Show Job Controls
Bid Cobra

TRAVIS SH0130 (6340-47-001)

Items: 57

County: TRAVIS
Length: N/A
Highway: SH0130
District: AUSTIN
Control Number: 6340-47-001
DBE Goal: 0.0%
Project: RMC - 634047001
Guaranty: N/A
Time: 360 W
Engineer's Estimate: $47,208,868.34
Date: 12/05/2023 (2 years ago)
Contract Number: N/A
Type: ACP OVERLAY
Mail/Deliver Bids To: N/A
GISEL CARRASCO
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$47,208,868.34
$40,923,831.42
Over/Under Est: -13.31% -$6,285,036.92
Over/Under Est: -7.36% -$3,473,784.03
Amt Left: 6.87% $2,811,252.89
$44,620,888.41
Over/Under Est: -5.48% -$2,587,979.93
Amt Left: 9.03% $3,697,056.99
Delta: -2.03% -$885,804.10
Subcontractor Percentage Amount
MC2 CIVIL, LLC 27.61% $11,299,069.86
PENHALL COMPANY 3.89% $1,591,937.04
TRP CONSTRUCTION GROUP, LLC 2.52% $1,031,280.55
ENVIRONMENTAL SAFETY SERVICES, INC. 1.16% $474,716.44
SCR CIVIL CONSTRUCTION, LLC 0.42% $171,880.09
TEXAS CURB CUT 0.24% $98,217.20
SAN ANTONIO SWEEPING SERVICES, INC. 0.21% $85,940.05
STRIPE IT UP, LLC 0.02% $8,184.77
TEXAS TRAFFIC AND BARRICADE, LLC 0.02% $8,184.77
HOLES INCORPORATED 0.00% $0.00
Total: 36.09% $14,769,410.77

