Bid Cobra

TERRY US 62 (0228-01-062)

Items: 80

County: TERRY
Length: N/A
Highway: US 62
District: LUBBOCK
Control Number: 0228-01-062
DBE Goal: 250.0%
Project: F 2024(427)
Guaranty: N/A
Time: 132 WORKING DAYS
Engineer's Estimate: $11,660,773.50
Date: 12/06/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEVE SISNEROS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$11,660,773.50
$11,408,518.79
Over/Under Est: -2.16% -$252,254.71
$14,346,679.79
Over/Under Est: 23.03% $2,685,906.29
Amt Left: 25.75% $2,938,161.00
$14,801,959.91
Over/Under Est: 26.94% $3,141,186.41
Amt Left: 29.74% $3,393,441.12
Delta: -3.17% -$455,280.12
Over/Under Est: 30.33% $3,536,597.92
Amt Left: 33.21% $3,788,852.63
Delta: -2.67% -$395,411.51
Subcontractor Percentage Amount
INDUSTRIAL FABRICS, INC. 7.95% $906,977.24
NM AC & COMPANY LLC 2.08% $237,297.19
TRP CONSTRUCTION GROUP, LLC 1.96% $223,606.97
A BROTHERS MILLING, LLC 1.14% $130,057.11
SQUARE ROOT SERVICES LLC 0.47% $53,620.04
BARRICADES UNLIMITED 0.33% $37,648.11
MORRIS COUNTY CONTRACTORS, L.L.C. 0.32% $36,507.26
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.27% $30,803.00
MOBILE ENTERPRISES, INC. 0.20% $22,817.04
MURRAY CONSTRUCTION 0.18% $20,535.33
WEST TEXAS ROCK RESOURCES, LLC 0.06% $6,845.11
Total: 14.96% $1,706,714.40

