TYLER US 190 (0213-06-041)

Items: 64

County: TYLER
Length: N/A
Highway: US 190
District: BEAUMONT
Control Number: 0213-06-041
DBE Goal: 550.0%
Project: NH 2013(561)
Guaranty: N/A
Time: 173 WORKING DAYS
Engineer's Estimate: $8,132,488.10
Date: 01/04/2024 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PASSING LANES
Mail/Deliver Bids To: N/A
DAVE COLLINS
RICHARD BRADLEY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$8,132,488.10
$9,062,104.57
Over/Under Est: 11.43% $929,616.47
$9,851,983.65
Over/Under Est: 21.14% $1,719,495.55
Amt Left: 8.72% $789,879.08
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 48.61% $4,401,526.94
AMERICAN REMEDIATION OPTIONS, INC. 4.12% $373,056.80
DREWERY CONSTRUCTION COMPANY, INCORPORATED 1.51% $136,727.13
STRIPING TECHNOLOGY, L.P. 1.45% $131,294.26
DREWERY BROS. TREE SERVICE, INC. 1.37% $124,050.44
A R BROTHERS CONSTRUCTION SERVICES, INC. 1.30% $117,712.10
PANOLA SIGN & BARRICADE, INC. 0.62% $56,139.62
WEST TEXAS ROCK RESOURCES, LLC 0.27% $24,447.90
CAP RIVER LLC 0.23% $20,825.99
CPAVE, INC. 0.04% $3,621.91
Total: 59.52% $5,389,403.09

Bid Items & Bid Tabulations

64 Total 0 of 64
TYLER  |  US 190  |  BEAUMONT  |  0213-06-041  |  01/04/2024  |  $8,132,488.10  |  NH 2013(561)  |  CONSTRUCT PASSING LANES  |  173 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PINTO CONSTRUCTION CO., INC.
A. L. HELMCAMP, INC.
PREPARING ROW
AC 18.730 $6,000.000 $20,228.300 $10,000.000
SUBGRADE WIDENING (ORD COMP)
STA 291.250 $500.000 $380.310 $500.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 10,714.000 $55.000 $21.420 $55.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,548.000 $59.000 $30.000 $75.000
BLADING
LF 508.000 $7.000 $5.230 $15.000
BROADCAST SEED (TEMP) (WARM)
SY 34,983.000 $0.350 $0.170 $0.210
BROADCAST SEED (TEMP) (COOL)
SY 34,983.000 $0.350 $0.170 $0.210
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 69,964.000 $1.000 $0.660 $0.230
VEGETATIVE WATERING
MG 82.000 $40.000 $0.010 $75.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
SY 29,125.000 $35.000 $64.920 $53.000
PRIME COAT (AE-P)
GAL 4,787.000 $4.500 $7.610 $10.000
PRIME COAT & BLOTTER (AE-P)
GAL 488.000 $6.000 $14.840 $15.000
ASPH (CRS-2P)
GAL 12,622.000 $5.500 $5.420 $5.000
AGGR(TY-PD GR-4 OR TY-PL GR-4)
CY 249.000 $185.000 $261.700 $300.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 6,953.000 $3.500 $7.080 $5.000
CL C CONC (COLLAR)
EA 1.000 $3,500.000 $1,100.000 $2,400.000
RIPRAP (MOW STRIP)(4 IN)
CY 80.000 $100.000 $1,200.000 $1,100.000
RC PIPE (CL III)(18 IN)
LF 42.000 $100.000 $104.500 $75.000
RC PIPE (CL III)(30 IN)
LF 4.000 $130.000 $514.800 $240.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $2,200.000 $1,848.000 $1,200.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $3,150.000 $3,520.000 $3,500.000
REMOV STR (SET)
EA 3.000 $650.000 $852.500 $1,400.000
REMOV STR (PIPE)
LF 42.000 $25.000 $66.000 $70.000
MOBILIZATION
LS 1.000 $800,000.000 $800,000.000 $950,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $10,000.000 $5,200.000 $12,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 500.000 $50.000 $52.800 $50.000
ROCK FILTER DAMS (REMOVE)
LF 500.000 $15.000 $13.200 $12.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 30,100.000 $10.000 $8.800 $8.250
BIODEG EROSN CONT LOGS (REMOVE)
LF 30,100.000 $2.000 $1.100 $1.250
DRIVEWAYS (ACP)
SY 1,953.000 $48.000 $48.870 $100.000
RUMBLE STRIPS (SHOULDER)
LF 52,760.000 $0.200 $0.310 $0.230
RUMBLE STRIPS (CENTERLINE)
LF 26,380.000 $0.200 $0.400 $0.270
MTL W-BEAM GD FEN (TIM POST)
LF 750.000 $36.000 $27.500 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,200.000 $2,678.500 $2,100.000
REMOVE METAL BEAM GUARD FENCE
LF 926.000 $10.000 $4.950 $2.750
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,200.000 $3,091.000 $3,775.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $220.000 $275.000 $325.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 13.000 $350.000 $242.000 $275.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $350.000 $297.000 $300.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $700.000 $632.500 $765.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 24.000 $630.000 $770.000 $690.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,000.000 $962.500 $815.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 4.000 $500.000 $550.000 $485.000
REMOVE SM RD SN SUP&AM
EA 17.000 $150.000 $110.000 $75.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 1.000 $50.000 $63.800 $225.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 31.000 $40.000 $49.500 $25.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 6,800.000 $1.000 $0.550 $0.630
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 58,900.000 $1.000 $0.220 $0.250
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 40.000 $11.000 $5.500 $6.340
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 65,110.000 $1.000 $0.220 $0.250
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,050.000 $1.000 $1.500 $0.830
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 6,260.000 $1.000 $1.100 $1.270
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 58,895.000 $1.000 $0.770 $0.890
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 65,160.000 $1.000 $0.770 $0.890
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 40.000 $18.000 $22.000 $25.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 8.000 $500.000 $330.000 $380.000
REFL PAV MRKR TY I-C
EA 313.000 $6.000 $5.500 $6.340
REFL PAV MRKR TY II-A-A
EA 1,282.000 $6.000 $4.400 $5.000
D-GR HMA TY-D SAC-A PG70-22
TON 14,074.000 $160.000 $163.840 $180.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 12,405.000 $130.000 $154.340 $180.000
TACK COAT
GAL 20,385.000 $6.000 $5.510 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $30,000.000 $15,000.000
TMA (STATIONARY)
DAY 163.000 $350.000 $250.000 $500.000
TMA (MOBILE OPERATION)
DAY 20.000 $350.000 $50.000 $750.000
Totals: $8,132,488.100 $9,062,104.586 $9,851,983.650