Bid Cobra

TRAVIS SH 71 (0700-03-145)

Items: 153

County: TRAVIS
Length: N/A
Highway: SH 71
District: AUSTIN
Control Number: 0700-03-145
DBE Goal: N/A
Project: C 700-3-145
Guaranty: N/A
Time: 253 WORKING DAYS
Engineer's Estimate: $12,843,171.40
Date: 01/06/2022 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$12,843,171.40
$13,908,750.59
Over/Under Est: 8.3% $1,065,579.19
Over/Under Est: 16.67% $2,141,521.49
Amt Left: 7.74% $1,075,942.30
$17,051,654.76
Over/Under Est: 32.77% $4,208,483.36
Amt Left: 22.6% $3,142,904.17
Delta: -13.79% -$2,066,961.87
Subcontractor Percentage Amount
AARON CONCRETE CONTRACTORS, L.P. 4.78% $722,660.59
COX COMMERCIAL CONSTRUCTION LLC 3.57% $539,727.68
JB PINNACLE GROUP, LLC 3.03% $458,088.20
THE LEVY COMPANY, INC. 3.03% $458,088.20
ROADWAY SPECIALTIES, INC. 2.73% $412,732.93
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 1.41% $213,169.76
D. I. J. CONSTRUCTION, INC. 1.20% $181,421.07
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC 0.45% $68,032.90
EGGEMEYER LAND CLEARING, LLC 0.37% $55,938.16
TRP CONSTRUCTION GROUP, LLC 0.21% $31,748.69
FIBERTEL, LLC 0.11% $16,630.26
ROYAL REBAR 0.03% $4,535.53
DEPENDABLE FENCE 0.00% $0.00
Total: 20.92% $3,162,773.97

Bid Items & Bid Tabulations

153 Total 0 of 153
TRAVIS  |  SH 71  |  AUSTIN  |  0700-03-145  |  01/06/2022  |  $12,843,171.40  |  C 700-3-145  |  HWY IMPRV  |  253 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
CAPITAL EXCAVATION COMPANY
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 209.000 $5,000.000 $962.370 $1,500.000 $6,441.020
REMOVING CONC (RIPRAP)
SY 581.000 $10.000 $13.320 $10.600 $12.890
REMOVING CONC (DRIVEWAYS)
SY 580.000 $15.000 $13.320 $26.800 $13.580
REMOVING CONC (CURB)
LF 7.000 $6.000 $36.630 $64.700 $193.230
REMOVING CONCRETE(MOW STRIP)
LF 392.000 $13.000 $13.320 $11.350 $13.230
REMOVING STAB BASE & ASPH PAV (12")
SY 39,209.000 $4.000 $6.660 $5.300 $6.310
EXCAVATION (ROADWAY)
CY 31,084.000 $10.000 $15.240 $12.000 $17.390
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 43,901.000 $10.000 $11.220 $23.000 $12.880
FURNISHING AND PLACING TOPSOIL (4")
SY 107,478.000 $1.500 $1.460 $3.290 $1.130
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 107,478.000 $0.150 $0.140 $0.140 $0.180
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 107,478.000 $0.090 $0.110 $0.110 $0.140
VEGETATIVE WATERING
MG 3,232.000 $15.000 $16.650 $32.750 $1.290
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 92,796.000 $0.980 $0.750 $0.750 $0.940
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 14,682.000 $1.400 $1.920 $1.950 $2.420
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 27,583.000 $45.000 $48.820 $47.000 $43.310
PRIME COAT (MULTI OPTION)
GAL 17,466.000 $4.000 $3.950 $3.750 $5.150
TOM (ASPHALT) PG 76-22
TON 660.000 $150.000 $118.350 $132.000 $152.010
TOM - C (AGGREGATE) SAC - B
TON 9,994.000 $100.000 $118.350 $132.000 $152.010
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 10,576.000 $20.000 $16.170 $15.000 $21.900
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 53,411.000 $1.500 $2.330 $0.910 $3.220
CUT & RESTORING PAV
SY 199.000 $110.000 $103.270 $127.000 $98.600
FLOWABLE BACKFILL
CY 360.400 $250.000 $145.780 $227.000 $255.820
TRENCH EXCAVATION PROTECTION
LF 254.000 $6.000 $6.070 $10.200 $7.270
TEMPORARY SPL SHORING
SF 560.000 $20.000 $72.350 $8.000 $428.200
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 12.000 $310.000 $484.100 $480.000 $605.460
