WEBB IH 35 (0018-06-181)

Items: 58

County: WEBB
Length: 8.2560 MILES
Highway: IH 35
District: LAREDO
Control Number: 0018-06-181
DBE Goal: 0.0%
Project: C 18-6-181
Guaranty: $100,000.00
Time: 109 WORKING DAYS
Engineer's Estimate: $11,256,117.52
Date: 02/06/2025 (1 year ago)
Contract Number: 2253007
Type: OVERLAY
Project ID: A00067526
Project Description: RESURFACE OF EXISTING ROADWAY MILL/INLAY, SPOT BASE REPAIR, MBGF, PAVEMENT MARKING & ENTR/EXIT RAMPS, CONCRETE BARRIER REPAIR, REPLACE DMS
Mail/Deliver Bids To: N/A
JOSE VARGAS
MISAEL AGUILAR
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$11,256,117.52
$10,599,419.72
Over/Under Est: -5.83% -$656,697.80
Over/Under Est: -0.47% -$52,948.70
Amt Left: 5.7% $603,749.10
$12,035,478.64
Over/Under Est: 6.92% $779,361.12
Amt Left: 13.55% $1,436,058.92
Delta: -7.43% -$832,309.82
$12,096,656.50
Over/Under Est: 7.47% $840,538.98
Amt Left: 14.13% $1,497,236.78
Delta: -0.51% -$61,177.86
Subcontractor Percentage Amount
PERFORMANCE EQUIPMENT SERVICE 3.95% $421,615.67
DEPENDABLE FENCE 1.45% $154,770.31
HIGHWAY BARRICADES AND SERVICES, LLC 1.29% $137,692.21
TEXAS ICON CONSTRUCTION, LLC 0.54% $57,638.60
MOBILE ENTERPRISES, INC. 0.48% $51,234.31
CHEROKEE SERVICES 0.34% $36,290.97
TRAF-TEX, INC. 0.27% $28,819.30
PROFESSIONAL TRAFFIC CONTROL LLC 0.14% $14,943.34
Total: 8.46% $903,004.71

