Show Job Controls
Bid Cobra

WALKER FM 2821 (2850-01-018)

Items: 92

County: WALKER
Length: N/A
Highway: FM 2821
District: BRYAN
Control Number: 2850-01-018
DBE Goal: N/A
Project: STP 2021(351)
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $2,215,967.25
Date: 02/05/2021 (5 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENTS, RT & LT TURN LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (10)
E
Engineer's Estimate
$2,215,967.25
$2,117,590.11
Over/Under Est: -4.44% -$98,377.14
Over/Under Est: -0.99% -$21,831.80
Amt Left: 3.61% $76,545.34
Over/Under Est: -0.46% -$10,267.22
Amt Left: 4.16% $88,109.92
Delta: -0.53% -$11,564.58
Over/Under Est: 2.61% $57,892.93
Amt Left: 7.38% $156,270.07
Delta: -3.09% -$68,160.15
Over/Under Est: 3.44% $76,317.42
Amt Left: 8.25% $174,694.56
Delta: -0.81% -$18,424.49
$2,382,048.90
Over/Under Est: 7.49% $166,081.65
Amt Left: 12.49% $264,458.79
Delta: -3.92% -$89,764.23
Over/Under Est: 10.93% $242,252.72
Amt Left: 16.09% $340,629.86
Delta: -3.20% -$76,171.07
$2,834,589.14
Over/Under Est: 27.92% $618,621.89
Amt Left: 33.86% $716,999.03
Delta: -15.31% -$376,369.17
Over/Under Est: 34.87% $772,809.65
Amt Left: 41.14% $871,186.79
Delta: -5.44% -$154,187.76
$2,995,461.20
Over/Under Est: 35.18% $779,493.95
Amt Left: 41.46% $877,871.09
Delta: -0.22% -$6,684.30

Bid Items & Bid Tabulations

92 Total 0 of 92
WALKER  |  FM 2821  |  BRYAN  |  2850-01-018  |  02/05/2021  |  $2,215,967.25  |  STP 2021(351)  |  INTERS IMPRVS, RT & LT TURN LANES  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VULCAN CONSTRUCTION
LARRY YOUNG PAVING, INC.
CORNERSTONE PAVING AND CONSTRUCTION LLC
BIG CREEK CONSTRUCTION, LTD.
ANGEL BROTHERS HOLDINGS CORP.
A. L. HELMCAMP, INC.
KNIFE RIVER CORPORATION - SOUTH
TRIPLE B SERVICES LLP
TEXCON GENERAL CONTRACTORS
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 34.200 $900.000 $1,137.530 $86.000 $100.000 $1,000.000 $1,000.000 $2,170.000 $839.000 $875.000 $395.000 $323.470
REMOVING STAB BASE AND ASPH PAV(15")
SY 2,164.000 $12.000 $14.580 $10.500 $8.600 $10.000 $10.000 $11.000 $9.500 $15.000 $14.300 $14.590
EXCAVATION (ROADWAY)
CY 2,005.000 $10.000 $8.350 $16.500 $10.800 $12.500 $13.000 $15.000 $7.500 $20.000 $5.000 $18.580
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,547.000 $11.000 $23.290 $19.000 $15.400 $12.500 $18.000 $13.000 $12.000 $19.000 $20.000 $18.330
COMPOST MANUF TOPSOIL (4")
SY 28,775.000 $2.000 $1.070 $0.950 $0.950 $2.000 $0.900 $1.000 $1.000 $1.250 $1.650 $0.980
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 28,775.000 $0.250 $0.200 $0.300 $0.180 $0.200 $0.150 $0.190 $0.190 $0.310 $0.200 $0.140
DRILL SEEDING (TEMP) (WARM)
SY 14,389.000 $0.250 $0.180 $0.250 $0.160 $0.160 $0.100 $0.170 $0.170 $0.310 $0.180 $0.130
DRILL SEEDING (TEMP) (COOL)
SY 14,389.000 $0.250 $0.180 $0.250 $0.160 $0.160 $0.100 $0.170 $0.170 $0.310 $0.180 $0.120
VEGETATIVE WATERING
MG 292.000 $40.000 $78.960 $39.500 $20.000 $15.000 $20.000 $20.000 $32.000 $20.000 $95.000 $25.880