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 28.000 $310.000 $545.900 $540.000 $682.750
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 44.000 $480.000 $679.800 $680.000 $850.220
CL B CONC (FLUME)
CY 541.600 $650.000 $650.000 $650.000 $736.400
CL C CONC (FOOTING)
CY 273.000 $600.000 $600.000 $700.000 $775.900
CL C CONC (RAIL FOUNDATION)
CY 386.000 $410.000 $630.000 $720.000 $632.430
RIPRAP (CONC)(5 IN)
CY 1,055.000 $450.000 $450.000 $550.000 $367.540
RIPRAP CONC (8 IN)
CY 1,049.000 $470.000 $450.000 $610.000 $352.790
RIPRAP (CONC)(CL B)(5 IN)
CY 167.000 $420.000 $630.000 $650.000 $378.070
RIPRAP (MOW STRIP)(4 IN)
CY 324.000 $410.000 $650.000 $760.000 $383.680
RAIL (TY SSTR)
LF 2,026.000 $45.000 $60.000 $77.500 $77.260
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 500.000 $60.000 $70.000 $75.300 $57.970
RAIL (TY SSTR)(MOD)
LF 914.000 $72.000 $175.000 $143.000 $135.580
CMP (GAL STL 30 IN)
LF 20.000 $130.000 $150.000 $242.000 $361.120
CMP (GAL STL 36 IN)
LF 12.000 $100.000 $170.000 $620.000 $552.020
RC PIPE (CL III)(18 IN)
LF 846.000 $59.000 $80.000 $80.000 $48.790
RC PIPE (CL III)(24 IN)
LF 1,015.000 $80.000 $90.000 $84.000 $54.950
RC PIPE (CL III)(36 IN)
LF 167.000 $120.000 $450.000 $205.000 $86.970
RC PIPE (ARCH)(CL III)(DES 8)
LF 100.000 $350.000 $580.000 $600.000 $673.090
SET (PIPE RUNNER ASSEMBLY)
EA 1.000 $8,000.000 $6,000.000 $18,100.000 $5,802.020
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 2.000 $850.000 $2,000.000 $1,790.000 $1,965.800
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,100.000 $1,900.000 $1,840.000 $2,045.990
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 24.000 $1,600.000 $2,000.000 $2,060.000 $1,039.260
SET (TY II) (24 IN) (RCP) (3: 1) (P)
EA 3.000 $1,500.000 $2,000.000 $2,510.000 $1,647.610
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 22.000 $1,500.000 $2,000.000 $2,950.000 $1,310.660
SET (TY II) (30 IN) (CMP) (3: 1) (C)
EA 2.000 $2,500.000 $2,000.000 $3,600.000 $2,516.510
SET (TY II) (36 IN) (CMP) (3: 1) (C)
EA 2.000 $2,800.000 $2,000.000 $3,820.000 $3,573.480
SET (TY II) (36 IN) (RCP) (3: 1) (P)
EA 1.000 $4,600.000 $4,700.000 $6,200.000 $5,086.480
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $2,700.000 $5,000.000 $4,350.000 $3,929.990
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 1.000 $4,000.000 $5,000.000 $5,500.000 $6,144.410
SET (TY I) (DES 8) (3:1) (C)
EA 2.000 $6,000.000 $8,500.000 $9,800.000 $15,276.820
CLEAN EXIST CULVERTS
EA 3.000 $2,500.000 $2,000.000 $2,460.000 $2,232.290
REMOV STR (SET)
EA 55.000 $450.000 $500.000 $350.000 $385.320
REMOV STR (HEADWALL)
EA 1.000 $1,350.000 $2,500.000 $2,210.000 $1,624.430
REMOV STR (PIPE)
LF 1,220.000 $14.000 $24.000 $11.700 $10.180
MOBILIZATION
LS 1.000 $1,119,001.440 $1,374,000.000 $1,200,000.000 $1,674,666.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $9,500.000 $10,000.000 $5,300.000 $19,323.070
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 244.000 $30.000 $30.000 $29.700 $38.680
ROCK FILTER DAMS (REMOVE)
LF 244.000 $10.000 $12.000 $11.900 $13.890
TEMP SEDMT CONT FENCE (INSTALL)
LF 19,837.000 $2.700 $3.500 $3.500 $1.350
TEMP SEDMT CONT FENCE (REMOVE)
LF 19,837.000 $0.750 $0.700 $0.700 $0.780
CONSTRUCTING DETOURS (TY 1)
SY 1,599.000 $56.000 $48.180 $57.400 $53.660
DRIVEWAYS (CONC)
SY 449.000 $75.000 $95.000 $116.000 $67.920
DRIVEWAYS (ACP)
SY 5,559.000 $40.000 $35.040 $66.700 $52.740
MTL W-BEAM GD FEN (TIM POST)
LF 7,363.000 $21.500 $28.000 $26.150 $14.070
