Show Job Controls
Bid Cobra

VICTORIA US 87 (0089-19-017)

Items: 46

County: VICTORIA
Length: 3.2530 MILES
Highway: US 87
District: YOAKUM
Control Number: 0089-19-017
DBE Goal: 600.0%
Project: F 2B25(153)
Guaranty: $82,000.00
Time: 237 WORKING DAYS
Engineer's Estimate: $4,110,179.59
Date: 09/05/2025 (9 months ago)
Contract Number: 9253220
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00196303
Contract Type: Federal
Project Description: UPGRADE AND INSTALL SIDEWALKS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES JANAK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$4,110,179.59
$3,607,164.00
Over/Under Est: -12.24% -$503,015.59
Over/Under Est: -9.52% -$391,179.82
Amt Left: 3.1% $111,835.77
$3,795,520.50
Over/Under Est: -7.66% -$314,659.09
Amt Left: 5.22% $188,356.50
Delta: -2.06% -$76,520.73
Over/Under Est: -4.93% -$202,601.59
Amt Left: 8.33% $300,414.00
Delta: -2.95% -$112,057.50
$4,141,818.88
Over/Under Est: 0.77% $31,639.29
Amt Left: 14.82% $534,654.88
Delta: -5.99% -$234,240.88
Over/Under Est: 1.65% $67,943.41
Amt Left: 15.83% $570,959.00
Delta: -0.88% -$36,304.12
$4,206,842.10
Over/Under Est: 2.35% $96,662.51
Amt Left: 16.62% $599,678.10
Delta: -0.69% -$28,719.10
Over/Under Est: 6.79% $279,267.91
Amt Left: 21.69% $782,283.50
Delta: -4.34% -$182,605.40
Subcontractor Percentage Amount
STONE RIVER BRIDGE, LLC 44.00% $1,587,152.16
HIGHWAY BARRICADES AND SERVICES, LLC 2.01% $72,504.00
Total: 46.01% $1,659,656.16

