SUTTON US 277 (0160-01-036)

Items: 99

County: SUTTON
Length: N/A
Highway: US 277
District: SAN ANGELO
Control Number: 0160-01-036
DBE Goal: N/A
Project: F 2021(598)
Guaranty: N/A
Time: 178 WORKING DAYS
Engineer's Estimate: $8,510,241.09
Date: 06/04/2021 (5 years ago)
Contract Number: N/A
Type: ADD PASSING LANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$8,510,241.09
$8,455,478.51
Over/Under Est: -0.64% -$54,762.58
Over/Under Est: 5.26% $447,518.86
Amt Left: 5.94% $502,281.44
$9,834,265.44
Over/Under Est: 15.56% $1,324,024.35
Amt Left: 16.31% $1,378,786.93
Delta: -9.78% -$876,505.49

Bid Items & Bid Tabulations

99 Total 0 of 99
SUTTON  |  US 277  |  SAN ANGELO  |  0160-01-036  |  06/04/2021  |  $8,510,241.09  |  F 2021(598)  |  ADD PASSING LANES  |  178 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN KELLER COMPANY
HUNTER INDUSTRIES, LTD.
REECE ALBERT, INC.
PREPARING ROW
STA 453.000 $300.000 $220.000 $710.910 $291.380
REMOVING CONC (DRIVEWAYS)
SY 209.000 $16.000 $8.800 $12.270 $15.840
REMOVING STAB BASE AND ASPH PAV (0-4")
SY 581.000 $5.000 $5.800 $9.990 $3.980
EXCAVATION (ROADWAY)
CY 10,064.000 $15.000 $20.300 $16.650 $26.390
EXCAVATION (CHANNEL)
CY 102.900 $50.000 $36.750 $27.180 $67.730
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 7,329.000 $15.000 $8.000 $16.650 $11.560
BACKFILL (TY A OR B)
STA 453.000 $180.000 $175.000 $128.850 $168.280
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 18.200 $470.000 $1,080.000 $871.000 $739.840
DRILL SEEDING (PERM)(WARM OR COOL)
SY 88,000.000 $0.180 $0.260 $0.210 $0.180
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 11,578.000 $45.000 $39.000 $46.740 $41.660
ASPH (AC-20-5TR)
GAL 88,075.000 $3.000 $3.500 $3.950 $3.800
ASPH (RC-250)
GAL 4,818.000 $5.000 $4.400 $5.230 $4.710
AGGR(TY-B GR-4 SAC-B)
CY 2,960.000 $80.000 $45.000 $67.640 $85.850
AGGR(TY-PB GR-5 SAC-B)
CY 156.000 $140.000 $123.000 $96.970 $205.760
LRA PAV TY-I GR-A
TON 536.000 $100.000 $82.000 $90.180 $161.150
LRA PAV TY-I GR-D
TON 3,995.000 $95.000 $88.000 $90.180 $146.430
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 4,832.000 $50.000 $50.000 $46.170 $67.970
PLAN & TEXT ASPH CONC PAV(0" TO 3")
SY 5,545.000 $6.000 $6.900 $2.850 $8.900
PLANE ASPH CONC PAV (3")
SY 1,000.000 $6.000 $6.500 $4.130 $14.030
TEMPORARY SPL SHORING
SF 1,941.400 $18.000 $18.550 $15.750 $23.780
RIPRAP (CONC)(5 IN)
CY 317.600 $550.000 $620.000 $524.990 $533.740
RIPRAP (STONE TY R)(DRY)(12 IN)
CY 112.000 $195.000 $200.000 $149.800 $320.300
RIPRAP (STONE PROTECTION)(12 IN)
CY 90.000 $177.000 $200.000 $149.800 $353.520
CLEANING AND SEALING EXISTING JOINTS
LF 1,228.000 $60.000 $34.500 $23.720 $24.840
CMP (GAL STL 18 IN)
LF 64.000 $60.000 $86.500 $73.500 $63.410
CMP AR (GAL STL DES 1)
LF 100.000 $80.000 $93.000 $78.750 $73.980
CONC BOX CULV (3 FT X 2 FT)
LF 65.000 $600.000 $465.000 $393.750 $628.860
CONC BOX CULV (5 FT X 2 FT)
LF 19.000 $800.000 $620.000 $524.990 $834.960
CONC BOX CULV (7 FT X 3 FT)
LF 14.000 $450.000 $700.000 $603.740 $930.080
CONC BOX CULV (8 FT X 5 FT)
LF 12.000 $500.000 $850.000 $734.990 $1,152.030
CONC BOX CULV (10 FT X 5 FT)
LF 13.000 $500.000 $1,110.000 $944.990 $1,321.140
WINGWALL (FW - 0) (HW=3 FT)
EA 4.000 $5,000.000 $8,050.000 $6,824.930 $6,500.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $8,800.000 $14,250.000 $12,074.880 $8,666.660
WINGWALL (FW - 0) (HW=7 FT)
EA 2.000 $9,500.000 $14,850.000 $12,599.880 $10,045.930
WINGWALL (PW - 1) (HW=3 FT)
EA 2.000 $6,750.000 $13,600.000 $11,549.890 $9,047.150
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $11,100.000 $15,500.000 $13,124.870 $10,405.280
WINGWALL (PW - 1) (HW=5 FT)
EA 3.000 $13,500.000 $22,900.000 $19,424.810 $11,256.090
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $19,000.000 $27,870.000 $23,624.770 $26,422.760
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 4.000 $990.000 $2,230.000 $1,889.980 $1,268.290
SET (TY II) (DES 1) (CMP) (6: 1) (P)
EA 2.000 $2,750.000 $2,475.000 $2,099.980 $4,439.030
CLEAN EXIST CULVERTS
EA 7.000 $2,000.000 $2,475.000 $2,099.980 $2,272.360
REMOV STR (SET)
EA 2.000 $390.000 $1,240.000 $1,049.990 $1,062.200
REMOV STR (WINGWALL)
EA 12.000 $2,500.000 $1,850.000 $1,574.980 $1,321.140
REMOV STR (HEADWALL)
EA 2.000 $1,065.000 $1,480.000 $1,259.990 $1,062.200
REMOV STR (PIPE)
EA 1.000 $400.000 $500.000 $420.000 $2,642.280
MOBILIZATION
LS 1.000 $647,000.000 $600,000.000 $890,000.000 $487,877.260