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $1,800.000 $2,100.000 $1,850.000 $2,378.560
SHORT RADIUS
LF 517.500 $36.000 $35.000 $31.800 $113.520
DRIVEWAY TERMINAL ANCHOR SECTION
EA 4.000 $850.000 $900.000 $820.000 $1,204.450
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 21.000 $1,500.000 $1,600.000 $1,230.000 $1,471.720
REMOVE METAL BEAM GUARD FENCE
LF 1,932.000 $2.500 $1.300 $2.050 $3.190
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $220.000 $200.000 $205.000 $1,384.820
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $200.000 $200.000 $205.000 $229.540
GUARDRAIL END TREATMENT (INSTALL)
EA 23.000 $2,650.000 $4,000.000 $3,130.000 $3,404.080
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $500.000 $220.000 $260.000 $284.780
RELOCATE EXISTING MAILBOX
EA 16.000 $525.000 $600.000 $300.000 $528.160
CONDT (PVC) (SCH 40) (2")
LF 114.000 $10.000 $15.000 $13.350 $16.750
CONDT (PVC) (SCH 40) (3")
LF 846.000 $15.000 $28.000 $27.700 $34.780
CONDT (PVC) (SCH 40) (3") (BORE)
LF 705.000 $33.000 $60.000 $58.500 $73.430
ELEC CONDR (NO.8) BARE
LF 1,693.000 $1.280 $2.500 $2.250 $2.830
ELEC CONDR (NO.8) INSULATED
LF 1,410.000 $1.500 $2.700 $2.650 $3.350
ELEC CONDR (NO.6) BARE
LF 35.000 $1.400 $6.000 $5.950 $7.470
ELEC CONDR (NO.6) INSULATED
LF 70.000 $1.800 $6.000 $5.950 $7.470
ELEC CONDR (NO.4) INSULATED
LF 300.000 $2.000 $5.000 $4.600 $5.800
GROUND BOX TY C (162911)W/APRON
EA 6.000 $1,400.000 $1,800.000 $1,740.000 $2,189.950
REMOVE GROUND BOX
EA 4.000 $300.000 $115.000 $113.000 $141.700
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 33.000 $520.000 $540.000 $530.000 $611.900
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 21.000 $600.000 $640.000 $640.000 $805.130
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,000.000 $760.000 $750.000 $1,030.560
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 4.000 $700.000 $925.000 $920.000 $1,030.560
IN SM RD SN SUP&AM (INST SIGN ONLY)
EA 7.000 $400.000 $445.000 $440.000 $553.930
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 41.000 $440.000 $440.000 $440.000 $901.740
RELOCATE SM RD SN SUP&AM TY S80
EA 4.000 $520.000 $570.000 $560.000 $1,114.300
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 17.000 $20.000 $33.000 $32.800 $25.760
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 20.000 $27.000 $40.000 $38.950 $38.650
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 38,001.000 $0.200 $0.400 $0.250 $0.230
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 8,614.000 $0.200 $0.450 $0.250 $0.330
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 43,667.000 $0.200 $0.400 $0.250 $0.230
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 58,896.000 $0.700 $0.500 $0.540 $0.770
WK ZN PAV MRK REMOV (Y)4"(BRK)
LF 9,052.000 $0.800 $1.000 $0.550 $1.700
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 54,092.000 $0.650 $0.500 $0.540 $0.740
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,341.000 $0.800 $1.000 $0.750 $0.940
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 127.000 $7.000 $14.000 $7.200 $7.010
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $145.000 $235.000 $159.000 $139.340
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $150.000 $260.000 $190.000 $159.550
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 10,747.000 $0.450 $0.400 $0.350 $0.440
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 11,260.000 $0.350 $0.400 $0.350 $0.370
