WHARTON US 59 (0089-07-156)
Items: 13
County: WHARTON
Length: N/A
Highway: US 59
District: YOAKUM
Control Number: 0089-07-156
DBE Goal: N/A
Project: C 89-7-156
Guaranty: N/A
Time: 30 WORKING DAYS
Engineer's Estimate: $295,465.00
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: SLOPE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$295,465.00 | |||
| $286,694.00 |
-2.97%
-$8,771.00
|
|||
| $315,780.00 |
6.88%
$20,315.00
|
10.15%
$29,086.00
|
||
| $358,775.98 |
21.43%
$63,310.98
|
25.14%
$72,081.98
|
-13.62%
-$42,995.98
|
|
| $376,292.50 |
27.36%
$80,827.50
|
31.25%
$89,598.50
|
-4.88%
-$17,516.52
|
|
|
5
|
$378,077.50 |
27.96%
$82,612.50
|
31.87%
$91,383.50
|
-0.47%
-$1,785.00
|
| $387,387.50 |
31.11%
$91,922.50
|
35.12%
$100,693.50
|
-2.46%
-$9,310.00
|
|
| $394,565.00 |
33.54%
$99,100.00
|
37.63%
$107,871.00
|
-1.85%
-$7,177.50
|
|
| $491,938.75 |
66.5%
$196,473.75
|
71.59%
$205,244.75
|
-24.68%
-$97,373.75
|
E
Engineer's Estimate
$295,465.00
1
Awarded
$286,694.00
Over/Under Est:
-2.97%
-$8,771.00
$315,780.00
Over/Under Est:
6.88%
$20,315.00
Amt Left:
10.15%
$29,086.00
$358,775.98
Over/Under Est:
21.43%
$63,310.98
Amt Left:
25.14%
$72,081.98
Delta:
-13.62%
-$42,995.98
$376,292.50
Over/Under Est:
27.36%
$80,827.50
Amt Left:
31.25%
$89,598.50
Delta:
-4.88%
-$17,516.52
5
$378,077.50
Over/Under Est:
27.96%
$82,612.50
Amt Left:
31.87%
$91,383.50
Delta:
-0.47%
-$1,785.00
$387,387.50
Over/Under Est:
31.11%
$91,922.50
Amt Left:
35.12%
$100,693.50
Delta:
-2.46%
-$9,310.00
$394,565.00
Over/Under Est:
33.54%
$99,100.00
Amt Left:
37.63%
$107,871.00
Delta:
-1.85%
-$7,177.50
$491,938.75
Over/Under Est:
66.5%
$196,473.75
Amt Left:
71.59%
$205,244.75
Delta:
-24.68%
-$97,373.75
Bid Items & Bid Tabulations
13
Total