Bid Items & Bid Tabulations

80 Total 0 of 80
TERRY  |  US 62  |  LUBBOCK  |  0228-01-062  |  12/06/2023  |  $11,660,773.50  |  F 2024(427)  |  REHAB EXIST ROADWAY  |  132 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES HAMILTON CONSTRUCTION CO.
A. L. HELMCAMP, INC.
DUININCK, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
REMOVING CONC (CURB AND GUTTER)
LF 1,589.000 $15.000 $12.000 $13.000 $8.350 $9.350
BACKFILL (TY B)
STA 411.000 $400.000 $400.000 $400.000 $210.000 $758.130
BLADING
STA 411.000 $400.000 $400.000 $125.000 $210.000 $236.570
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 128,423.000 $0.200 $0.240 $0.230 $0.230 $0.270
PROOF ROLLING
HR 20.000 $100.000 $100.000 $225.000 $185.000 $241.870
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 28,253.000 $3.500 $4.000 $5.000 $3.800 $4.980
FOG SEAL (CSS-1H)
GAL 15,038.000 $4.000 $4.000 $5.000 $3.950 $5.230
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,104.000 $60.000 $58.000 $125.000 $89.500 $91.140
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 6,312.000 $33.000 $31.000 $60.000 $47.000 $44.990
PLANE ASPH CONC PAV (2 1/2")
SY 59,333.000 $1.700 $2.000 $5.750 $3.350 $3.040
PLANE ASPH CONC PAV (5")
SY 32,062.000 $6.000 $4.700 $9.500 $7.350 $7.810
CONC STR REPR(RAPID VERT AND OVERHEAD)
SF 100.000 $130.000 $203.500 $210.000 $310.000 $368.770
RIPRAP (MOW STRIP)(5 IN)
CY 52.000 $800.000 $475.000 $892.500 $875.000 $799.000
RETROFIT RAIL (TY T551)
LF 64.000 $700.000 $692.000 $588.000 $575.000 $758.410
MOBILIZATION
LS 1.000 $1,060,000.000 $1,140,000.000 $1,200,000.000 $1,400,000.000 $1,575,203.510
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $30,000.000 $30,000.000 $50,000.000 $30,000.000 $35,000.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 444.000 $40.000 $40.000 $10.000 $35.000 $41.860
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $5.000 $5.000 $5.000 $14.000 $16.750
SANDBAGS FOR EROSION CONTROL
EA 96.000 $12.000 $30.000 $28.610 $28.000 $33.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 120.000 $7.000 $7.000 $6.950 $6.800 $8.140
TEMP SEDMT CONT FENCE (REMOVE)
LF 60.000 $3.000 $1.500 $1.370 $1.350 $1.600
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,420.000 $6.000 $10.500 $10.060 $9.850 $11.780
BIODEG EROSN CONT LOGS (REMOVE)
LF 710.000 $2.000 $1.500 $1.370 $1.350 $1.600
CONC CURB & GUTTER (TY II)
LF 480.000 $50.000 $90.000 $84.000 $82.500 $95.670
CONC CURB & GUTTER (VALLEY GUTTER)
LF 1,109.000 $50.000 $165.000 $157.500 $155.000 $102.920
CONCRETE CURB (SPECIAL)
LF 604.000 $100.000 $135.000 $126.000 $125.000 $80.800
INTERSECTIONS (ACP)
SY 1,379.000 $50.000 $30.000 $80.000 $65.500 $63.610
CONC SIDEWALKS (4")
SY 722.000 $200.000 $120.000 $115.500 $115.000 $175.300
CURB RAMPS (TY 7)
SY 161.000 $300.000 $260.000 $246.750 $240.000 $305.400
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 62,737.000 $0.200 $0.150 $0.290 $0.070 $0.260
MTL W-BEAM GD FEN (STEEL POST)
LF 600.000 $50.000 $33.000 $34.930 $41.000 $38.110
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,430.000 $1,971.960 $1,600.000 $2,151.160
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $1,000.000 $880.000 $1,014.150 $1,400.000 $1,106.310
MTL THRIE-BEAM GD FEN (STEEL POST)
EA 2.000 $1,500.000 $2,390.000 $3,380.490 $2,500.000 $3,687.710
REMOVE METAL BEAM GUARD FENCE
LF 650.000 $5.000 $2.750 $2.250 $6.150 $2.460
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $500.000 $165.000 $563.420 $410.000 $614.620
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $4,000.000 $3,380.000 $4,394.640 $4,100.000 $4,794.020
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $500.000 $220.000 $563.420 $410.000 $614.620
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 11.000 $900.000 $935.000 $1,031.810 $875.000 $1,075.580
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $1,000.000 $1,045.000 $1,179.210 $980.000 $1,229.240
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,500.000 $1,210.000 $147.410 $1,100.000 $1,382.890
REMOVE SM RD SN SUP&AM
EA 22.000 $100.000 $110.000 $117.920 $105.000 $122.920
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $50.000 $22.000 $17.690 $20.500 $18.440
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 2.000 $150.000 $100.000 $123.820 $92.500 $129.070
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 24,136.000 $0.250 $0.280 $0.260 $0.260 $0.310
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 83,132.000 $0.250 $0.280 $0.260 $0.260 $0.310
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 1,114.000 $1.200 $1.100 $1.050 $1.050 $1.230
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 12,254.000 $0.600 $0.550 $0.530 $0.510 $0.610
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 680.000 $5.500 $5.500 $5.250 $5.150 $6.150
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 3,336.000 $0.250 $0.280 $0.260 $0.260 $0.310
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 94,580.000 $0.250 $0.280 $0.260 $0.260 $0.310
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,718.000 $1.500 $1.200 $0.830 $1.450 $2.460
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,474.000 $1.500 $1.200 $0.830 $1.450 $2.460
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 557.000 $2.500 $2.200 $2.100 $2.050 $2.460
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,127.000 $2.000 $1.400 $1.310 $1.300 $1.540
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 12,068.000 $0.750 $0.800 $0.790 $0.770 $0.920
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 41,566.000 $0.750 $0.700 $0.680 $0.670 $0.800
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 1,668.000 $0.750 $0.700 $0.790 $0.770 $0.920
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 47,290.000 $0.750 $0.700 $0.680 $0.670 $0.800
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 340.000 $15.000 $14.800 $14.180 $14.000 $16.590
PREFAB PAV MRK TY C (W) (ARROW)
EA 40.000 $250.000 $248.000 $236.250 $230.000 $276.580
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 167.000 $80.000 $60.500 $57.750 $56.500 $67.610
REFL PAV MRKR TY II-A-A
EA 167.000 $4.500 $6.600 $6.300 $6.150 $7.380
REFL PAV MRKR TY II-C-R
EA 1,211.000 $4.500 $5.000 $4.730 $4.650 $5.530
ELIM EXT PAV MRK & MRKS (6")
LF 102,592.000 $0.600 $0.550 $0.530 $0.510 $0.610
ELIM EXT PAV MRK & MRKS (8")
LF 6,127.000 $1.500 $0.800 $0.790 $0.770 $0.920
FULL - WIDTH MOWING
CYC 2.000 $4,500.000 $4,200.000 $10,000.000 $2,900.000 $11,711.860
LITTER REMOVAL
CYC 2.000 $2,100.000 $2,560.000 $10,000.000 $2,200.000 $15,057.780
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 145,992.000 $6.500 $6.500 $7.000 $6.650 $7.400
ASPH FOR REINF FAB (PG76-28)
GAL 21,899.000 $5.500 $5.500 $5.000 $3.650 $6.550
TACK COAT
GAL 39,503.000 $5.000 $5.000 $4.000 $5.150 $5.460
D-GR HMA TY-C SAC-B PG76-28
TON 4,014.000 $140.000 $140.000 $180.000 $170.000 $195.060
D-GR HMA TY-F SAC-B PG76-28
TON 3,227.000 $170.000 $170.000 $190.000 $185.000 $205.060
D-GR HMA TY-B SAC-B PG 76-28
TON 14,889.000 $130.000 $125.000 $170.000 $180.000 $166.210
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
TON 24,827.000 $150.000 $140.000 $180.000 $215.000 $196.840
TACK COAT
GAL 16,613.000 $5.000 $5.000 $4.000 $5.150 $5.460
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 480.000 $60.000 $40.000 $275.000 $130.000 $152.470
TMA (STATIONARY)
DAY 264.000 $250.000 $200.000 $300.000 $310.000 $588.590
TMA (MOBILE OPERATION)
DAY 69.000 $800.000 $750.000 $400.000 $1,000.000 $1,153.500
TEMP SPEED MONITOR SYS
EA 2.000 $12,000.000 $12,000.000 $10,000.000 $15,500.000 $13,838.730
Totals: $11,660,773.500 $11,408,518.790 $14,346,679.790 $14,801,959.910 $15,197,371.420