Show Job Controls
Bid Cobra

TARRANT CS (0902-90-036)

Items: 150

County: TARRANT
Length: N/A
Highway: CS
District: FORT WORTH
Control Number: 0902-90-036
DBE Goal: N/A
Project: STP 2B20(199)MM
Guaranty: N/A
Time: 384 WORKING DAYS
Engineer's Estimate: $4,046,661.00
Date: 11/05/2020 (5 years ago)
Contract Number: N/A
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$4,046,661.00
$3,972,278.79
Over/Under Est: -1.84% -$74,382.21
Over/Under Est: -1.35% -$54,558.65
Amt Left: 0.5% $19,823.56
Over/Under Est: 0.8% $32,441.65
Amt Left: 2.69% $106,823.86
Delta: -2.18% -$87,000.30
Over/Under Est: 4.01% $162,274.77
Amt Left: 5.96% $236,656.98
Delta: -3.18% -$129,833.12
$4,305,067.50
Over/Under Est: 6.39% $258,406.50
Amt Left: 8.38% $332,788.71
Delta: -2.28% -$96,131.73
Over/Under Est: 17.41% $704,461.00
Amt Left: 19.61% $778,843.21
Delta: -10.36% -$446,054.50
$5,192,221.40
Over/Under Est: 28.31% $1,145,560.40
Amt Left: 30.71% $1,219,942.61
Delta: -9.28% -$441,099.40
$5,514,786.00
Over/Under Est: 36.28% $1,468,125.00
Amt Left: 38.83% $1,542,507.21
Delta: -6.21% -$322,564.60

Bid Items & Bid Tabulations

150 Total 0 of 150
TARRANT  |  CS  |  FORT WORTH  |  0902-90-036  |  11/05/2020  |  $4,046,661.00  |  STP 2B20(199)MM  |  BICYCLE AND PEDESTRIAN IMPRVS  |  384 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
ACCELERATED CRITICAL PATH, INC.
ED BELL CONSTRUCTION COMPANY
RAGLE CONSTRUCTION, INC.
TEXAS-REYES GROUP LTD.
TEXAS MATERIALS GROUP, INC.
ALTUS CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 21.000 $2,000.000 $1,001.700 $9,250.000 $7,350.000 $20,000.000 $2,327.500 $4,000.000 $6,880.720 $19,048.000
REMOVING CONC (DRIVEWAYS)
SY 635.000 $15.000 $23.010 $18.000 $21.000 $10.000 $17.000 $16.000 $16.100 $20.000
REMOVING CONC (CURB AND GUTTER)
LF 139.000 $12.000 $16.990 $9.000 $21.000 $8.000 $6.500 $7.000 $9.500 $20.000
REMOVING CONC (FLUME)
SY 415.000 $10.000 $25.720 $17.000 $21.000 $9.000 $10.500 $17.000 $20.890 $20.000
REMOV STAB BASE & ASPH PAV (4"-14")
SY 6,665.000 $15.000 $4.210 $5.000 $5.000 $5.000 $4.000 $4.250 $6.600 $10.000
EXCAVATION (ROADWAY)
CY 3,700.000 $10.000 $20.530 $16.000 $10.000 $40.000 $30.500 $19.000 $21.390 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 800.000 $15.000 $22.790 $9.000 $10.000 $50.000 $34.000 $38.000 $41.280 $30.000
COMPOST MANUF TOPSOIL (4")
SY 3,375.000 $2.000 $1.730 $6.500 $6.000 $0.920 $2.000 $1.200 $1.270 $8.000
BLOCK SODDING
SY 3,375.000 $7.500 $8.260 $5.500 $10.000 $6.690 $9.500 $5.000 $4.470 $5.000
BROADCAST SEED (PERM) (URBAN) (CLAY)
SY 3,375.000 $1.000 $0.620 $1.000 $0.500 $0.350 $0.500 $0.600 $0.480 $1.000
VEGETATIVE WATERING
MG 120.000 $30.000 $37.340 $49.000 $50.000 $10.000 $40.500 $41.000 $41.280 $50.000
LIME (HYD, COM, OR QK(SLURRY))
TON 254.000 $180.000 $182.000 $160.000 $200.000 $160.000 $207.500 $180.000 $233.940 $200.000