FL BS (CMP IN PLC)(TY D GR1-2)(8")
SY 11,531.000 $13.000 $29.200 $18.000 $19.000 $16.500 $18.000 $21.000 $16.250 $20.000 $15.000 $23.340
CEMENT
TON 141.000 $160.000 $160.550 $190.000 $165.000 $170.000 $160.000 $155.000 $154.000 $165.000 $185.000 $200.040
CEMENT TREAT (SUBGRADE) (8")
SY 11,531.000 $3.000 $3.020 $2.000 $2.250 $2.000 $2.500 $3.000 $1.380 $3.500 $2.500 $6.780
PRIME COAT (AE-P)
GAL 2,309.000 $5.000 $2.630 $2.250 $3.000 $3.750 $5.000 $2.000 $3.650 $3.690 $6.000 $4.190
ASPH (RC-250)
GAL 8,561.000 $5.500 $3.660 $3.250 $4.500 $3.250 $3.000 $4.000 $3.650 $4.250 $6.000 $4.850
AGGR(TY-B GR-5 SAC-A)
CY 231.000 $167.000 $114.860 $100.000 $92.450 $110.000 $65.000 $205.000 $219.000 $136.290 $220.000 $102.370
PLANE ASPH CONC PAV(0" TO 2")
SY 19,032.000 $3.000 $2.050 $1.750 $0.800 $1.500 $2.000 $2.500 $1.470 $1.750 $2.500 $2.540
TEMPORARY SPL SHORING
SF 494.000 $50.000 $44.850 $19.000 $40.000 $40.000 $75.000 $63.000 $43.000 $62.000 $67.000 $19.460
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $200.000 $234.050 $200.000 $204.000 $210.000 $208.000 $215.000 $224.000 $237.080 $328.000 $261.130
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 28.000 $255.000 $308.270 $240.000 $245.000 $250.000 $275.000 $250.000 $295.700 $277.800 $460.000 $253.770
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 22.000 $375.000 $398.850 $320.000 $325.000 $350.000 $356.000 $340.000 $382.000 $371.670 $590.000 $394.140
CL C CONC (WINGWALLS)
CY 34.000 $1,200.000 $1,401.550 $650.000 $1,200.000 $1,300.000 $1,800.000 $1,600.000 $1,344.000 $1,826.850 $1,780.000 $1,339.630
RIPRAP (CONC)(5 IN)
CY 10.000 $530.000 $840.930 $540.000 $625.000 $425.000 $550.000 $890.000 $806.000 $932.610 $945.000 $437.780
RIPRAP (CONC) (CL B) (4")
CY 0.350 $600.000 $252.380 $2,600.000 $3,000.000 $750.000 $600.000 $1,000.000 $242.000 $1,145.560 $1,112.000 $393.380
RIPRAP (STONE TY R)(DRY)(18 IN)
CY 24.000 $225.000 $224.250 $160.000 $225.000 $90.000 $235.000 $230.000 $215.000 $256.620 $250.000 $186.320
RIPRAP (MOW STRIP)(4 IN)
CY 55.000 $500.000 $560.620 $320.000 $525.000 $410.000 $550.000 $680.000 $453.000 $488.560 $723.000 $352.110
CONC BOX CULV (10 FT X 10 FT)
LF 19.000 $1,100.000 $1,401.550 $1,400.000 $1,685.000 $1,600.000 $2,400.000 $1,500.000 $1,344.000 $1,755.840 $1,585.000 $923.320
RC PIPE (CL III)(24 IN)
LF 136.000 $75.000 $140.160 $69.000 $75.000 $75.000 $106.000 $135.000 $134.400 $103.000 $145.000 $52.400
RC PIPE (CL III)(30 IN)
LF 16.000 $125.000 $224.250 $80.000 $150.000 $110.000 $280.000 $235.000 $215.000 $235.000 $250.000 $69.870
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 6.000 $1,500.000 $1,121.240 $1,400.000 $1,800.000 $1,100.000 $1,700.000 $1,000.000 $1,075.000 $1,190.250 $1,112.000 $1,521.620
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $2,000.000 $2,803.110 $1,900.000 $2,500.000 $1,510.000 $2,350.000 $2,600.000 $2,690.000 $2,777.430 $2,780.000 $1,839.910
