WHARTON CR (0913-09-065)

Items: 36

County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-065
DBE Goal: N/A
Project: BR 2014(682)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $316,096.00
Date: 08/08/2017 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$316,096.00
1
$320,804.30
Over/Under Est: 1.49% $4,708.30
Over/Under Est: 6.06% $19,141.15
Amt Left: 4.5% $14,432.85
Over/Under Est: 6.89% $21,779.29
Amt Left: 5.32% $17,070.99
Delta: -0.79% -$2,638.14
Over/Under Est: 8.6% $27,198.00
Amt Left: 7.01% $22,489.70
Delta: -1.60% -$5,418.71
$353,042.15
Over/Under Est: 11.69% $36,946.15
Amt Left: 10.05% $32,237.85
Delta: -2.84% -$9,748.15
Over/Under Est: 18.47% $58,380.60
Amt Left: 16.73% $53,672.30
Delta: -6.07% -$21,434.45
$388,126.26
Over/Under Est: 22.79% $72,030.26
Amt Left: 20.99% $67,321.96
Delta: -3.64% -$13,649.66
Over/Under Est: 29.61% $93,583.35
Amt Left: 27.7% $88,875.05
Delta: -5.55% -$21,553.09
Over/Under Est: 43.3% $136,865.30
Amt Left: 41.2% $132,157.00
Delta: -10.56% -$43,281.95
$469,829.95
Over/Under Est: 48.64% $153,733.95
Amt Left: 46.45% $149,025.65
Delta: -3.72% -$16,868.65