LIME TRT (EXST MATL)(8")
SY 11,145.000 $5.000 $12.620 $4.000 $4.000 $4.000 $5.000 $4.100 $5.780 $12.000
PRIME COAT (MULTI OPTION)
GAL 2,229.000 $4.000 $3.820 $4.000 $5.280 $5.300 $6.500 $4.800 $6.840 $10.000
PLANE ASPH CONC PAV (2")
SY 3,995.000 $2.000 $2.530 $4.000 $2.130 $1.250 $2.500 $2.500 $3.300 $20.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 40.000 $120.000 $161.020 $180.000 $315.000 $250.000 $139.000 $123.000 $96.330 $200.000
CUT & RESTORING PAV
SY 100.000 $145.000 $105.270 $290.000 $140.000 $10.000 $70.500 $125.000 $172.020 $200.000
TRENCH EXCAVATION PROTECTION
LF 6,418.000 $3.000 $2.110 $2.000 $1.000 $1.000 $1.000 $2.250 $4.130 $10.000
CL A CONC (FLUME)
CY 50.000 $700.000 $831.620 $500.000 $735.000 $200.000 $395.000 $850.000 $552.380 $650.000
RIPRAP (CONC)(4 IN)
CY 40.000 $600.000 $510.550 $500.000 $735.000 $500.000 $458.000 $500.000 $494.990 $550.000
RAIL (TY C411)
LF 200.000 $175.000 $236.850 $250.000 $126.000 $225.000 $312.000 $260.000 $335.640 $200.000
CONC BOX CULV (5 FT X 3 FT)
LF 35.000 $450.000 $426.340 $290.000 $260.000 $350.000 $559.000 $455.000 $387.280 $450.000
CONC BOX CULV (5 FT X 4 FT)
LF 335.000 $350.000 $452.660 $300.000 $275.000 $425.000 $388.000 $600.000 $427.550 $650.000
CONC BOX CULV (6 FT X 5 FT)
LF 110.000 $600.000 $568.450 $490.000 $375.000 $100.000 $580.000 $630.000 $602.010 $850.000
CONC BOX CULV (8 FT X 5 FT)
LF 130.000 $800.000 $703.200 $590.000 $575.000 $600.000 $628.000 $825.000 $787.990 $850.000
CONC BOX CULV (8 FT X 5 FT)(EXTEND)
LF 30.000 $1,000.000 $612.660 $1,100.000 $575.000 $700.000 $1,624.000 $655.000 $916.260 $1,000.000
RC PIPE (CL III)(18 IN)
LF 1,300.000 $100.000 $121.060 $95.000 $100.000 $90.000 $78.000 $140.000 $49.850 $85.000
RC PIPE (CL III)(24 IN)
LF 310.000 $120.000 $136.850 $130.000 $110.000 $95.000 $84.000 $150.000 $72.860 $105.000
RC PIPE (CL III)(30 IN)
LF 865.000 $150.000 $163.170 $135.000 $120.000 $110.000 $98.500 $190.000 $99.700 $125.000
INLET (COMPL)(CURB)(TY 2)(10')
EA 5.000 $4,000.000 $6,737.200 $12,000.000 $11,550.000 $10,000.000 $8,165.500 $7,500.000 $8,731.640 $8,500.000
INLET(COMPL)(DROP)(TY 1)(1 GRATE)
EA 3.000 $5,500.000 $4,947.630 $5,000.000 $6,300.000 $5,000.000 $9,573.000 $5,400.000 $5,147.330 $8,500.000
JCT BOX (COMPL)(SPL)
EA 1.000 $15,000.000 $13,684.940 $11,000.000 $11,550.000 $14,000.000 $19,813.000 $15,000.000 $20,217.760 $8,500.000
MANH(COMPL)(TY 1-C)
EA 7.000 $3,100.000 $7,158.280 $4,000.000 $7,350.000 $5,000.000 $12,791.500 $7,900.000 $2,110.450 $8,500.000
INLET(COMPL)(RECESS CURB)(10')
EA 8.000 $4,000.000 $6,842.470 $7,500.000 $9,450.000 $5,000.000 $7,830.500 $7,600.000 $8,818.330 $8,500.000
INLET(COMPL)(RECESS CURB)(16')
EA 6.000 $4,000.000 $8,947.850 $11,000.000 $11,550.000 $7,000.000 $10,902.500 $10,500.000 $12,831.170 $12,500.000
INLET (COMPL)(CU)(10 FT)(FTW)
