STERLING CR (0907-11-006)

Items: 55

County: STERLING
Length: N/A
Highway: CR
District: SAN ANGELO
Control Number: 0907-11-006
DBE Goal: N/A
Project: BR 1702(584)
Guaranty: N/A
Time: 132 WORKING DAYS
Engineer's Estimate: $1,274,063.50
Date: 07/09/2019 (6 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,274,063.50
$1,323,346.40
Over/Under Est: 3.87% $49,282.90
$1,477,210.02
Over/Under Est: 15.94% $203,146.52
Amt Left: 11.63% $153,863.62
Over/Under Est: 20.17% $256,991.10
Amt Left: 15.7% $207,708.20
Delta: -3.65% -$53,844.58
Over/Under Est: 73.05% $930,688.85
Amt Left: 66.6% $881,405.95
Delta: -44.00% -$673,697.75

Bid Items & Bid Tabulations

55 Total 0 of 55
STERLING  |  CR  |  SAN ANGELO  |  0907-11-006  |  07/09/2019  |  $1,274,063.50  |  BR 1702(584)  |  BRIDGE REPL  |  132 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACME BRIDGE COMPANY, INC.
RELMCO, INC.
TALBRAN ENTERPRISES LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREPARING ROW
STA 16.130 $2,200.000 $3,000.000 $2,000.000 $270.000 $1,094.550
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 2.000 $1,000.000 $5,000.000 $1,500.000 $1,350.000 $2,993.040
REMOVING CONC (RIPRAP)
SY 336.000 $40.000 $13.200 $30.000 $13.500 $44.710
OBLITERATING ABANDONED ROAD
SY 179.000 $5.500 $4.700 $60.000 $20.250 $99.840
EXCAVATION (ROADWAY)
CY 188.000 $25.000 $41.600 $20.000 $16.200 $61.530
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 2,482.000 $35.000 $26.600 $18.000 $22.950 $30.480
FURNISHING AND PLACING TOPSOIL (4")
SY 3,084.000 $6.000 $3.800 $6.000 $2.700 $9.180
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 3,084.000 $1.000 $1.400 $1.000 $2.700 $0.330
BROADCAST SEED (TEMP) (WARM)
SY 1,542.000 $1.000 $1.400 $1.000 $1.350 $0.390
BROADCAST SEED (TEMP) (COOL)
SY 1,542.000 $1.000 $1.400 $1.000 $1.350 $0.390
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 323.000 $3.000 $3.450 $5.000 $6.750 $3.300
PROOF ROLLING
HR 5.000 $200.000 $82.700 $85.000 $135.000 $142.240
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 1,755.000 $20.000 $23.000 $30.000 $54.000 $35.430
CEM STABIL BKFL
CY 51.000 $220.000 $165.000 $200.000 $370.000 $243.530
TEMPORARY SPL SHORING
SF 587.000 $60.000 $50.100 $55.000 $40.500 $96.600
DRILL SHAFT (36 IN)
LF 306.000 $205.000 $320.000 $750.000 $438.750 $626.500
CL C CONC (ABUT)
CY 34.400 $1,200.000 $1,150.000 $1,105.000 $1,620.000 $1,772.950
CL C CONC (CAP)
CY 26.100 $1,500.000 $950.000 $1,378.000 $1,417.500 $2,291.440
CL C CONC (COLUMN)
CY 18.400 $1,250.000 $950.000 $1,196.000 $1,485.000 $2,035.580
REINF CONC SLAB
SF 5,700.000 $34.000 $22.000 $23.400 $26.330 $36.030
APPROACH SLAB
CY 44.900 $600.000 $600.000 $891.800 $1,080.000 $1,194.780
PRESTR CONC GIRDER (TX28)
LF 754.000 $165.000 $259.000 $175.000 $216.000 $187.480
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 99.000 $300.000 $218.000 $175.000 $337.500 $312.540
RIPRAP (STONE PROTECTION)(12 IN)
