRUCT THE IMPROVED PEDESTRIAN PATWAYS.
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,558,830.58 | |||
| $2,130,273.30 |
-16.75%
-$428,557.28
|
|||
| $2,142,703.83 |
-16.26%
-$416,126.75
|
0.58%
$12,430.53
|
||
| $2,205,475.00 |
-13.81%
-$353,355.58
|
3.53%
$75,201.70
|
-2.93%
-$62,771.17
|
|
| $2,573,813.97 |
0.59%
$14,983.39
|
20.82%
$443,540.67
|
-16.70%
-$368,338.97
|
|
| $2,737,621.50 |
6.99%
$178,790.92
|
28.51%
$607,348.20
|
-6.36%
-$163,807.53
|
|
| $3,182,905.00 |
24.39%
$624,074.42
|
49.41%
$1,052,631.70
|
-16.27%
-$445,283.50
|
E
Engineer's Estimate
$2,558,830.58
1
Awarded
$2,130,273.30
Over/Under Est:
-16.75%
-$428,557.28
$2,142,703.83
Over/Under Est:
-16.26%
-$416,126.75
Amt Left:
0.58%
$12,430.53
$2,205,475.00
Over/Under Est:
-13.81%
-$353,355.58
Amt Left:
3.53%
$75,201.70
Delta:
-2.93%
-$62,771.17
$2,573,813.97
Over/Under Est:
0.59%
$14,983.39
Amt Left:
20.82%
$443,540.67
Delta:
-16.70%
-$368,338.97
$2,737,621.50
Over/Under Est:
6.99%
$178,790.92
Amt Left:
28.51%
$607,348.20
Delta:
-6.36%
-$163,807.53
$3,182,905.00
Over/Under Est:
24.39%
$624,074.42
Amt Left:
49.41%
$1,052,631.70
Delta:
-16.27%
-$445,283.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| RAM-ROD CONCRETE COMPANY, INC. | 9.38% | $199,819.64 |
| THIRD COAST SERVICES LLC | 5.71% | $121,638.61 |
| SANTA FE CONCRETE SERVICES LLC | 3.11% | $66,251.50 |
| ROBIN STEEL LLC | 1.69% | $36,001.62 |
| CONCRETE CUTTING & BREAKING COMPANY | 0.92% | $19,598.51 |
| SOUTH TEXAS TRAFFIC ALLIANCE INC. | 0.62% | $13,207.69 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 0.17% | $3,621.46 |
| Total: | 21.60% | $460,139.03 |
Bid Items & Bid Tabulations
83
Total
0 of 83
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $1,500.00 |