EA 2.000 $3,750.000 $6,842.470 $11,500.000 $10,500.000 $9,500.000 $9,258.500 $7,600.000 $18,704.550 $12,500.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 1.000 $3,750.000 $3,894.950 $2,500.000 $3,600.000 $4,000.000 $6,968.500 $4,300.000 $4,551.600 $2,500.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 1.000 $5,250.000 $5,368.710 $3,200.000 $4,800.000 $4,500.000 $7,894.500 $5,900.000 $7,024.830 $3,500.000
WINGWALL (FW - S) (HW=3 FT)
EA 2.000 $8,000.000 $10,316.340 $5,000.000 $4,000.000 $9,000.000 $12,013.000 $11,400.000 $12,707.320 $12,000.000
WINGWALL (FW - S) (HW=8 FT)
EA 3.000 $30,000.000 $29,475.260 $19,000.000 $12,000.000 $12,000.000 $34,377.500 $33,000.000 $29,192.430 $25,000.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 1.000 $1,000.000 $578.980 $700.000 $132.910 $500.000 $384.000 $643.000 $978.860 $250.000
ADJUSTING MANHOLES (WATER METER)
EA 12.000 $500.000 $315.810 $1,900.000 $132.910 $350.000 $1,741.500 $350.000 $780.520 $250.000
ADJUSTING MANHOLES (IRRIGATION BOX)
EA 10.000 $350.000 $315.810 $700.000 $132.910 $300.000 $1,574.500 $350.000 $433.490 $250.000
REMOV STR (SET)
EA 6.000 $500.000 $473.710 $90.000 $500.000 $500.000 $841.500 $525.000 $764.900 $500.000
REMOV STR (WINGWALL)
EA 10.000 $1,300.000 $2,105.380 $800.000 $2,000.000 $500.000 $2,402.500 $2,500.000 $1,779.640 $2,500.000
REMOV STR (HEADWALL)
EA 11.000 $1,500.000 $2,315.910 $800.000 $1,000.000 $600.000 $3,041.500 $2,600.000 $1,249.640 $2,500.000
REMOV STR (PIPE)
LF 284.000 $25.000 $26.320 $39.000 $21.000 $15.000 $147.000 $35.000 $18.580 $30.000
REMOV STR (BOX CULVERT)
LF 41.000 $60.000 $63.160 $90.000 $73.500 $60.000 $236.500 $70.000 $72.540 $100.000
REMOV STR (DRIVEWAY CULVERT)
EA 23.000 $400.000 $700.040 $490.000 $315.000 $300.000 $1,035.500 $800.000 $656.320 $500.000
MOBILIZATION
LS 1.000 $315,000.000 $390,000.000 $440,000.000 $405,000.000 $420,000.000 $350,000.000 $475,057.000 $509,173.370 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $12,000.000 $3,750.000 $3,900.000 $15,750.000 $15,000.000 $4,167.500 $12,000.000 $31,229.300 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 195.000 $60.000 $71.200 $65.000 $31.900 $55.000 $30.500 $52.000 $75.690 $30.000
ROCK FILTER DAMS (REMOVE)
LF 195.000 $10.000 $19.500 $10.000 $15.950 $9.000 $10.000 $26.000 $12.390 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,260.000 $3.000 $3.810 $4.000 $1.490 $1.700 $2.000 $2.450 $2.340 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,260.000 $1.000 $0.840 $0.500 $0.110 $0.500 $0.500 $1.100 $0.690 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 601.000 $5.000 $5.210 $5.000 $3.140 $3.800 $3.500 $4.300 $5.230 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 601.000 $2.000 $0.840 $1.000 $1.060 $0.700 $0.500 $1.200 $0.960 $9.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 2,600.000 $15.000 $14.050 $6.000 $10.000 $9.000 $12.000 $15.000 $11.980 $35.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 2,600.000 $15.000 $9.660 $5.000 $7.500 $9.000 $26.000 $13.000 $10.070 $20.000
