SUTTON IH 10 (0141-02-033)

Items: 68

County: SUTTON
Length: N/A
Highway: IH 10
District: SAN ANGELO
Control Number: 0141-02-033
DBE Goal: N/A
Project: C 141-2-33
Guaranty: N/A
Time: 221 WORKING DAYS
Engineer's Estimate: $21,507,910.30
Date: 11/03/2022 (3 years ago)
Contract Number: N/A
Type: ACP OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$21,507,910.30
$21,298,153.59
Over/Under Est: -0.98% -$209,756.71
$22,839,592.65
Over/Under Est: 6.19% $1,331,682.35
Amt Left: 7.24% $1,541,439.06
$24,793,848.44
Over/Under Est: 15.28% $3,285,938.14
Amt Left: 16.41% $3,495,694.85
Delta: -8.56% -$1,954,255.79
$24,957,468.27
Over/Under Est: 16.04% $3,449,557.97
Amt Left: 17.18% $3,659,314.68
Delta: -0.66% -$163,619.83
Subcontractor Percentage Amount
RPV CONSTRUCTION, LLC 3.64% $775,252.79
NICKEL ROCK, LLC 2.81% $598,478.12
BLB CONSTRUCTION, LLC 2.76% $587,829.04
K. L. DURHAM CONSTRUCTION, L.L.C. 2.41% $513,285.50
TRP CONSTRUCTION GROUP, LLC 1.99% $423,833.26
SCR CIVIL CONSTRUCTION, LLC 1.05% $223,630.61
BARRICADES UNLIMITED 0.31% $66,024.28
WEST TEXAS ROCK RESOURCES, LLC 0.09% $19,168.34
Total: 15.06% $3,207,501.94