REMOV STR (SET)
EA 8.000 $550.000 $840.930 $480.000 $200.000 $330.000 $530.000 $785.000 $806.000 $633.520 $835.000 $599.320
REMOV STR (WINGWALL)
EA 2.000 $1,400.000 $1,681.860 $6,200.000 $800.000 $2,500.000 $1,500.000 $1,500.000 $1,600.000 $1,837.750 $1,670.000 $1,394.390
REMOV STR (PIPE)
LF 136.000 $14.000 $28.030 $22.000 $12.000 $14.000 $29.000 $30.000 $26.900 $19.000 $33.000 $14.560
MOBILIZATION
LS 1.000 $150,000.000 $25,460.060 $106,000.000 $45,000.000 $210,000.000 $175,000.000 $155,000.000 $176,000.000 $160,000.000 $121,420.000 $291,125.460
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $8,338.010 $15,000.000 $2,500.000 $5,000.000 $4,500.000 $8,700.000 $710.000 $2,500.000 $10,000.000 $15,526.690
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 441.000 $32.000 $33.640 $37.000 $30.000 $30.000 $30.000 $30.000 $32.260 $40.000 $33.000 $48.070
ROCK FILTER DAMS (REMOVE)
LF 441.000 $10.000 $11.210 $12.000 $10.000 $10.000 $10.000 $10.000 $10.750 $8.000 $11.150 $15.330
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 444.000 $25.000 $31.390 $31.000 $28.000 $30.000 $28.000 $15.000 $30.000 $25.000 $32.000 $39.900
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $7.000 $15.700 $9.000 $14.000 $15.000 $14.000 $2.000 $15.000 $10.000 $16.000 $11.610
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,348.000 $4.000 $3.080 $2.750 $2.750 $3.000 $2.750 $3.000 $3.000 $4.000 $3.000 $3.490
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,348.000 $1.750 $0.840 $0.750 $0.750 $1.000 $0.750 $0.750 $1.000 $1.000 $0.850 $0.980
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 8,030.000 $30.000 $6.810 $31.500 $57.700 $50.000 $40.000 $30.000 $59.480 $72.000 $64.000 $53.010
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 520.000 $35.000 $8.310 $31.000 $60.000 $50.000 $54.000 $30.000 $61.000 $72.000 $64.000 $39.200
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 8,030.000 $10.000 $6.810 $11.500 $10.000 $8.000 $5.000 $10.000 $11.500 $12.000 $10.000 $7.890
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 520.000 $10.000 $8.310 $11.000 $10.000 $8.000 $5.000 $10.000 $9.000 $12.000 $10.000 $10.790
DRIVEWAYS (CONC)
SY 444.000 $80.000 $134.550 $73.500 $85.000 $85.000 $105.000 $135.000 $113.000 $145.000 $144.000 $76.020
DRIVEWAYS (ACP)
SY 161.000 $60.000 $42.910 $39.000 $45.000 $32.000 $40.000 $85.000 $69.000 $66.190 $98.000 $45.180
RUMBLE STRIPS (SHOULDER)
LF 6,850.000 $5.000 $0.880 $0.550 $1.300 $1.000 $0.600 $1.000 $1.050 $2.270 $1.390 $1.040
MTL W-BEAM GD FEN (STEEL POST)
LF 805.000 $30.000 $23.270 $25.500 $21.000 $25.000 $22.000 $22.000 $23.120 $23.920 $58.000 $21.090
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $3.000 $2.240 $4.000 $2.000 $3.000 $2.000 $2.000 $2.150 $1.220 $9.300 $2.600
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,100.000 $2,724.620 $2,500.000 $2,430.000 $2,750.000 $2,600.000 $2,550.000 $2,715.000 $2,424.530 $4,610.000 $2,636.800