COLORED TEXTURED CONC (10")
SY 120.000 $200.000 $252.120 $200.000 $250.000 $180.000 $388.000 $141.000 $292.840 $200.000
CONC CURB (TY II)
LF 4,055.000 $25.000 $23.740 $39.000 $12.000 $1.000 $26.000 $16.000 $9.110 $35.000
DRIVEWAYS (CONC) (HES)
SY 1,085.000 $100.000 $76.090 $95.000 $100.000 $70.000 $85.000 $155.000 $124.540 $105.000
CONC SIDEWALKS (5")
SY 1,525.000 $60.000 $55.160 $70.000 $63.000 $45.000 $47.000 $80.000 $80.500 $55.000
CURB RAMPS (TY 1)
EA 1.000 $2,500.000 $1,631.130 $2,000.000 $2,500.000 $1,300.000 $2,954.000 $2,000.000 $1,981.650 $3,000.000
CURB RAMPS (TY 2)
EA 1.000 $2,500.000 $2,193.870 $2,200.000 $2,500.000 $1,600.000 $2,954.000 $2,150.000 $1,995.410 $3,000.000
CURB RAMPS (TY 7)
EA 4.000 $2,000.000 $1,475.430 $1,900.000 $2,500.000 $1,800.000 $3,965.000 $1,545.000 $2,064.220 $3,000.000
REMOVE METAL BEAM GUARD FENCE
LF 250.000 $50.000 $5.260 $6.000 $11.020 $4.610 $18.500 $7.000 $3.550 $3.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 13.000 $500.000 $247.380 $250.000 $249.880 $450.000 $427.000 $375.000 $277.810 $850.000
RELOCATE EXISTING MAILBOX
EA 14.000 $400.000 $526.340 $550.000 $683.550 $250.000 $427.000 $615.000 $206.420 $650.000
MASONRY MAILBOX
EA 2.000 $1,500.000 $2,631.720 $3,900.000 $2,126.600 $750.000 $793.500 $1,400.000 $688.070 $8,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $500.000 $526.340 $550.000 $637.980 $474.470 $726.500 $485.000 $688.070 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $775.000 $684.250 $700.000 $744.310 $651.000 $848.500 $900.000 $894.490 $850.000
WK ZN PV MK NON-REM (Y)(4")SLD W/MRKR
LF 8,970.000 $5.000 $1.530 $1.000 $0.850 $0.800 $2.000 $2.500 $1.100 $2.000
WK ZN PAV MRK REMOV (W)4"(SLD W/MRKR)
LF 440.000 $5.000 $4.470 $1.700 $1.590 $1.500 $3.500 $7.000 $2.060 $2.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 200.000 $1.000 $1.420 $2.100 $2.130 $2.000 $1.000 $2.000 $2.750 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,110.000 $1.000 $0.830 $1.300 $1.320 $1.240 $1.000 $1.000 $1.710 $6.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 50.000 $4.000 $3.530 $3.200 $3.190 $3.000 $5.000 $4.000 $4.130 $6.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 185.000 $8.000 $6.320 $7.500 $7.440 $7.000 $7.500 $7.000 $9.630 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 8.000 $150.000 $125.270 $110.000 $106.330 $100.000 $177.000 $140.000 $137.610 $250.000
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 1.000 $150.000 $210.540 $160.000 $159.500 $150.000 $274.500 $235.000 $206.420 $500.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 8.000 $150.000 $210.540 $110.000 $106.330 $100.000 $226.000 $235.000 $137.610 $250.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 155.000 $1.000 $3.530 $3.200 $3.190 $3.000 $5.000 $4.000 $4.130 $6.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 1,665.000 $1.000 $0.260 $0.500 $0.490 $0.460 $0.500 $0.300 $0.630 $1.000