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $10,000.000 $15,000.000 $10,000.000 $14,113.260
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,834.000 $32.000 $30.000 $34.750 $32.760
ROCK FILTER DAMS (REMOVE)
LF 1,834.000 $10.000 $8.000 $13.000 $9.510
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $30.000 $40.000 $33.760 $31.710
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $10.000 $12.000 $11.000 $10.570
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,811.000 $3.000 $4.000 $2.950 $3.700
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,811.000 $0.500 $0.750 $0.610 $0.790
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 7,800.000 $1.500 $4.000 $3.000 $4.970
BIODEG EROSN CONT LOGS (REMOVE)
LF 7,800.000 $2.500 $1.000 $1.000 $1.060
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 300.000 $60.000 $40.000 $57.260 $37.950
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,800.000 $15.000 $13.000 $18.340 $20.310
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 300.000 $30.000 $24.000 $37.930 $28.290
DRIVEWAYS (CONC)
SY 174.000 $93.750 $120.000 $105.000 $143.000
DRIVEWAYS (ACP)
SY 1,945.000 $40.000 $29.000 $35.040 $37.220
RUMBLE STRIPS (SHOULDER)
LF 52,824.000 $0.200 $0.210 $0.100 $0.170
RUMBLE STRIPS (CENTERLINE)
LF 12,618.000 $0.180 $0.400 $0.200 $0.340
MTL W-BEAM GD FEN (STEEL POST)
LF 9,775.000 $25.000 $31.000 $27.100 $28.640
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $1,845.000 $2,380.000 $2,026.000 $2,141.300
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 300.000 $55.000 $65.000 $67.030 $70.840
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,050.000 $945.000 $1,069.000 $1,129.840
REMOVE METAL BEAM GUARD FENCE
LF 3,412.000 $1.300 $1.500 $2.000 $2.110
REMOVE TERMINAL ANCHOR SECTION
EA 13.000 $200.000 $245.000 $245.000 $258.940
GUARDRAIL END TREATMENT (INSTALL)
EA 44.000 $2,600.000 $3,365.000 $2,684.000 $2,836.750
GUARDRAIL END TREATMENT (REMOVE)
EA 13.000 $230.000 $250.000 $245.000 $258.940
CRASH CUSH ATTEN (MOVE & RESET)
EA 24.000 $1,200.000 $1,600.000 $795.000 $978.050
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $1,000.000 $1,140.000 $795.000 $978.020
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $8,500.000 $10,400.000 $7,600.000 $9,174.610
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $658.000 $1,235.000 $723.020 $1,056.910
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,300.000 $1,850.000 $1,300.260 $1,056.910
REMOVE SM RD SN SUP&AM
EA 3.000 $110.000 $380.000 $137.290 $270.920
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 32.000 $30.000 $45.000 $21.600 $52.860
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 40.000 $32.000 $45.000 $30.450 $52.860
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 115.000 $32.000 $45.000 $28.890 $52.860
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 39,416.000 $0.600 $0.620 $0.500 $0.530
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 39,416.000 $0.650 $0.680 $0.550 $0.580
REFL PAV MRK TY I (W)4"(DOT)(090MIL)
LF 700.000 $0.850 $0.740 $0.600 $0.630
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 285.000 $0.800 $1.000 $0.800 $0.850
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 520.000 $10.000 $8.670 $7.000 $7.400
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 3,750.000 $0.350 $0.400 $0.320 $0.340
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 90,556.000 $0.350 $0.380 $0.310 $0.330
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 6,837.000 $0.350 $0.380 $0.310 $0.330
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 57,142.000 $0.350 $0.370 $0.300 $0.320
PREFAB PAV MRK TY C (W) (ARROW)
EA 9.000 $260.000 $335.000 $270.000 $285.370
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 4.000 $550.000 $625.000 $505.000 $533.740
PREFAB PAV MRK TY C (W) (WORD)
EA 3.000 $320.000 $335.000 $270.000 $285.370
REFL PAV MRKR TY I-C
EA 204.000 $4.000 $4.750 $3.850 $4.070
REFL PAV MRKR TY II-A-A
EA 1,062.000 $4.000 $4.340 $3.850 $3.700
ELIM EXT PAV MRK & MRKS (4")
LF 39,416.000 $0.250 $0.620 $0.500 $0.530
SP MIXES SP-C SAC-B PG70-22
TON 42,652.000 $90.000 $87.500 $90.080 $108.930
TACK COAT
GAL 12,583.000 $3.500 $3.000 $3.380 $2.060
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 356.000 $60.000 $65.000 $75.000 $118.110
TMA (STATIONARY)
DAY 178.000 $175.000 $180.000 $150.000 $273.970
TMA (MOBILE OPERATION)
HR 100.000 $70.000 $180.000 $150.000 $62.570
Totals: $8,510,241.090 $8,455,478.515 $8,957,759.956 $9,834,265.461