Bid Items & Bid Tabulations

46 Total 0 of 46
VICTORIA  |  US 87  |  YOAKUM  |  0089-19-017  |  09/05/2025  |  $4,110,179.59  |  F 2B25(153)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  237 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ICOS MANAGEMENT, LLC
HUNTER INDUSTRIES, LTD.
STX CIVIL
TEXAS STEEL INDUSTRIAL PLACING, LLC
TI-ZACK CONCRETE, LLC
GARRET SHIELDS INFRASTRUCTURE
3LW CIVIL LLC
E-Z BEL CONSTRUCTION, LLC
PREPARING ROW
STA 12.000 $3,400.000 $2,000.000 $1,165.500 $5,000.000 $500.000 $812.500 $1,000.000 $3,500.000 $16,000.000
REMOV CONC (RIPRAP)
SY 29.000 $24.000 $200.000 $18.800 $10.000 $50.000 $30.660 $40.000 $36.000 $5.000
REMOV CONC (MEDIANS)
SY 183.000 $40.000 $80.000 $18.800 $10.000 $50.000 $24.300 $40.000 $30.000 $5.000
REMOV CONC (DRIVEWAYS)
SY 7,460.000 $24.000 $40.000 $16.400 $20.000 $20.000 $28.610 $20.000 $42.500 $5.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 7,474.000 $10.000 $40.000 $22.300 $20.000 $25.000 $9.150 $20.000 $24.000 $5.000
REMOV CONC (CURB & GUTTER)
LF 4,318.000 $25.000 $3.000 $10.500 $6.000 $9.000 $10.300 $10.000 $24.000 $5.000
RMV (0"-6") TRT/UNTRT BASE & ASPH PAV
SY 882.000 $22.000 $15.000 $9.400 $15.000 $25.000 $20.160 $10.000 $25.000 $11.000
EXCAV (ROADWAY)
CY 30.000 $30.000 $2,000.000 $77.000 $20.000 $40.000 $59.280 $50.000 $125.000 $27.000
EMBANK (FNL)(OC)(TY C)
CY 22.000 $34.000 $250.000 $101.200 $40.000 $50.000 $80.840 $100.000 $125.000 $24.000
BLOCK SODDING
SY 464.000 $10.000 $210.000 $26.180 $5.500 $5.000 $17.600 $12.000 $12.500 $8.000
VEGETATIVE WATERING
TGL 2.870 $64.000 $10,000.000 $24.390 $50.000 $100.000 $1.100 $500.000 $475.000 $50.000
D-GR HMA TY-B PG70-22
TON 102.000 $210.000 $300.000 $224.400 $145.000 $200.000 $285.000 $200.000 $350.000 $235.000
D-GR HMA TY-D SAC-B PG70-22
TON 21.000 $205.000 $600.000 $286.000 $180.000 $200.000 $313.500 $200.000 $350.000 $242.000
CUT & RESTORE ASPH PAVING
SY 3.000 $150.000 $2,100.000 $1,000.000 $300.000 $200.000 $296.400 $200.000 $1,062.000 $190.000
RIPRAP (CONC)(5 IN)
CY 4.000 $650.000 $1,200.000 $1,200.000 $650.000 $750.000 $807.430 $800.000 $1,062.000 $2,100.000
RAIL (HANDRAIL)(TY B)
LF 62.000 $250.000 $400.000 $225.000 $250.000 $200.000 $170.500 $200.000 $390.000 $94.000
ADJUSTING INLETS
EA 1.000 $4,000.000 $10,000.000 $2,750.000 $1,800.000 $2,800.000 $1,778.400 $2,000.000 $3,500.000 $1,500.000
REMOV STR (RET WALL)
LF 128.000 $110.000 $500.000 $28.000 $50.000 $60.000 $34.730 $100.000 $138.000 $20.000
MOBILIZATION
LS 1.000 $453,124.910 $350,000.000 $334,979.390 $350,000.000 $390,000.000 $417,136.690 $250,000.000 $347,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $7,000.000 $17,791.280 $2,000.000 $2,200.000 $1,650.000 $5,000.000 $3,968.750 $8,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $25,000.000 $5,250.740 $10,000.000 $30,000.000 $0.110 $1,000.000 $10,500.000 $6,700.000
TMA (STATIONARY)
DAY 80.000 $325.000 $1,000.000 $157.520 $130.000 $150.000 $0.110 $800.000 $125.000 $189.000
SANDBAGS FOR EROSION CONTROL
EA 30.000 $12.000 $40.000 $13.450 $0.100 $5.000 $0.110 $5.000 $0.100 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 400.000 $7.300 $3.000 $12.470 $0.100 $4.000 $0.110 $6.000 $0.100 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 400.000 $2.000 $1.000 $2.830 $0.100 $2.000 $0.110 $1.000 $0.100 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 400.000 $8.400 $20.000 $11.820 $0.100 $5.000 $0.110 $6.000 $0.100 $4.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 400.000 $3.000 $1.000 $2.830 $0.100 $2.000 $0.110 $1.000 $0.100 $1.000
CONC CURB & GUTTER (TY II)
LF 6,730.000 $50.000 $40.000 $28.000 $45.000 $55.000 $52.420 $40.000 $41.700 $34.000
CONC CURB (TY C1)
LF 197.000 $122.000 $220.000 $85.000 $80.000 $155.000 $140.260 $50.000 $110.000 $89.000
INTERSECTIONS (ACP)
SY 14.000 $135.000 $240.000 $69.000 $150.000 $200.000 $170.500 $120.000 $350.000 $39.000
DRIVEWAYS (CONC)
SY 8,479.000 $140.000 $40.000 $100.000 $120.000 $100.000 $129.280 $120.000 $132.000 $130.000
CONC SIDEWALKS (5")
SY 13,010.000 $90.000 $45.000 $95.000 $100.000 $100.000 $116.340 $100.000 $95.000 $123.000
CONC SIDEWALKS (6")
SY 108.000 $105.000 $280.000 $125.000 $110.000 $100.000 $139.690 $100.000 $146.610 $145.000
CURB RAMPS (TY 1)
SY 239.000 $155.000 $60.000 $175.000 $150.000 $200.000 $139.690 $400.000 $160.230 $250.000
CURB RAMPS (TY 2)
SY 265.000 $155.000 $400.000 $175.000 $150.000 $200.000 $139.690 $400.000 $150.000 $250.000
CURB RAMPS (TY 3)
SY 88.000 $155.000 $400.000 $190.000 $150.000 $200.000 $139.690 $400.000 $150.000 $250.000
CURB RAMPS (TY 5)
SY 63.000 $155.000 $420.000 $120.000 $150.000 $200.000 $139.690 $400.000 $150.000 $250.000
CURB RAMPS (TY 7)
SY 389.000 $155.000 $400.000 $175.000 $150.000 $200.000 $139.690 $400.000 $176.000 $250.000
CURB RAMPS (TY 10)
SY 721.000 $155.000 $400.000 $175.000 $150.000 $200.000 $139.690 $400.000 $150.000 $325.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 27.000 $603.000 $1,200.000 $500.000 $500.000 $500.000 $495.000 $350.000 $650.000 $500.000
RE PM TY II (W) 6" (BRK)
LF 42.000 $1.000 $80.000 $7.500 $3.000 $7.500 $1.760 $25.000 $12.000 $2.000
RE PM TY II (W) 6" (SLD)
LF 128.000 $1.000 $80.000 $7.500 $3.000 $7.500 $1.760 $14.000 $12.000 $2.000
RE PM TY II (W) 12" (SLD)
LF 175.000 $3.000 $150.000 $9.500 $5.000 $9.500 $6.600 $25.000 $24.000 $6.000
RE PM TY II (Y) 6" (SLD)
LF 183.000 $1.000 $80.000 $7.500 $3.000 $7.500 $1.760 $15.000 $12.000 $2.000
PREFAB PM TY C (W)(ARROW)
EA 2.000 $450.000 $1,000.000 $350.000 $350.000 $350.000 $308.000 $400.000 $420.000 $280.000
ELIM EXT PM & MRKS (8")
LF 224.000 $1.250 $25.000 $3.500 $5.000 $3.500 $3.080 $12.000 $12.000 $3.000
Totals: $4,110,179.590 $3,607,164.000 $3,718,999.769 $3,795,520.500 $3,907,578.000 $4,141,818.877 $4,178,123.000 $4,206,842.100 $4,389,447.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $17,208.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $18,708.00