CY 349.000 $125.000 $207.000 $175.000 $337.500 $341.290
RAIL (TY T66)
LF 412.000 $200.000 $175.000 $150.000 $202.500 $193.600
ARMOR JOINT
LF 52.000 $125.000 $100.000 $75.000 $135.000 $154.190
MOBILIZATION
LS 1.000 $130,000.000 $115,000.000 $150,000.000 $170,000.000 $496,487.820
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $8,000.000 $7,300.000 $6,500.000 $4,000.000 $1,287.530
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 145.000 $35.000 $22.500 $50.000 $67.500 $25.420
ROCK FILTER DAMS (REMOVE)
LF 145.000 $10.000 $11.300 $30.000 $6.750 $13.430
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $30.000 $22.500 $30.000 $33.750 $23.130
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $11.300 $25.000 $9.450 $12.130
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,849.000 $10.000 $11.300 $15.000 $8.100 $11.650
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,849.000 $2.000 $2.250 $10.000 $1.350 $2.300
CONSTRUCTING DETOURS
SY 897.000 $52.000 $103.000 $68.000 $135.000 $264.960
MTL W-BEAM GD FEN (STEEL POST)
LF 75.000 $40.000 $56.200 $100.000 $47.250 $37.550
MTL BEAM GD FEN TRANS (TL2)
EA 2.000 $1,300.000 $562.000 $1,900.000 $2,025.000 $1,793.130
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,300.000 $1,350.000 $2,100.000 $2,025.000 $1,875.630
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $950.000 $1,350.000 $2,100.000 $1,350.000 $1,545.630
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,400.000 $2,810.000 $2,500.000 $4,320.000 $3,498.130
CHAIN LINK FENCE (INSTALL) (6')
LF 28.000 $25.000 $16.900 $100.000 $47.250 $117.950
CHAIN LINK FENCE GATE (INSTALL)(6'X4')
EA 2.000 $125.000 $225.000 $900.000 $1,350.000 $2,068.130
WIRE FENCE (WATER GAP)
LF 285.000 $80.000 $45.000 $80.000 $81.000 $55.620
CONDT (PVC) (SCH 40) (2")
LF 294.000 $15.000 $5.600 $15.000 $13.500 $17.100
GROUND BOX TY A (122311)
EA 2.000 $700.000 $562.000 $900.000 $1,620.000 $1,738.130
REMOVE SM RD SN SUP&AM
EA 6.000 $120.000 $112.000 $150.000 $135.000 $194.380
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 16.000 $30.000 $22.500 $30.000 $47.250 $33.020
INSTL OM ASSM (OM-2Y)(WC)GND
EA 4.000 $90.000 $84.400 $150.000 $101.250 $137.570
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $50.000 $22.500 $150.000 $54.000 $66.030
GRAFFITI REMOVAL (BLAST CLEANING)
SF 300.000 $12.000 $4.500 $40.000 $6.750 $23.480
GRAFFITI REMOVAL (CHEMICAL CLEANING)
SF 50.000 $15.000 $11.300 $40.000 $27.000 $125.640
REP STL BRIDGE MEMBER (TRUSS RAIL)
EA 1.000 $2,500.000 $3,070.000 $3,500.000 $4,050.000 $28,821.120
REP STL BRDG MEMB (PACK RUST REMOVAL)
LS 1.000 $7,000.000 $35,400.000 $7,500.000 $6,750.000 $11,579.750
DEAD END ROADWAY BARRICADE
LF 20.000 $150.000 $112.000 $500.000 $101.250 $36.310
REML & DISPL DRIFTWOOD & DEBRIS
LS 1.000 $8,000.000 $9,190.000 $50,000.000 $3,375.000 $18,570.420
Totals: $1,274,063.500 $1,323,346.400 $1,477,210.020 $1,531,054.600 $2,204,752.360