WEBB VA (0922-00-075)
Items: 52
County: WEBB
Length: N/A
Highway: VA
District: LAREDO
Control Number: 0922-00-075
DBE Goal: 0.0%
Project: C 922-00-75
Guaranty: N/A
Time: 480 WORKING DAYS
Engineer's Estimate: $3,104,310.78
Date: 04/04/2024 (2 years ago)
Contract Number: N/A
Type: REMOVE/REPLACE BRIDGE RAIL
Mail/Deliver Bids To: N/A
ROGELIO CHAPA
ANGEL MARTINEZ
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,104,310.78 | |||
| $3,357,098.75 |
8.14%
$252,787.97
|
|||
| $3,473,362.30 |
11.89%
$369,051.52
|
3.46%
$116,263.55
|
||
| $3,650,517.50 |
17.6%
$546,206.72
|
8.74%
$293,418.75
|
-5.10%
-$177,155.20
|
|
| $5,567,597.00 |
79.35%
$2,463,286.22
|
65.85%
$2,210,498.25
|
-52.52%
-$1,917,079.50
|
E
Engineer's Estimate
$3,104,310.78
1
Awarded
$3,357,098.75
Over/Under Est:
8.14%
$252,787.97
$3,473,362.30
Over/Under Est:
11.89%
$369,051.52
Amt Left:
3.46%
$116,263.55
$3,650,517.50
Over/Under Est:
17.6%
$546,206.72
Amt Left:
8.74%
$293,418.75
Delta:
-5.10%
-$177,155.20
$5,567,597.00
Over/Under Est:
79.35%
$2,463,286.22
Amt Left:
65.85%
$2,210,498.25
Delta:
-52.52%
-$1,917,079.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| RC CONTRACT SERVICES LLC | 17.24% | $578,763.82 |
| BUYERS BARRICADES SAN ANTONIO, LLC | 2.57% | $86,277.44 |
| Total: | 19.81% | $665,041.26 |
Bid Items & Bid Tabulations
52
Total
0 of 52