Bid Items & Bid Tabulations

68 Total 0 of 68
SUTTON  |  IH 10  |  SAN ANGELO  |  0141-02-033  |  11/03/2022  |  $21,507,910.30  |  C 141-2-33  |  ACP OVERLAY  |  221 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
DELHUR INDUSTRIES, INC.
RK HALL, LLC
ALLEN KELLER COMPANY
HUNTER INDUSTRIES, LTD.
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 2,503.000 $20.000 $12.000 $79.670 $25.000 $18.000
BACKFILL (TY B)
STA 961.000 $120.000 $240.000 $255.000 $170.000 $125.100
FOG SEAL (CSS-1H)
GAL 10,750.000 $3.000 $3.535 $7.370 $7.200 $3.940
ASPH (AC-20-5TR)
GAL 217,690.000 $3.250 $4.338 $4.600 $4.270 $5.020
AGGR(TY-PB GR-4 SAC-B)
CY 5,110.000 $100.000 $125.007 $144.270 $155.000 $145.800
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 2,800.000 $95.000 $91.116 $130.940 $123.000 $124.150
PLANE ASPH CONC PAV(0" TO 1")
SY 10,834.000 $3.000 $0.813 $7.860 $1.700 $1.850
PLANE ASPH CONC PAV(0" TO 2")
SY 2,290.000 $6.580 $1.539 $13.110 $3.900 $1.850
PLANE ASPH CONC PAV (1")
SY 246,742.000 $1.300 $1.638 $1.340 $1.290 $1.640
PLANE ASPH CONC PAV (2")
SY 2,664.000 $1.450 $1.363 $6.140 $2.600 $2.390
PLANE ASPH CONC PAV (3")
SY 141,738.000 $2.000 $0.890 $2.480 $2.550 $2.390
PLANE ASPH CONC PAV (4")
SY 624.000 $2.800 $4.674 $17.580 $4.950 $3.470
PLANE ASPH CONC PAV (2"-3")
SY 4,992.000 $4.250 $0.857 $6.870 $3.090 $2.390
PLANE ASPH CONC PAV (1/2")
SY 20,586.000 $4.250 $0.835 $2.920 $1.450 $1.850
PLANE ASPH CONC PAV(1" TO 2")
SY 3,826.000 $5.250 $1.033 $4.290 $2.400 $1.960
PLANE ASPH CONC PAV (3" TO 4")
SY 1,248.000 $5.250 $2.474 $19.880 $5.100 $6.710
RIPRAP (MOW STRIP)(4 IN)
CY 1,273.000 $550.000 $770.000 $825.000 $660.000 $788.110
CLEANING EXISTING JOINTS
LF 2,612.000 $18.000 $3.300 $10.730 $7.500 $10.280
HEADER TYPE EXPANSION JOINT
LF 2,612.000 $135.000 $88.000 $73.940 $190.000 $70.870
MOBILIZATION
LS 1.000 $1,525,355.290 $1,026,344.000 $869,755.670 $2,000,000.000 $2,494,364.940
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $10,000.000 $22,837.800 $13,865.470 $40,000.000 $6,500.000
RUMBLE STRIPS (SHOULDER)
LF 213,167.000 $0.150 $0.099 $0.100 $0.250 $0.170
MTL W-BEAM GD FEN (STEEL POST)
LF 20,645.000 $35.000 $32.505 $33.610 $36.000 $38.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 28.000 $1,815.000 $1,457.500 $1,625.980 $1,600.000 $1,550.000
REMOVE METAL BEAM GUARD FENCE
LF 18,695.000 $3.000 $1.650 $3.300 $2.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 28.000 $250.000 $192.500 $302.390 $210.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 28.000 $3,000.000 $3,580.500 $3,552.140 $4,000.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 28.000 $300.000 $247.500 $302.390 $270.000 $375.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 226.000 $35.000 $7.700 $13.230 $14.500 $35.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 9.000 $30.000 $7.700 $13.230 $14.500 $45.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 38.000 $100.000 $170.500 $60.820 $70.000 $100.000
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND
EA 32.000 $142.000 $170.500 $63.930 $70.000 $85.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND
EA 29.000 $60.000 $170.500 $65.490 $72.000 $95.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 219,647.000 $0.400 $0.220 $0.200 $0.250 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 219,647.000 $0.270 $0.220 $0.200 $0.250 $0.200
WK ZN PAV MRK REMOV (W)4"(SLD W/MRKR)
LF 5,760.000 $1.200 $1.650 $1.080 $1.800 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 250.000 $1.000 $5.500 $9.540 $1.790 $1.490
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 562.000 $0.450 $5.500 $8.550 $1.790 $1.490
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 2,600.000 $1.000 $1.100 $1.160 $1.200 $1.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 28,970.000 $0.150 $0.275 $0.170 $0.300 $0.250
REFL PAV MRK TY II (W) 4" (SLD)
LF 115,965.000 $0.150 $0.198 $0.170 $0.220 $0.180
REFL PAV MRK TY II (W) 8" (SLD)
LF 2,600.000 $0.350 $0.550 $0.350 $0.600 $0.500
REFL PAV MRK TY II (Y) 4" (SLD)
LF 116,240.000 $0.150 $0.198 $0.170 $0.220 $0.180
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 28,970.000 $0.400 $0.495 $0.610 $0.500 $0.450
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 115,965.000 $0.400 $0.440 $0.560 $0.480 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 116,240.000 $0.400 $0.440 $0.560 $0.480 $0.400
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 41.000 $25.000 $27.500 $27.500 $0.300 $25.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 2.000 $220.000 $550.000 $275.000 $600.000 $500.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 6.000 $40.000 $110.000 $27.500 $120.000 $100.000
PREFAB PAV MRK TY C (Y) (12") (SLD)
LF 610.000 $6.500 $8.800 $7.700 $9.600 $8.000
REFL PAV MRKR TY I-R
EA 56.000 $5.000 $4.950 $6.600 $5.400 $4.500
REFL PAV MRKR TY II-A-A
EA 73.000 $5.000 $4.950 $6.600 $5.400 $4.500
REFL PAV MRKR TY II-C-R
EA 1,398.000 $5.000 $4.950 $4.950 $5.400 $4.500
ELIM EXT PAV MRK & MRKS (4")
LF 445,055.000 $0.500 $0.385 $0.460 $0.240 $0.200
SP MIXES SP-C SAC-B PG70-22
TON 16,989.000 $115.000 $100.899 $148.810 $135.000 $120.600
TACK COAT
GAL 9,110.000 $3.500 $3.480 $5.340 $6.340 $4.340
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 55,920.000 $155.000 $152.389 $172.090 $180.000 $172.440
TACK COAT
GAL 28,870.000 $3.500 $3.480 $5.180 $6.350 $4.340
CEMENT
TON 707.000 $259.210 $281.600 $0.000 $366.000 $291.600
EMULSION
GAL 644,111.000 $3.850 $3.388 $0.000 $4.100 $3.910
EMUL TRTMNT (MX EXST MTRL) 9"
SY 150,198.000 $2.890 $5.436 $0.000 $3.200 $3.510
FILLING MILLED ASPHALT RUMBLE STRIPS
LF 213,167.000 $4.000 $4.852 $1.260 $0.750 $5.040
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 200.000 $100.000 $93.500 $118.730 $190.000 $450.000
TMA (STATIONARY)
DAY 194.000 $150.000 $275.000 $412.940 $200.000 $750.000
TMA (MOBILE OPERATION)
DAY 90.000 $200.000 $275.000 $583.590 $1,600.000 $1,250.000
1
CEMENT
TON 707.000 $260.030 $0.000 $466.560 $0.000 $0.000
1
ASPHALT BINDER (PG 64-22)
TON 1,671.000 $1,249.990 $0.000 $1,000.000 $0.000 $0.000
1
FOAMED ASPHALT TREAT (9")(DC)
SY 150,198.000 $5.490 $0.000 $4.680 $0.000 $0.000
Totals: $24,605,071.340 $21,298,153.654 $22,839,592.650 $24,793,848.440 $24,957,468.270