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 45,036.000 $0.350 $0.350 $0.350 $0.380
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 42,986.000 $0.570 $0.800 $0.600 $0.590
REFL PAV MRKR TY I-C
EA 538.000 $3.500 $4.200 $3.500 $3.340
REFL PAV MRKR TY II-A-A
EA 1,126.000 $3.300 $3.100 $3.500 $3.480
ELIM EXT PAV MRK & MRKS (4")
LF 101,301.000 $0.400 $0.250 $0.440 $0.390
ELIM EXT PAV MRK & MRKS (12")
LF 64.000 $2.500 $6.000 $2.050 $1.730
INSTALL HWY TRF SIG (FLASH BEACON)
EA 1.000 $8,000.000 $3,000.000 $2,970.000 $3,735.790
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $25,000.000 $3,650.000 $3,590.000 $4,508.720
REMOVING TRAFFIC SIGNALS
EA 2.000 $5,000.000 $4,500.000 $4,410.000 $5,539.280
TEMP TRAF SIGNALS
EA 2.000 $75,000.000 $60,000.000 $59,000.000 $74,715.877
VEH SIG SEC (12")LED(GRN)
EA 7.000 $230.000 $340.000 $340.000 $425.110
VEH SIG SEC (12")LED(GRN ARW)
EA 1.000 $240.000 $340.000 $340.000 $425.110
VEH SIG SEC (12")LED(YEL)
EA 19.000 $230.000 $340.000 $340.000 $425.110
VEH SIG SEC (12")LED(YEL ARW)
EA 2.000 $240.000 $340.000 $340.000 $425.110
VEH SIG SEC (12")LED(RED)
EA 11.000 $230.000 $340.000 $340.000 $425.110
VEH SIG SEC (12")LED(RED ARW)
EA 1.000 $240.000 $340.000 $340.000 $425.110
BACK PLATE (12")(2 SEC)
EA 8.000 $90.000 $125.000 $123.000 $154.580
BACKPLATE W/REFL BRDR(3 SEC)ALUM
EA 7.000 $135.000 $130.000 $128.000 $161.030
BACKPLATE W/REFL BRDR(4 SEC)ALUM
EA 1.000 $150.000 $140.000 $138.000 $173.910
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 2,868.000 $1.850 $2.250 $2.200 $2.770
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 319.000 $2.500 $2.600 $2.550 $3.220
INS TRF SIG PL AM(S)1 ARM(32')LUM
EA 1.000 $8,000.000 $11,500.000 $11,300.000 $14,170.250
INS TRF SIG PL AM(S)1 ARM(48')LUM
EA 2.000 $10,500.000 $16,000.000 $15,900.000 $19,967.170
INS TRF SIG PL AM(S)1 ARM(50')LUM
EA 1.000 $22,000.000 $38,300.000 $37,900.000 $47,663.570
INS TRF SIG PL AM(S)2 ARM(60-44')LUM
EA 1.000 $26,000.000 $45,000.000 $43,900.000 $55,135.160
INSTALL OF FND FOR GROUND MNT CABINETS
EA 2.000 $5,000.000 $3,300.000 $3,280.000 $4,122.250
INSTALL OF CONTROL CABINET(GRND MNT)
EA 2.000 $3,000.000 $2,200.000 $2,150.000 $2,705.230
VIVDS CABLE (INSTALL)
LF 1,000.000 $2.350 $3.800 $3.700 $4.640
VIVDS CAMERA (INSTALL)
EA 5.000 $2,500.000 $1,030.000 $1,030.000 $1,288.200
FULL - WIDTH MOWING
CYC 4.000 $3,500.000 $5,000.000 $4,520.000 $10,563.280
LITTER REMOVAL
CYC 4.000 $3,500.000 $6,300.000 $990.000 $1,666.310
CLEANING / SWEEPING (SPOT)
MI 3.960 $1,500.000 $1,575.000 $1,490.000 $446.180
D-GR HMA TY-C PG64-22
TON 9,607.000 $60.000 $78.090 $78.800 $101.770
D-GR HMA TY-D PG76-22
TON 20,951.000 $77.000 $87.540 $89.100 $121.090
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 2,203.000 $82.000 $94.380 $120.000 $126.240
BONDING COURSE
GAL 16,972.000 $3.200 $3.380 $2.800 $5.600
UNDERSEAL COURSE
GAL 38,092.000 $3.100 $3.610 $2.800 $5.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $10,000.000 $8,000.000 $14,800.000 $5,152.820
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 1.000 $7,000.000 $8,500.000 $8,400.000 $16,665.410
TMA (STATIONARY)
DAY 75.000 $160.000 $260.000 $460.000 $193.230
TMA (MOBILE OPERATION)
HR 50.000 $90.000 $240.000 $460.000 $128.820
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 10.000 $1,300.000 $3,100.000 $3,850.000 $5,306.680
SUBSURFACE UTIL LOCATE (WITHIN RDBED)
EA 5.000 $1,700.000 $5,200.000 $4,260.000 $8,083.480
Totals: $12,843,171.400 $13,908,750.592 $14,984,692.890 $17,051,654.775