Bid Items & Bid Tabulations

57 Total 0 of 57
TRAVIS  |  SH0130  |  AUSTIN  |  6340-47-001  |  12/05/2023  |  $47,208,868.34  |  RMC - 634047001  |  ACP OVERLAY  |  360 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
REMOVING CONCRETE(MOW STRIP)
LF 2,775.000 $15.000 $18.500 $16.500 $17.500
BACKFILL (TY B)
STA 1,260.000 $185.000 $82.000 $175.000 $162.000
EMULS ASPH (EROSN CONT)(SS-1)
GAL 4,194.000 $5.100 $3.900 $9.000 $4.500
ASPH (AC-20-5TR)
GAL 480,633.000 $3.750 $3.500 $5.000 $5.360
AGGR(TY-PB GR-4 SAC-B)
CY 7,282.000 $400.000 $225.000 $200.000 $156.240
PLANE CONC PAV(0" TO 3")
SY 9,631.000 $25.000 $28.000 $11.000 $22.000
FULL - DEPTH REPAIR CRCP (13")
SY 18,318.000 $770.000 $550.000 $540.000 $589.010
RIPRAP (MOW STRIP)(4 IN)
CY 126.000 $625.000 $1,000.000 $910.000 $1,081.040
HEADER TYPE EXPANSION JOINT
CF 110.000 $650.000 $1,300.000 $910.000 $615.000
JOINT SEALANT
LF 1,743.000 $20.000 $21.000 $20.000 $24.000
MOBILIZATION
LS 1.000 $4,319,169.940 $3,972,695.000 $2,920,000.000 $3,404,898.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $5,500.000 $70,000.000 $50,000.000 $47,444.780
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $5.000 $5.050 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,000.000 $1.250 $2.550 $2.500 $1.500
DRIVEWAYS (CONC)
SY 613.000 $230.000 $180.000 $162.500 $193.040
MTL W-BEAM GD FEN (TIM POST)
LF 1,825.000 $30.000 $35.000 $31.500 $34.650
MTL THRIE-BEAM GD FEN (TIM POST)
LF 114.000 $150.000 $203.000 $180.000 $198.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,500.000 $2,100.000 $1,942.000 $2,136.200
REMOVE METAL BEAM GUARD FENCE
LF 1,825.000 $2.000 $2.250 $2.000 $2.200
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 8.000 $130.000 $275.000 $250.000 $275.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $400.000 $600.000 $563.000 $619.300
GUARDRAIL END TREATMENT (INSTALL)
EA 14.000 $3,000.000 $4,100.000 $3,850.000 $4,235.000
GUARDRAIL END TREATMENT (REMOVE)
EA 14.000 $500.000 $425.000 $400.000 $440.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 60.000 $36.000 $40.000 $38.500 $42.350
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 21,045.000 $1.000 $0.800 $0.770 $0.770
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 16,383.000 $2.500 $1.620 $1.600 $1.600
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 7,622.000 $3.500 $3.780 $3.740 $3.740
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 12.000 $165.000 $162.000 $160.000 $160.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 6.000 $410.000 $345.000 $340.000 $340.000
REFL PAV MRK TY I (W)(NUMBER)(100MIL)
EA 9.000 $3,600.000 $255.000 $250.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 12.000 $165.000 $178.000 $176.000 $176.000
REFL PAV MRK TY II (W) 6" (BRK)
LF 59,750.000 $0.300 $0.320 $0.280 $0.280
REFL PAV MRK TY II (W) 6" (SLD)
LF 135,728.000 $0.300 $0.320 $0.280 $0.280
REFL PAV MRK TY II (W) 8" (SLD)
LF 21,045.000 $0.500 $0.490 $0.430 $0.430
REFL PAV MRK TY II (W) 12" (LNDP)
LF 16,383.000 $1.500 $0.870 $0.770 $0.770
REFL PAV MRK TY II (W) 12" (SLD)
LF 7,622.000 $1.500 $1.400 $1.240 $1.240
REFL PAV MRK TY II (W) (ARROW)
EA 12.000 $75.000 $78.990 $70.000 $70.000
REFL PAV MRK TY II (W) (LNDP ARW)
EA 6.000 $185.000 $86.890 $77.000 $77.000
REFL PAV MRK TY II (W) (NUMBER)
EA 9.000 $130.000 $139.920 $124.000 $124.000
REFL PAV MRK TY II (W) (WORD)
EA 12.000 $2,000.000 $78.990 $70.000 $70.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 133,815.000 $0.300 $0.320 $0.280 $0.280
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 59,750.000 $0.750 $0.790 $0.700 $0.700
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 135,728.000 $1.100 $1.300 $1.150 $1.150
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 133,815.000 $1.100 $1.300 $1.150 $1.150
REFL PAV MRKR TY II-C-R
EA 7,865.000 $4.000 $5.340 $4.730 $4.730
ELIM EXT PAV MRK & MRKS (6")
LF 329,293.000 $0.850 $1.250 $1.100 $1.100
ELIM EXT PAV MRK & MRKS (8")
LF 21,045.000 $2.000 $1.150 $1.000 $1.000
ELIM EXT PAV MRK & MRKS (12")
LF 24,005.000 $1.150 $1.200 $1.060 $1.060
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 223.000 $60.000 $96.000 $95.000 $103.620
CONTINUOUS DIAMOND GRINDING CONC PVMT
SY 400,000.000 $4.050 $4.000 $4.400 $4.600
PFC-C PG76-22 SAC-A
TON 58,989.000 $180.000 $154.000 $192.000 $200.800
TOM-F PG76-22 SAC-A
TON 50,685.000 $165.000 $160.000 $190.000 $172.200
BONDING COURSE
GAL 78,649.000 $4.250 $4.250 $7.000 $4.210
REPAIR OF CONCRETE PAVEMENT (PRECAST)
SY 810.000 $1,150.000 $1,125.000 $1,150.000 $1,254.370
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $22,000.000 $23,000.000 $500.000 $10,010.580
TMA (STATIONARY)
DAY 15.000 $500.000 $700.000 $250.000 $400.420
TMA (MOBILE OPERATION)
HR 120.000 $44.000 $45.000 $43.000 $100.110
Totals: $47,208,868.340 $40,923,831.420 $43,735,084.310 $44,620,888.410