Show Job Controls
Bid Cobra

VICTORIA BU 59-T (0089-19-011)

Items: 55

County: VICTORIA
Length: N/A
Highway: BU 59-T
District: YOAKUM
Control Number: 0089-19-011
DBE Goal: N/A
Project: NH 2020(043)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $3,570,484.64
Date: 09/06/2019 (6 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$3,570,484.64
$3,807,959.03
Over/Under Est: 6.65% $237,474.39
Over/Under Est: 59.47% $2,123,194.26
Amt Left: 49.52% $1,885,719.87

Bid Items & Bid Tabulations

55 Total 0 of 55
VICTORIA  |  BU 59-T  |  YOAKUM  |  0089-19-011  |  09/06/2019  |  $3,570,484.64  |  NH 2020(043)  |  MILL AND INLAY  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
BACKFILL (TY B)
STA 101.100 $110.000 $111.760 $175.000
BLADING
HR 20.000 $100.000 $96.900 $121.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 149.000 $90.000 $121.510 $121.000
AGGR(TY-PE GR-4 SAC-B)
CY 1,716.000 $80.000 $90.400 $100.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 75,803.000 $3.200 $3.200 $5.000
D-GR HMA TY-B PG64-22
TON 121.000 $125.000 $105.810 $115.000
D-GR HMA TY-D SAC-B PG76-22
TON 25,024.000 $75.000 $80.900 $133.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 5,000.000 $60.000 $41.140 $55.000
PLANE ASPH CONC PAV (8")
SY 276.000 $12.000 $18.030 $28.000
PLANE ASPH CONC PAV (2")
SY 222,950.000 $1.000 $1.490 $2.700
CLEANING AND SEALING EXISTING JOINTS
LF 168.000 $45.000 $45.000 $52.000
RETROFIT RAIL (TY SSTR)
LF 262.000 $180.000 $150.000 $360.000
HEADER TYPE EXPANSION JOINT
CF 37.300 $375.000 $525.000 $445.000
JOINT SEALANT
LF 168.000 $16.000 $15.000 $15.500
ADJUSTING MANHOLES
EA 5.000 $950.000 $1,100.000 $1,000.000
MOBILIZATION
LS 1.000 $325,000.000 $342,926.240 $361,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,500.000 $4,646.330 $1,600.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 540.000 $40.000 $30.000 $56.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 510.000 $10.000 $20.000 $15.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 540.000 $15.000 $30.000 $5.000
MTL W-BEAM GD FEN (TIM POST)
LF 675.000 $25.000 $23.700 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,900.000 $2,119.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 775.000 $2.000 $1.500 $1.500
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $2,945.000 $3,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $225.000 $200.000 $240.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,100.000 $1,500.000 $1,800.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $800.000 $1,000.000 $1,200.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,000.000 $7,000.000 $8,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 9.000 $25.000 $13.000 $16.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 28.000 $25.000 $16.950 $20.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 37,600.000 $0.200 $0.350 $0.400
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 41,400.000 $0.200 $0.350 $0.400
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 4,620.000 $0.500 $0.700 $0.800
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 22,618.000 $0.250 $0.350 $0.400
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 117,792.000 $0.250 $0.320 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,540.000 $1.250 $1.500 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 17,198.000 $1.250 $1.500 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 28.000 $0.630 $2.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,310.000 $0.740 $1.000 $1.000
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 200.000 $2.100 $3.000 $3.500
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 18,800.000 $0.400 $0.400 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 20,700.000 $0.400 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 11,309.000 $0.400 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 58,896.000 $0.400 $0.380 $0.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 1,120.000 $15.000 $14.000 $17.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $210.000 $195.000 $240.000
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $275.000 $275.000 $340.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 4.000 $600.000 $550.000 $680.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 412.000 $15.000 $15.000 $18.500
REFL PAV MRKR TY I-C
EA 940.000 $3.750 $4.000 $4.750
REFL PAV MRKR TY II-A-A
EA 1,386.000 $3.750 $3.750 $4.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $7,673.760 $8,750.000
LONG CHANNEL MOUNT CURB SYS (INSTALL)
LF 200.000 $65.000 $59.950 $75.000
TMA (STATIONARY)
EA 1.000 $8,000.000 $7,673.760 $6,200.000
TMA (MOBILE OPERATION)
DAY 20.000 $500.000 $255.790 $250.000
Totals: $3,570,484.640 $3,807,959.036 $5,693,678.900