Bid Items & Bid Tabulations

36 Total 0 of 36
WHARTON  |  CR  |  YOAKUM  |  0913-09-065  |  08/08/2017  |  $316,096.00  |  BR 2014(682)  |  REPLACE BRIDGE AND APPROACHES  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
HILL COUNTRY BRIDGE, INC.
REXCO CONSTRUCTION SERVICES, INC.
CONSTAR CONSTRUCTION
TREVWAY, INC.
JOHN REED AND COMPANY, LLC
SB CONTRACTORS LLC
ISI CONTRACTING, INC.
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
TMES LLC
PREPARING ROW
STA 3.400 $3,000.000 $1,500.000 $2,755.000 $2,900.000 $800.000 $1,400.000 $6,000.000 $5,000.000 $3,800.000 $2,100.000 $2,500.000
EXCAVATION (ROADWAY)
CY 30.000 $20.000 $100.000 $25.000 $100.000 $27.000 $50.000 $80.000 $20.000 $50.000 $115.000 $50.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 325.000 $25.000 $50.000 $27.600 $36.700 $30.000 $25.000 $60.000 $35.000 $36.000 $65.000 $43.600
BLADING
HR 10.000 $100.000 $200.000 $115.000 $90.000 $100.000 $50.000 $20.000 $85.000 $100.000 $130.000 $75.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 670.000 $2.000 $1.800 $3.750 $1.580 $2.000 $1.000 $0.100 $2.000 $1.100 $2.000 $2.250
CELL FBR MLCH SEED(TEMP)(WARM)
SY 168.000 $3.000 $1.800 $4.600 $1.580 $2.000 $2.000 $0.100 $5.000 $1.100 $7.300 $0.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 168.000 $3.000 $1.800 $4.600 $1.580 $2.000 $2.000 $0.100 $5.000 $1.100 $7.300 $8.130
VEGETATIVE WATERING
MG 3.000 $100.000 $85.000 $250.000 $250.000 $180.000 $100.000 $20.000 $65.000 $25.000 $110.000 $125.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 180.000 $100.000 $120.000 $128.350 $138.360 $130.000 $129.000 $120.000 $115.000 $115.000 $170.000 $107.590
DRILL SHAFT (24 IN)
LF 270.000 $200.000 $125.000 $206.000 $183.000 $250.000 $275.000 $230.000 $250.000 $325.000 $260.000 $282.340
CL C CONC (ABUT)
CY 24.000 $900.000 $800.000 $785.000 $877.930 $1,000.000 $585.000 $1,250.000 $1,100.000 $1,100.000 $1,100.000 $900.000
REINF CONC SLAB
SF 1,607.000 $15.000 $22.000 $19.750 $21.980 $16.000 $25.000 $14.000 $17.000 $24.000 $23.000 $19.000
PRESTR CONC SLAB BEAM (4SB15)
LF 396.000 $140.000 $146.000 $132.600 $129.900 $164.000 $160.000 $186.000 $140.000 $138.000 $170.000 $163.210
RIPRAP (STONE PROTECTION)(18 IN)
CY 156.000 $150.000 $170.000 $151.450 $138.150 $170.000 $150.000 $120.000 $210.000 $130.000 $190.000 $325.180
RAIL (TY T223)
LF 124.000 $100.000 $110.000 $98.500 $163.160 $140.000 $113.000 $60.000 $115.000 $89.000 $170.000 $150.000
ARMOR JOINT (SEALED)
LF 56.000 $75.000 $65.000 $62.800 $76.610 $56.000 $70.000 $60.000 $75.000 $69.000 $130.000 $96.920
RC PIPE (CL III)(15 IN)
LF 46.000 $50.000 $51.000 $43.250 $52.160 $35.000 $50.220 $50.000 $85.000 $52.000 $130.000 $75.000
RC PIPE (CL III)(18 IN)
LF 42.000 $60.000 $55.000 $46.350 $57.200 $40.000 $57.410 $55.000 $85.000 $59.000 $140.000 $85.000
SET (TY II) (15 IN) (RCP) (3: 1) (P)
EA 1.000 $400.000 $400.000 $864.000 $1,002.300 $1,000.000 $1,834.350 $500.000 $1,500.000 $1,000.000 $1,400.000 $2,500.000
SET (TY II) (15 IN) (RCP) (6: 1) (P)
EA 1.000 $600.000 $600.000 $1,465.000 $1,452.750 $1,200.000 $1,609.460 $600.000 $1,500.000 $1,000.000 $1,900.000 $2,500.000
SET (TY II) (18 IN) (RCP) (3: 1) (P)
EA 1.000 $800.000 $800.000 $1,010.000 $1,195.500 $1,300.000 $1,828.000 $700.000 $1,500.000 $1,000.000 $1,600.000 $3,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 1.000 $1,000.000 $1,100.000 $1,580.000 $1,231.200 $1,400.000 $1,713.000 $800.000 $1,500.000 $1,100.000 $2,300.000 $3,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $15,000.000 $20,500.000 $6,800.000 $10,000.000 $20,000.000 $28,000.000 $11,012.010 $32,000.000 $19,600.000 $14,500.000
REMOV STR (DRIVEWAY CULVERT)
EA 2.000 $500.000 $250.000 $530.000 $750.000 $1,000.000 $500.000 $500.000 $750.000 $1,400.000 $1,200.000 $1,000.000
MOBILIZATION
LS 1.000 $28,000.000 $30,000.000 $33,400.000 $36,000.000 $20,000.000 $35,000.000 $35,000.000 $38,500.000 $39,000.000 $44,000.000 $85,549.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $2,000.000 $2,080.000 $1,286.250 $1,000.000 $600.000 $1,000.000 $5,000.000 $1,100.000 $4,500.000 $2,267.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 695.000 $3.500 $4.000 $2.000 $4.730 $5.000 $2.000 $3.000 $4.000 $4.500 $3.700 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 695.000 $1.500 $1.500 $1.000 $1.050 $3.000 $1.000 $1.000 $1.000 $2.750 $1.700 $2.000
DRIVEWAYS (BASE)
SY 120.000 $25.000 $25.000 $36.450 $29.000 $50.000 $26.000 $22.000 $40.000 $105.000 $31.500 $35.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,000.000 $1,000.000 $745.000 $1,286.250 $1,500.000 $315.000 $900.000 $890.000 $1,000.000 $1,000.000 $1,625.000
SHORT RADIUS
LF 25.000 $30.000 $30.000 $25.600 $42.000 $40.000 $32.000 $36.000 $69.450 $50.000 $87.000 $47.500
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $650.000 $750.000 $500.000 $997.500 $700.000 $1,262.000 $850.000 $625.000 $750.000 $1,100.000 $775.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,200.000 $2,400.000 $2,025.000 $2,467.500 $3,300.000 $420.000 $2,100.000 $2,530.000 $2,400.000 $2,700.000 $2,750.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $20.000 $20.000 $15.000 $28.880 $50.000 $20.000 $10.000 $15.000 $6.000 $28.000 $25.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 3.000 $21.000 $20.000 $15.000 $28.880 $50.000 $25.000 $10.000 $15.000 $15.000 $31.500 $25.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 2.000 $50.000 $55.000 $50.000 $73.500 $45.000 $25.000 $36.000 $47.000 $21.000 $56.000 $93.750
Totals: $316,096.000 $320,804.300 $335,237.150 $337,875.290 $343,294.000 $353,042.150 $374,476.600 $388,126.260 $409,679.350 $452,961.300 $469,829.950