REFL PAV MRK TY II (W) 4" (DOT)
LF 200.000 $1.000 $1.050 $0.500 $0.430 $0.400 $0.500 $1.200 $0.550 $1.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 4,905.000 $1.000 $0.210 $0.400 $0.430 $0.400 $0.500 $0.240 $0.550 $1.000
REFL PAV MRK TY II (W) 8" (SLD)
LF 1,110.000 $1.000 $0.420 $0.650 $0.640 $0.600 $0.500 $0.470 $0.830 $6.000
REFL PAV MRK TY II (W) 12" (SLD)
LF 50.000 $4.000 $2.110 $2.100 $2.130 $2.000 $2.500 $2.400 $2.750 $6.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 185.000 $8.000 $3.160 $3.200 $3.190 $3.000 $3.500 $3.500 $4.130 $20.000
REFL PAV MRK TY II (W) (ARROW)
EA 8.000 $150.000 $73.690 $60.000 $61.670 $58.000 $91.500 $82.000 $79.820 $250.000
REFL PAV MRK TY II (W) (DBL ARROW)
EA 1.000 $250.000 $89.480 $90.000 $85.060 $80.000 $91.500 $100.000 $110.090 $250.000
REFL PAV MRK TY II (W) (WORD)
EA 8.000 $150.000 $84.220 $65.000 $65.930 $62.000 $91.500 $95.000 $85.320 $250.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 7,095.000 $1.000 $0.210 $0.400 $0.390 $0.380 $0.500 $0.250 $0.520 $1.000
REFL PAV MRK TY II (Y) 12" (SLD)
LF 155.000 $1.500 $2.110 $1.800 $1.810 $1.700 $2.500 $2.400 $2.340 $6.000
PAVEMENT SEALER 4"
LF 12,065.000 $1.000 $0.160 $0.250 $0.260 $0.240 $0.500 $0.180 $0.330 $1.000
PAVEMENT SEALER 8"
LF 1,110.000 $1.000 $0.210 $0.350 $0.320 $0.300 $0.500 $0.250 $0.410 $3.000
PAVEMENT SEALER 12"
LF 100.000 $1.000 $1.050 $0.500 $0.430 $0.400 $2.500 $1.200 $0.550 $6.000
PAVEMENT SEALER 24"
LF 185.000 $1.000 $2.110 $0.800 $0.800 $0.750 $3.500 $2.500 $1.030 $6.000
PAVEMENT SEALER (ARROW)
EA 8.000 $15.000 $26.320 $20.000 $21.270 $20.000 $91.500 $30.000 $27.520 $250.000
PAVEMENT SEALER (WORD)
EA 8.000 $15.000 $31.580 $20.000 $21.270 $20.000 $91.500 $35.000 $27.520 $250.000
PAVEMENT SEALER (DBL ARROW)
EA 1.000 $15.000 $36.840 $25.000 $25.520 $24.000 $91.500 $45.000 $33.030 $250.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,665.000 $1.000 $1.050 $0.800 $0.830 $0.780 $1.000 $1.200 $1.070 $1.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 4,905.000 $1.000 $1.050 $0.700 $0.730 $0.690 $1.000 $1.200 $0.950 $1.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 3,620.000 $1.000 $1.050 $0.800 $0.790 $0.740 $1.000 $1.200 $1.020 $1.000
REFL PAV MRKR TY I-C
EA 74.000 $5.000 $5.260 $4.200 $4.250 $4.000 $5.000 $6.000 $5.500 $5.000
REFL PAV MRKR TY II-A-A
EA 224.000 $5.000 $5.260 $4.200 $4.250 $4.000 $5.000 $6.000 $5.500 $5.000
TREE TRIMMING
MI 0.500 $7,500.000 $12,632.260 $14,000.000 $15,949.500 $30,000.000 $8,788.000 $9,000.000 $4,277.880 $20,000.000
TREE REMOVAL (4" - 12" DIA)