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $315.000 $224.250 $250.000 $200.000 $200.000 $150.000 $200.000 $161.000 $118.040 $1,060.000 $276.800
IN RD IL (TY ST) 40T-8 (250W EQ) LED
EA 1.000 $1,250.000 $3,960.550 $3,300.000 $3,350.000 $3,500.000 $3,600.000 $3,500.000 $3,798.000 $3,815.160 $5,900.000 $4,205.150
CONDT (PVC) (SCH 40) (2")
LF 165.000 $10.000 $11.540 $6.000 $6.000 $7.000 $11.000 $6.300 $11.060 $7.190 $17.050 $9.060
CONDT (PVC) (SCH 40) (2") (BORE)
LF 355.000 $24.000 $14.250 $15.500 $15.300 $16.000 $13.000 $16.000 $13.670 $17.130 $32.800 $28.470
CONDT (PVC) (SCH 40) (4")
LF 135.000 $16.000 $19.680 $9.250 $9.350 $10.000 $18.000 $9.750 $18.870 $11.340 $19.650 $12.940
CONDT (PVC) (SCH 40) (4") (BORE)
LF 235.000 $25.000 $25.100 $18.000 $18.250 $20.000 $23.000 $19.000 $24.070 $21.040 $39.300 $29.760
ELEC CONDR (NO.8) INSULATED
LF 1,605.000 $1.700 $1.730 $1.250 $1.250 $1.500 $1.600 $1.250 $1.660 $1.400 $2.650 $1.750
GROUND BOX TY D (162922)W/APRON
EA 5.000 $1,100.000 $919.100 $920.000 $925.000 $950.000 $820.000 $950.000 $881.000 $1,038.320 $1,510.000 $1,164.500
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $4,800.000 $4,724.620 $3,700.000 $3,680.000 $4,000.000 $4,300.000 $3,850.000 $4,531.000 $4,227.200 $7,210.000 $5,822.510
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 2.000 $400.000 $64.360 $75.000 $58.000 $150.000 $130.000 $160.000 $140.000 $90.050 $65.000 $258.780
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 6.000 $430.000 $468.610 $240.000 $420.000 $470.000 $470.000 $320.000 $500.000 $292.430 $500.000 $517.560
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $29.000 $30.000 $18.000 $28.500 $30.000 $28.000 $50.000 $31.000 $21.330 $94.000 $32.350
INSTL OM ASSM (OM-2Z)(FLX)SRF(BI)
EA 14.000 $100.000 $126.070 $42.000 $115.000 $110.000 $110.000 $100.000 $113.000 $53.230 $150.000 $122.920
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 6,130.000 $0.300 $0.310 $0.050 $0.060 $0.100 $0.060 $0.080 $0.060 $0.450 $0.310 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 9,450.000 $0.300 $0.310 $0.300 $0.240 $0.250 $0.250 $0.300 $0.260 $0.450 $0.310 $0.280
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 470.000 $1.500 $0.900 $0.600 $0.500 $0.500 $0.520 $0.630 $0.540 $0.450 $0.890 $2.720
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 3,390.000 $1.000 $0.900 $0.900 $0.750 $0.800 $0.800 $0.940 $0.810 $0.450 $0.890 $2.720
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $150.000 $185.010 $120.000 $100.000 $110.000 $105.000 $125.220 $108.000 $397.520 $161.000 $161.740
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 12.000 $150.000 $0.270 $150.000 $130.000 $140.000 $135.000 $162.790 $140.000 $397.520 $183.000 $161.740
REFL PAV MRK TY II (W) 4" (BRK)
LF 6,592.000 $0.750 $0.270 $0.050 $0.060 $0.100 $0.060 $0.080 $0.060 $0.450 $0.260 $0.280
REFL PAV MRK TY II (W) 4" (SLD)
LF 6,826.000 $0.500 $0.780 $0.250 $0.200 $0.250 $0.210 $0.250 $0.220 $0.450 $0.260 $0.280
