TRAVIS SL 275 (0015-11-075)
Items: 63
County: TRAVIS
Length: 0.0000 MILES
Highway: SL 275
District: AUSTIN
Control Number: 0015-11-075
DBE Goal: 0.0%
Project: F 2026(329)
Guaranty: $43,000.00
Time: 39 WORKING DAYS
Engineer's Estimate: $2,158,946.59
Date: 02/04/2026 (4 months ago)
Contract Number: 2263022
Type: PREVENTIVE MAINTENANCE
Project ID: A00209818
Contract Type: Federal
Project Description: 2" MILL, FDR, BONDING COURSE, 1" TY D, " TOM
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MATTHEW KELLY
KEVIN MACKAN
TRAVIS SL 275 (0015-11-075)
Project Name: N/A
Project: F 2026(329)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: BRAKER LANE
Limits To: MORROW ST.
Project Description: 2" MILL, FDR, BONDING COURSE, 1" TY D, " TOM
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,158,946.59 | |||
| $2,185,902.87 |
1.25%
$26,956.28
|
|||
| $2,253,645.50 |
4.39%
$94,698.91
|
3.1%
$67,742.63
|
||
| $2,504,006.18 |
15.98%
$345,059.59
|
14.55%
$318,103.31
|
-11.11%
-$250,360.68
|
|
| $2,853,776.50 |
32.18%
$694,829.91
|
30.55%
$667,873.63
|
-13.97%
-$349,770.32
|
|
| $3,464,076.40 |
60.45%
$1,305,129.81
|
58.47%
$1,278,173.53
|
-21.39%
-$610,299.90
|
E
Engineer's Estimate
$2,158,946.59
1
Awarded
$2,185,902.87
Over/Under Est:
1.25%
$26,956.28
$2,253,645.50
Over/Under Est:
4.39%
$94,698.91
Amt Left:
3.1%
$67,742.63
$2,504,006.18
Over/Under Est:
15.98%
$345,059.59
Amt Left:
14.55%
$318,103.31
Delta:
-11.11%
-$250,360.68
$2,853,776.50
Over/Under Est:
32.18%
$694,829.91
Amt Left:
30.55%
$667,873.63
Delta:
-13.97%
-$349,770.32
$3,464,076.40
Over/Under Est:
60.45%
$1,305,129.81
Amt Left:
58.47%
$1,278,173.53
Delta:
-21.39%
-$610,299.90
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $7,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $22,982.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $35,000.00 |
| Total: | $64,982.00 |