EA 19.000 $1,000.000 $842.150 $350.000 $212.660 $400.000 $366.000 $1,500.000 $1,535.120 $2,500.000
TREE REMOVAL (12" - 18" DIA)
EA 33.000 $1,200.000 $842.150 $590.000 $637.980 $800.000 $1,098.500 $1,700.000 $914.300 $2,850.000
TREE REMOVAL (18" - 24" DIA)
EA 13.000 $1,400.000 $1,052.690 $790.000 $956.970 $1,200.000 $1,464.500 $2,000.000 $1,872.660 $3,000.000
TREE REMOVAL (24" - 30" DIA)
EA 11.000 $1,600.000 $1,052.690 $1,300.000 $1,275.960 $1,600.000 $1,831.000 $2,200.000 $1,982.610 $5,000.000
D-GR HMA TY-B PG64-22
TON 4,797.000 $75.000 $74.000 $80.000 $76.900 $72.800 $91.500 $77.000 $100.180 $90.000
D-GR HMA TY-B PG70-22
TON 35.000 $100.000 $120.000 $120.000 $196.710 $275.000 $234.000 $200.000 $378.440 $200.000
SP MIXES SP-C SAC-A PG70-28
TON 2,076.000 $100.000 $102.000 $125.000 $111.650 $98.650 $133.000 $105.000 $135.760 $125.000
TACK COAT
GAL 2,772.000 $3.000 $3.730 $3.500 $3.300 $2.800 $4.000 $3.100 $3.850 $8.000
WROUGHT IRON FENCE
LF 110.000 $200.000 $52.630 $69.000 $175.440 $225.000 $94.500 $185.000 $344.040 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $8,600.000 $6,900.000 $17,500.000 $6,500.000 $337.500 $25,000.000 $12,777.480 $16,500.000
TMA (STATIONARY)
DAY 55.000 $180.000 $228.480 $160.000 $157.500 $300.000 $1,027.500 $350.000 $217.450 $350.000
REMOVE FIRE HYDRANT
EA 1.000 $600.000 $473.710 $800.000 $744.310 $1,100.000 $1,267.500 $600.000 $1,376.140 $2,500.000
REMOVE WATER VALVE AND BOX
EA 3.000 $200.000 $368.440 $600.000 $531.650 $500.000 $1,104.000 $415.000 $1,376.140 $250.000
REMOVE WATER METER AND VAULT
EA 1.000 $2,100.000 $1,368.490 $1,600.000 $2,232.930 $100.000 $507.000 $1,525.000 $1,376.140 $250.000
CUT AND PLUG WATER MAIN (6")
EA 2.000 $1,500.000 $1,579.030 $1,300.000 $8,612.730 $650.000 $3,746.500 $2,000.000 $3,440.360 $1,500.000
REMOVE WATER METER
EA 15.000 $750.000 $473.710 $300.000 $74.430 $100.000 $313.000 $575.000 $1,376.140 $250.000
POST CONSTRUCTION TELEVISION INSPECTION
LF 3,125.000 $5.000 $5.260 $3.000 $1.060 $1.000 $3.000 $7.000 $6.880 $3.000
GATE VALVE & BOX (12")
EA 12.000 $4,500.000 $3,158.060 $3,900.000 $3,296.230 $6,000.000 $4,426.000 $3,600.000 $5,184.210 $8,000.000
RECONNECT EXISTING WATER SERVICE
EA 17.000 $800.000 $2,315.910 $900.000 $457.220 $800.000 $422.500 $2,600.000 $2,064.220 $1,500.000
INSTALL FIRE HYDRANT
EA 5.000 $9,500.000 $3,789.680 $4,500.000 $6,486.130 $3,000.000 $5,763.500 $4,400.000 $11,464.800 $4,500.000
6" GATE VALVE
EA 8.000 $1,750.000 $1,579.030 $1,900.000 $1,408.870 $1,200.000 $2,645.500 $2,000.000 $2,540.360 $3,150.000
8" GATE VALVE
EA 2.000 $2,250.000 $1,789.570 $2,200.000 $1,807.610 $1,600.000 $3,067.500 $2,000.000 $3,642.270 $3,850.000
10" GATE VALVE
EA 1.000 $2,500.000 $3,684.410 $2,900.000 $2,551.920 $4,000.000 $3,654.500 $5,000.000 $5,476.060 $6,500.000
FLOWABLE BACKFILL
CY 210.000 $200.000 $168.430 $140.000 $239.240 $100.000 $133.500 $195.000 $275.230 $350.000
