WHARTON CR (0913-09-059)
Items: 40
County: WHARTON
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-09-059
DBE Goal: N/A
Project: BR 2012(412)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $775,371.00
Date: 04/04/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$775,371.00 | |||
| $746,501.30 |
-3.72%
-$28,869.70
|
|||
| $774,426.26 |
-0.12%
-$944.74
|
3.74%
$27,924.96
|
||
| $813,995.33 |
4.98%
$38,624.33
|
9.04%
$67,494.03
|
-5.11%
-$39,569.07
|
|
| $826,148.49 |
6.55%
$50,777.49
|
10.67%
$79,647.19
|
-1.49%
-$12,153.16
|
|
| $838,897.00 |
8.19%
$63,526.00
|
12.38%
$92,395.70
|
-1.54%
-$12,748.51
|
|
| $892,819.55 |
15.15%
$117,448.55
|
19.6%
$146,318.25
|
-6.43%
-$53,922.55
|
|
| $1,074,437.76 |
38.57%
$299,066.76
|
43.93%
$327,936.46
|
-20.34%
-$181,618.21
|
E
Engineer's Estimate
$775,371.00
1
Awarded
$746,501.30
Over/Under Est:
-3.72%
-$28,869.70
$774,426.26
Over/Under Est:
-0.12%
-$944.74
Amt Left:
3.74%
$27,924.96
$813,995.33
Over/Under Est:
4.98%
$38,624.33
Amt Left:
9.04%
$67,494.03
Delta:
-5.11%
-$39,569.07
$826,148.49
Over/Under Est:
6.55%
$50,777.49
Amt Left:
10.67%
$79,647.19
Delta:
-1.49%
-$12,153.16
$838,897.00
Over/Under Est:
8.19%
$63,526.00
Amt Left:
12.38%
$92,395.70
Delta:
-1.54%
-$12,748.51
Over/Under Est:
15.15%
$117,448.55
Amt Left:
19.6%
$146,318.25
Delta:
-6.43%
-$53,922.55
$1,074,437.76
Over/Under Est:
38.57%
$299,066.76
Amt Left:
43.93%
$327,936.46
Delta:
-20.34%
-$181,618.21
Bid Items & Bid Tabulations
40
Total
0 of 40