SHELBY FM 947 (1195-01-034)

Items: 78

County: SHELBY
Length: 0.0000 MILES
Highway: FM 947
District: LUFKIN
Control Number: 1195-01-034
DBE Goal: 3.0%
Project: STP 2025(353)HES
Guaranty: $100,000.00
Time: 205 WORKING DAYS
Engineer's Estimate: $5,249,245.10
Date: 01/07/2025 (1 year ago)
Contract Number: 1253012
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00178004
Contract Type: Federal
Project Description: PROVIDE ADDITIONAL PAVED SURFACE WIDTH TO 26', SAFETY TREAT FIXED OBJECTS, PROFILE EDGELINE MARKINGS, PROFILE CENTERLINE MARKINGS
Mail/Deliver Bids To: N/A
RANDAL COOPER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,249,245.10
$5,239,176.28
Over/Under Est: -0.19% -$10,068.82
Over/Under Est: 17.71% $929,614.79
Amt Left: 17.94% $939,683.61
Over/Under Est: 23.49% $1,233,173.72
Amt Left: 23.73% $1,243,242.54
Delta: -4.91% -$303,558.93
$7,204,179.68
Over/Under Est: 37.24% $1,954,934.58
Amt Left: 37.51% $1,965,003.40
Delta: -11.13% -$721,760.86
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 29.36% $1,553,339.98
A R BROTHERS CONSTRUCTION SERVICES, INC. 9.76% $516,369.15
DREWERY CONSTRUCTION COMPANY, INCORPORATED 4.20% $222,208.04
DREWERY BROS. TREE SERVICE, INC. 3.57% $188,876.83
DREWERY'S TREE SERVICE AND CONSTRUCTION CO., INC. 3.57% $188,876.83
KENT TREE SERVICE LLC 1.78% $94,173.88
CAP RIVER LLC 1.67% $88,354.15
STRIPE-A-ZONE, LLC 1.31% $69,307.74
SOUTHWEST ENVIRONMENT SERVICES LLC 1.04% $55,022.94
AMERICAN REMEDIATION OPTIONS, INC. 0.65% $34,389.34
PANOLA SIGN & BARRICADE, INC. 0.36% $19,046.40
Total: 57.27% $3,029,965.28