INSTALL FIRE HYDRANT EXTENSION
EA 3.000 $1,250.000 $1,579.030 $2,200.000 $531.650 $3,000.000 $1,473.000 $1,850.000 $1,376.140 $1,500.000
CONNECT TO EXISTING WATER LINES
EA 8.000 $2,500.000 $6,421.400 $1,300.000 $4,200.040 $500.000 $3,510.500 $7,550.000 $2,064.220 $1,500.000
WATER MAIN (PVC)(DR 18 C900) (6")
LF 180.000 $80.000 $63.160 $100.000 $80.810 $150.000 $97.500 $80.000 $68.810 $48.000
WATER MAIN (PVC)(DR 18 C900) (8")
LF 20.000 $90.000 $68.420 $140.000 $88.250 $210.000 $109.000 $80.000 $82.570 $58.000
WATER MAIN (PVC)(DR 18 C900) (12")
LF 2,480.000 $130.000 $94.740 $99.000 $105.270 $185.000 $97.500 $130.000 $96.330 $85.000
INSTALL WATER SERVICE LINE
EA 17.000 $2,000.000 $1,736.940 $900.000 $3,110.150 $1,000.000 $1,358.500 $2,000.000 $4,847.700 $1,500.000
WATER LINE FITTINGS (GENERAL)(6")
TON 1.000 $10,000.000 $7,579.350 $6,000.000 $4,519.030 $6,700.000 $13,371.000 $8,500.000 $16,513.730 $8,500.000
WATER LINE FITTINGS (GENERAL)(8")
TON 1.000 $12,000.000 $7,579.350 $6,000.000 $2,870.910 $6,700.000 $13,371.000 $8,500.000 $16,513.730 $8,500.000
WATER LINE FITTINGS (GENERAL)(12")
TON 1.000 $14,000.000 $7,579.350 $6,000.000 $67,147.400 $6,700.000 $13,371.000 $8,500.000 $16,513.730 $8,500.000
WATER LINE FITTINGS(GENERAL)(SERV LINE)
TON 1.000 $5,000.000 $3,158.060 $6,000.000 $1,275.960 $6,700.000 $13,371.000 $3,500.000 $16,513.730 $8,500.000
PROCODER T-10 NEPTUNE MODEL WATER METER
EA 15.000 $500.000 $2,631.720 $1,900.000 $287.090 $1,200.000 $641.000 $3,000.000 $3,440.360 $6,500.000
CONNECTION TO EXISTING MANHOLE(SANSEWR)
EA 1.000 $4,500.000 $1,579.030 $1,400.000 $4,412.700 $1,500.000 $7,491.000 $2,000.000 $2,064.220 $2,500.000
EPOXY MANHOLE LINER
LF 70.000 $15.000 $235.800 $190.000 $318.990 $40.000 $366.000 $275.000 $275.230 $450.000
REMOVE EXISTING WASTEWATER MANHOLES
EA 1.000 $1,000.000 $578.980 $1,400.000 $3,881.050 $1,500.000 $3,724.000 $645.000 $1,376.140 $2,500.000
REMOVE EXISTING WASTEWATER LINE (8")
EA 175.000 $20.000 $18.950 $90.000 $63.800 $35.000 $85.000 $25.000 $68.810 $35.000
SANSWR (10IN)(PVC)(SDR 18)(RESJT)
LF 205.000 $150.000 $136.850 $190.000 $223.290 $275.000 $300.000 $155.000 $344.040 $100.000
MANHOLE (SAN SEWER)(4' DIA)
EA 2.000 $7,000.000 $7,684.620 $12,000.000 $9,559.070 $8,000.000 $9,035.000 $9,500.000 $13,761.440 $10,000.000
VACUUM EXCAVATION
HR 36.000 $1,000.000 $463.180 $150.000 $372.160 $265.000 $390.500 $525.000 $1,376.140 $250.000
CONNECT TO EXISTING SEWER LINE
EA 5.000 $2,500.000 $736.880 $900.000 $1,515.200 $700.000 $2,578.500 $900.000 $2,752.290 $1,500.000
ADJUSTING MANHOLES (SANITARY SEWER)
EA 6.000 $2,000.000 $3,158.060 $2,400.000 $956.970 $1,000.000 $1,642.500 $3,700.000 $3,440.360 $2,500.000
Totals: $4,046,661.000 $3,972,278.790 $3,992,102.350 $4,079,102.650 $4,208,935.770 $4,305,067.500 $4,751,122.000 $5,192,221.400 $5,514,786.000