Bid Items & Bid Tabulations

58 Total 0 of 58
WEBB  |  IH 35  |  LAREDO  |  0018-06-181  |  02/06/2025  |  $11,256,117.52  |  C 18-6-181  |  OVERLAY  |  109 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
CK NEWBERRY, LLC
BACKFILL (TY B)
STA 377.950 $115.000 $174.000 $100.000 $151.000 $200.000
BLADING
HR 24.000 $180.000 $188.000 $170.000 $156.000 $175.000
FOG SEAL (CSS-1H)
GAL 44,550.000 $4.000 $0.500 $0.210 $2.920 $1.000
D-GR HMA TY-C SAC-A PG76-22
TON 12,924.000 $135.000 $125.000 $171.000 $136.400 $155.000
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
TON 24,757.000 $150.000 $154.000 $158.000 $182.100 $155.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 49,806.000 $45.000 $37.000 $44.500 $42.080 $49.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 13,015.000 $70.000 $60.000 $64.000 $72.060 $85.000
PLANE ASPH CONC PAV(2")
SY 19,476.000 $3.000 $2.800 $2.300 $2.440 $3.000
PLANE ASPH CONC PAV(3")
SY 122,748.000 $3.500 $3.800 $4.000 $3.540 $3.500
PLANE ASPH CONC PAV (2.5")
SY 32,779.000 $3.000 $2.700 $2.250 $3.540 $3.000
RIPRAP (MOW STRIP)(4 IN)
CY 102.000 $550.000 $740.000 $675.000 $728.990 $800.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,016.000 $30.000 $50.000 $45.000 $60.000 $65.000
MOBILIZATION
LS 1.000 $1,018,776.270 $912,000.000 $589,000.000 $1,077,431.430 $1,175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $8,500.000 $4,000.000 $1,800.000 $4,578.310 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $8,500.000 $7,000.000 $9,742.500 $15,000.000
TMA (STATIONARY)
DAY 86.000 $260.000 $230.000 $270.000 $270.620 $350.000
TMA (MOBILE OPERATION)
HR 200.000 $60.000 $770.000 $55.000 $108.250 $100.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 192.000 $85.000 $78.000 $70.000 $108.000 $60.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 72,880.000 $0.250 $0.120 $0.210 $0.210 $0.100
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 11,126.000 $0.250 $0.180 $0.860 $0.860 $0.100
MTL W-BEAM GD FEN (TIM POST)
LF 1,825.000 $32.000 $30.000 $28.500 $28.000 $23.000
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $60.000 $120.000 $100.000 $110.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 9.000 $2,000.000 $3,500.000 $3,250.000 $2,400.000 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 7.000 $1,750.000 $1,750.000 $1,350.000 $1,600.000 $1,500.000
MTL BM GD FEN TRANS (NON - SYM)
EA 7.000 $1,000.000 $1,250.000 $1,000.000 $1,150.000 $700.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 14.000 $800.000 $1,400.000 $600.000 $1,250.000 $1,100.000
REMOVE METAL BEAM GUARD FENCE
LF 1,825.000 $3.250 $3.000 $2.500 $3.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 7.000 $200.000 $325.000 $200.000 $300.000 $225.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 5.000 $150.000 $325.000 $200.000 $300.000 $225.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $3,200.000 $3,800.000 $3,000.000 $3,500.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 15.000 $260.000 $325.000 $200.000 $300.000 $225.000
ELEC CONDR (NO.6) BARE
LF 60.000 $2.300 $3.000 $7.500 $7.500 $2.500
ELEC CONDR (NO.6) INSULATED
LF 180.000 $2.350 $3.000 $7.500 $7.500 $3.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 60.000 $30.000 $27.000 $50.000 $25.000 $25.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 41.000 $18.000 $11.000 $50.000 $10.000 $50.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 8,018.000 $2.000 $2.200 $1.750 $1.630 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,762.000 $2.000 $2.200 $1.750 $1.630 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,205.000 $1.750 $0.960 $0.880 $0.880 $0.500
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,245.000 $2.500 $1.200 $1.100 $1.100 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 110.000 $10.000 $18.000 $16.000 $16.000 $5.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $200.000 $165.000 $150.000 $150.000 $200.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 9.000 $200.000 $275.000 $250.000 $250.000 $200.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 2.000 $600.000 $550.000 $500.000 $500.000 $500.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 360.000 $1.400 $1.200 $1.100 $1.100 $5.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 156.000 $7.000 $18.000 $16.000 $16.000 $10.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 16,206.000 $0.750 $0.850 $0.780 $0.780 $1.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 62,624.000 $0.750 $0.740 $0.680 $0.680 $0.250
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 46,432.000 $0.750 $0.740 $0.680 $0.680 $0.200
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 359.000 $3.500 $2.200 $2.000 $2.000 $50.000
REFL PAV MRKR TY I-C
EA 724.000 $5.000 $8.000 $7.500 $7.500 $10.000
REFL PAV MRKR TY II-A-A
EA 384.000 $5.500 $8.000 $7.500 $7.500 $10.000
REFL PAV MRKR TY II-C-R
EA 392.000 $6.000 $8.000 $7.500 $7.500 $10.000
PERM CONC TRF BARR REPAIR(SINGLE SLOPE)
LF 6.000 $2,500.000 $2,800.000 $2,000.000 $3,244.950 $1,000.000
BONDING COURSE
GAL 45,387.000 $4.000 $2.500 $3.850 $3.540 $4.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 1.000 $23,000.000 $18,000.000 $31,000.000 $31,000.000 $16,000.000
INSTALLATION OF CELLULAR MODEM
EA 1.000 $360.000 $1,200.000 $1,300.000 $1,300.000 $1,200.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $9,500.000 $12,000.000 $5,800.000 $12,990.000 $5,000.000
REMOVE DMS
EA 1.000 $3,000.000 $12,000.000 $11,900.000 $11,900.000 $12,000.000
Totals: $11,256,117.520 $10,599,419.720 $11,203,168.820 $12,035,478.640 $12,096,656.500