Bid Items & Bid Tabulations

78 Total 0 of 78
SHELBY  |  FM 947  |  LUFKIN  |  1195-01-034  |  01/07/2025  |  $5,249,245.10  |  STP 2025(353)HES  |  HAZARD ELIM & SAFETY  |  205 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PINTO CONSTRUCTION CO., INC.
EAST TEXAS BRIDGE, INC.
L. S. EQUIPMENT CO., INC.
LAKEY, INC.
PREPARING ROW
STA 156.330 $1,500.000 $1,375.500 $4,200.000 $1,500.000 $4,485.936
REMOV CONC (DRIVEWAYS)
SY 149.000 $45.000 $31.500 $25.000 $90.000 $28.921
SUBGR WIDEN (OC)
STA 156.330 $800.000 $500.000 $800.000 $1,250.000 $798.983
EMBANK (VEH)(OC)(TY B)
CY 1,879.000 $45.000 $25.000 $35.000 $50.000 $101.010
BACKFILL (TY B)
STA 156.330 $250.000 $300.000 $400.000 $600.000 $351.389
BLADING
STA 156.330 $225.000 $300.000 $350.000 $350.000 $434.070
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 34.000 $150.000 $136.500 $150.000 $200.000 $191.100
BLOCK SODDING
SY 1,252.000 $6.000 $5.850 $6.500 $10.000 $12.474
BROADCAST SEED (TEMP_WARM)
SY 34,172.000 $0.650 $0.140 $0.120 $0.500 $1.092
BROADCAST SEED (TEMP_COOL)
SY 34,172.000 $0.650 $0.140 $0.150 $0.500 $1.092
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 68,343.000 $1.000 $0.630 $0.650 $1.500 $1.226
VEGETATIVE WATERING
TGL 2,766.800 $20.000 $0.010 $10.000 $0.010 $37.674
CEM TRT(PLNT MX)(CL N)(TY D)(GR 4)(12")
SY 12,159.000 $95.000 $111.850 $95.000 $90.000 $65.260
ASPH (RC-250)
TON 12.930 $2,000.000 $1,957.250 $1,500.000 $2,000.000 $16,036.020
ASPH (AC-15P OR CRS-2P)
TON 80.680 $1,200.000 $1,235.500 $1,300.000 $2,600.000 $1,212.120
AGGR (TY E OR L, GR-5)
CY 84.000 $375.000 $320.500 $300.000 $225.000 $1,638.000
AGGR (TY E OR L, PE OR PL GR 4)
CY 335.000 $225.000 $228.250 $300.000 $225.000 $1,638.000
SP MIXES SP-C SAC-A PG70-22
TON 6,210.000 $180.000 $182.890 $200.000 $220.000 $189.941
SP MIXES SP-D PG70-22
TON 1,738.000 $180.000 $223.760 $212.000 $230.000 $189.941
CUT & RESTORE ASPH PAVING
SY 34.000 $150.000 $157.500 $150.000 $250.000 $191.646
CUT AND RESTORE PAV (FLEX BASE)
SY 189.000 $75.000 $78.750 $65.000 $400.000 $70.980
CEM STABIL BKFL
CY 19.000 $325.000 $514.500 $450.000 $350.000 $245.700
CL C CONC (COLLAR)
EA 20.000 $1,100.000 $945.000 $1,500.000 $3,250.000 $1,261.260
RIPRAP (CONC)(CL A)
CY 8.000 $1,000.000 $945.000 $1,500.000 $800.000 $698.880
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 25.000 $300.000 $325.500 $325.000 $125.000 $218.400
RC PIPE (CL III)(18 IN)
LF 1,686.000 $100.000 $74.550 $100.000 $150.000 $109.200
RC PIPE (CL III)(24 IN)
LF 18.000 $150.000 $98.700 $135.000 $273.000 $139.012
RC PIPE (CL III)(30 IN)
LF 6.000 $175.000 $262.500 $185.000 $499.000 $151.570
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $5,000.000 $6,825.000 $5,000.000 $7,900.000 $4,499.040
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 3.000 $6,500.000 $6,825.000 $9,000.000 $7,300.000 $12,223.109
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 3.000 $7,000.000 $8,925.000 $5,000.000 $8,000.000 $8,449.745
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 1.000 $7,200.000 $9,975.000 $6,500.000 $10,000.000 $8,449.745
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 3.000 $15,500.000 $16,800.000 $12,000.000 $20,000.000 $18,837.000
HEADWALL (CH - PW - 0) (DIA= 54 IN)
EA 1.000 $20,500.000 $19,950.000 $18,000.000 $25,000.000 $18,837.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 16.000 $1,100.000 $1,155.000 $1,350.000 $1,400.000 $1,456.946
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 71.000 $1,500.000 $1,155.000 $1,800.000 $2,200.000 $1,904.414
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,400.000 $1,575.000 $1,800.000 $2,200.000 $1,938.300
ADJUSTING MANHOLES
EA 2.000 $1,500.000 $2,205.000 $2,000.000 $1,500.000 $3,089.268
CLEAN EXIST CULVERTS
EA 3.000 $3,000.000 $2,625.000 $5,000.000 $2,000.000 $5,460.000
REMOV STR (PIPE)
EA 41.000 $1,200.000 $472.500 $1,000.000 $650.000 $1,276.271
MOBILIZATION
LS 1.000 $450,000.000 $500,000.000 $500,000.000 $625,000.000 $661,903.435
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $3,500.000 $3,000.000 $15,000.000 $15,000.000 $14,498.946
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $20,000.000 $45,000.000 $25,000.000 $10,000.000 $13,036.254
TMA (STATIONARY)
DAY 179.000 $300.000 $250.000 $350.000 $350.000 $336.916
TMA (MOBILE OPERATION)
DAY 45.000 $250.000 $50.000 $400.000 $350.000 $294.420
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 580.000 $55.000 $30.250 $42.000 $65.000 $62.832
ROCK FILTER DAMS (REMOVE)
LF 580.000 $15.000 $10.450 $11.000 $21.000 $21.672
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 181.000 $30.000 $15.000 $40.000 $65.000 $38.783
CONSTRUCTION EXITS (REMOVE)
SY 181.000 $10.000 $7.500 $11.000 $27.500 $14.666
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,420.000 $5.000 $6.000 $4.000 $6.200 $6.266
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,420.000 $1.000 $2.000 $1.000 $3.000 $2.108
DRIVEWAYS (CONC)
SY 148.000 $250.000 $194.250 $165.000 $30.000 $152.670
DRIVEWAYS (ACP)
SY 3,055.000 $75.000 $60.000 $85.000 $75.000 $108.436
TURNOUTS (SURF TREAT)
SY 822.000 $100.000 $70.000 $60.000 $100.000 $136.912
MAILBOX INSTALL-S (WC-POST) TY 3
EA 27.000 $275.000 $288.750 $300.000 $375.000 $316.243
MAILBOX INSTALL-D (WC-POST) TY 3
EA 3.000 $325.000 $309.750 $350.000 $450.000 $315.042
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $700.000 $680.400 $800.000 $990.000 $894.928
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $850.000 $780.150 $900.000 $1,340.000 $1,050.974
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,200.000 $948.150 $1,000.000 $1,445.000 $1,244.233
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $1,200.000 $1,289.400 $1,300.000 $1,900.000 $1,317.683
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 30.000 $550.000 $423.150 $800.000 $750.000 $742.308
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $650.000 $492.450 $600.000 $975.000 $777.538
RELOCATE SM RD SN SUP&AM TY TWT
EA 2.000 $500.000 $446.250 $500.000 $750.000 $539.801
REMOVE SM RD SN SUP&AM
EA 37.000 $150.000 $99.750 $125.000 $200.000 $183.372
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 36.000 $125.000 $131.250 $150.000 $125.000 $212.940
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 650.000 $0.500 $0.420 $1.100 $1.000 $0.462
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 27,666.000 $0.500 $0.420 $1.100 $1.000 $0.764
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,577.000 $2.000 $2.250 $2.000 $1.500 $1.445
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 21,991.000 $0.750 $0.870 $1.300 $1.650 $1.646
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 18,918.000 $0.750 $0.870 $1.300 $1.150 $2.537
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 628.000 $0.750 $0.890 $2.250 $2.100 $3.242
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 8,812.000 $1.000 $0.680 $0.850 $1.000 $1.453
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 9,050.000 $1.000 $0.680 $0.850 $1.000 $1.235
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 1,442.000 $5.000 $6.140 $7.500 $6.500 $6.065
PREFAB PM TY C (W)(24")(SLD)
LF 38.000 $20.000 $14.540 $25.000 $25.000 $19.597
PREFAB PM TY C (W)(RR XING)
EA 1.000 $750.000 $577.500 $1,000.000 $1,300.000 $678.283
REFL PAV MRKR TY II-A-A
EA 375.000 $6.000 $7.190 $8.000 $8.000 $8.652
BONDING COURSE
GAL 2,258.000 $6.500 $6.300 $9.000 $7.500 $7.039
Totals: $5,249,245.100 $5,239,176.276 $6,178,859.890 $6,482,418.818 $7,204,179.676