REFL PAV MRK TY II (W) 8" (SLD)
LF 1,205.000 $1.000 $0.780 $0.700 $0.600 $0.600 $0.620 $0.750 $0.650 $0.680 $0.770 $0.630
REFL PAV MRK TY II (W) 24" (SLD)
LF 50.000 $4.000 $4.480 $3.500 $3.000 $3.000 $3.000 $3.760 $3.230 $3.410 $4.400 $6.150
REFL PAV MRK TY II (Y) 4" (BRK)
LF 2,312.000 $0.750 $0.270 $0.050 $0.060 $0.100 $0.060 $0.080 $0.060 $0.450 $0.260 $0.280
REFL PAV MRK TY II (Y) 4" (SLD)
LF 8,544.000 $0.750 $0.270 $0.200 $0.190 $0.200 $0.190 $0.240 $0.200 $0.450 $0.260 $0.280
REFL PAV MRKR TY II-A-A
EA 365.000 $3.500 $5.050 $4.500 $3.750 $4.000 $4.000 $0.470 $4.030 $3.980 $5.000 $7.760
TRAFFIC BUTTON TY I-C
EA 65.000 $6.000 $5.050 $8.250 $7.000 $7.000 $7.500 $8.770 $7.530 $3.980 $5.000 $9.700
ELIM EXT PAV MRK & MRKS (4")
LF 20,156.000 $0.500 $0.470 $0.250 $0.200 $0.250 $0.210 $0.250 $0.430 $0.170 $0.470 $0.300
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $25,000.000 $28,013.820 $22,000.000 $22,480.000 $24,000.000 $26,000.000 $24,000.000 $27,000.000 $25,765.730 $32,800.000 $34,935.060
VEH SIG SEC (12")LED(YEL)
EA 4.000 $165.000 $193.170 $230.000 $232.000 $250.000 $175.000 $250.000 $185.240 $258.580 $394.000 $271.720
VEH SIG SEC (12")LED(RED)
EA 4.000 $165.000 $193.170 $230.000 $232.000 $250.000 $175.000 $250.000 $185.240 $258.580 $394.000 $271.720
BACK PLATE (12")(1 SEC)
EA 8.000 $155.000 $64.280 $94.000 $94.000 $100.000 $60.000 $100.000 $61.640 $103.680 $132.000 $116.450
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 1,205.000 $1.700 $2.110 $1.750 $1.700 $2.000 $1.900 $1.800 $2.020 $1.950 $3.280 $1.750
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 1.000 $9,000.000 $9,870.020 $8,300.000 $8,330.000 $9,000.000 $9,000.000 $8,700.000 $9,500.000 $9,508.680 $13,115.000 $11,968.490
INS TRF SIG PL AM(S)1 ARM(44')LUM
EA 1.000 $8,000.000 $10,040.960 $8,500.000 $8,480.000 $9,000.000 $9,000.000 $8,900.000 $9,630.000 $9,679.440 $14,425.000 $10,609.910
INS TRF SIG PL AM(S)2 ARM(50 - 40')LUM
EA 1.000 $21,000.000 $27,393.200 $24,000.000 $23,850.000 $25,000.000 $25,000.000 $25,000.000 $26,300.000 $27,159.250 $27,735.000 $25,877.820
SP MIXES SP-B PG64-22
TON 3,025.000 $90.000 $88.120 $94.500 $83.000 $75.000 $89.000 $90.000 $82.680 $98.990 $113.000 $130.910
SP MIXES SP-D SAC-A PG70-22
TON 3,231.000 $90.000 $95.430 $100.000 $95.000 $84.000 $97.000 $102.000 $97.500 $105.290 $117.000 $140.440
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $3,363.730 $8,900.000 $8,000.000 $8,000.000 $5,000.000 $15,000.000 $8,900.000 $7,000.000 $3,000.000 $5,175.560
TMA (STATIONARY)
DAY 79.000 $180.000 $56.060 $260.000 $135.000 $170.000 $50.000 $150.000 $440.000 $210.000 $300.000 $194.080
TMA (MOBILE OPERATION)
DAY 79.000 $120.000 $270.890 $260.000 $135.000 $195.000 $50.000 $10.000 $376.000 $380.000 $1,280.000 $323.470
Totals: $2,215,967.250 $2,117,590.119 $2,194,135.450 $2,205,700.030 $2,273,860.180 $2,292,284.670 $2,382,048.900 $2,458,219.970 $2,834,589.146 $2,988,776.900 $2,995,461.207