Show Job Controls
Bid Cobra

SAN PATRICIO US 181 (0101-04-130)

Items: 80

County: SAN PATRICIO
Length: 0.0000 MILES
Highway: US 181
District: CORPUS CHRISTI
Control Number: 0101-04-130
DBE Goal: 0.0%
Project: BR 2026(158)
Guaranty: $38,000.00
Time: 117 WORKING DAYS
Engineer's Estimate: $1,908,594.70
Date: 02/05/2026 (4 months ago)
Contract Number: 2263229
Type: BRIDGE REPLACEMENT
Project ID: A00186405
Contract Type: Federal
Project Description: REPLACE SB BRIDGE AND APPROACHES AT MUSTANG MOTT DITCH.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RENE ZAVALA
CHANDLER WILLIAMS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (12)
E
Engineer's Estimate
$1,908,594.70
$1,812,289.67
Over/Under Est: -5.05% -$96,305.03
Over/Under Est: 0.99% $18,969.26
Amt Left: 6.36% $115,274.29
$2,039,744.54
Over/Under Est: 6.87% $131,149.84
Amt Left: 12.55% $227,454.87
Delta: -5.82% -$112,180.58
Over/Under Est: 8.15% $155,635.60
Amt Left: 13.9% $251,940.63
Delta: -1.20% -$24,485.76
$2,098,584.50
Over/Under Est: 9.95% $189,989.80
Amt Left: 15.8% $286,294.83
Delta: -1.66% -$34,354.20
Over/Under Est: 12.99% $247,953.57
Amt Left: 19% $344,258.60
Delta: -2.76% -$57,963.77
Over/Under Est: 13.94% $266,094.30
Amt Left: 20% $362,399.33
Delta: -0.84% -$18,140.73
Over/Under Est: 17.83% $340,308.05
Amt Left: 24.09% $436,613.08
Delta: -3.41% -$74,213.75
$2,282,402.54
Over/Under Est: 19.59% $373,807.84
Amt Left: 25.94% $470,112.87
Delta: -1.49% -$33,499.79
$2,349,103.03
Over/Under Est: 23.08% $440,508.33
Amt Left: 29.62% $536,813.36
Delta: -2.92% -$66,700.49
$2,372,409.59
Over/Under Est: 24.3% $463,814.89
Amt Left: 30.91% $560,119.92
Delta: -0.99% -$23,306.56
$2,437,987.95
Over/Under Est: 27.74% $529,393.25
Amt Left: 34.53% $625,698.28
Delta: -2.76% -$65,578.36

Bid Items & Bid Tabulations

80 Total 0 of 80
SAN PATRICIO  |  US 181  |  CORPUS CHRISTI  |  0101-04-130  |  02/05/2026  |  $1,908,594.70  |  BR 2026(158)  |  BRIDGE REPL  |  117 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LISKA CONSTRUCTION COMPANY, INC.
GARRET SHIELDS INFRASTRUCTURE
STX CIVIL
J E CONSTRUCTION SERVICES, LLC
CK NEWBERRY, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
E-Z BEL CONSTRUCTION, LLC
LUCANIA CONTRACTORS LLC
ACEE CONSTRUCTION LLC.
J. CARROLL WEAVER, INC.
HUNTER INDUSTRIES, LTD.
3LW CIVIL LLC
PREPARING ROW
STA 5.000 $2,500.000 $3,000.000 $1,000.000 $2,385.000 $3,200.000 $1,000.000 $2,635.940 $1,500.000 $3,750.000 $6,000.000 $2,325.790 $35,000.000 $7,908.070
REMOV CONC (MOWSTRIP)
LF 2,317.000 $14.000 $3.700 $10.000 $12.000 $6.000 $5.000 $5.470 $8.000 $5.000 $1.100 $6.430 $77.500 $4.580
RMV (23") TRT/UNTRT BASE & ASPH PAV
SY 2,248.000 $20.000 $6.000 $45.000 $6.500 $14.000 $15.000 $10.100 $15.500 $20.000 $11.500 $19.570 $17.500 $39.820
EXCAV (ROADWAY)
CY 21.000 $26.500 $10.000 $20.000 $10.000 $7.000 $25.000 $181.520 $12.250 $20.000 $40.000 $19.580 $101.200 $52.710
EMBANK (FNL)(DC)(TY C)
CY 265.000 $28.000 $19.500 $20.000 $40.000 $15.000 $25.000 $79.980 $34.000 $30.000 $50.000 $30.590 $41.400 $33.760
FURN & PLACE TOPSOIL (4")
SY 17,720.000 $5.000 $1.750 $4.000 $7.000 $1.000 $1.000 $4.280 $0.850 $3.000 $1.250 $0.740 $2.220 $4.280
BROADCAST SEED (PERM_RURAL_SAND)
SY 17,720.000 $1.000 $0.350 $0.650 $0.250 $1.000 $0.400 $0.320 $0.300 $0.350 $0.700 $0.580 $0.650 $0.460
BROADCAST SEED (TEMP_WARM)
SY 8,420.000 $1.000 $0.150 $0.650 $0.250 $1.000 $0.300 $0.450 $0.200 $0.250 $0.700 $0.760 $0.650 $0.010
VEGETATIVE WATERING
TGL 476.400 $30.000 $40.000 $10.000 $50.000 $32.000 $15.000 $38.730 $83.000 $5.000 $1.500 $47.040 $38.500 $11.790
FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS
CY 912.000 $110.000 $120.000 $60.000 $90.000 $130.000 $135.000 $118.250 $150.000 $140.000 $147.500 $138.620 $132.710 $115.200
LIME (COM OR QK)(SLURRY)
TON 32.000 $394.000 $335.000 $350.000 $370.000 $380.000 $325.000 $622.360 $425.000 $375.000 $340.000 $365.060 $440.000 $413.000
LIME TRT (EXIST MATL)(6")
SY 2,346.000 $5.000 $6.200 $25.000 $4.500 $9.000 $10.000 $8.120 $5.000 $10.000 $7.050 $10.900 $7.200 $4.520
PRIME COAT (MC-30)
GAL 470.000 $9.000 $7.500 $9.000 $8.000 $7.000 $8.000 $7.420 $7.000 $10.000 $6.650 $4.680 $9.100 $8.260
AGGR (TY-PB, GR-4S OR 4)(SAC-B)
CY 18.000 $123.000 $632.000 $320.000 $150.000 $500.000 $400.000 $625.740 $1,250.000 $600.000 $530.250 $1,355.250 $209.000 $1,475.000
ASPH (MULTI OPTION)
GAL 787.000 $7.000 $5.100 $8.000 $10.000 $5.000 $5.000 $6.650 $9.000 $10.000 $4.500 $6.210 $9.200 $10.620
D-GR HMA TY-B PG70-22 (EXEMPT)
TON 640.000 $120.000 $167.000 $200.000 $180.000 $134.000 $150.000 $147.070 $155.000 $240.000 $162.750 $166.570 $160.600 $182.900
D-GR HMA TY-D SAC-B PG 76-22 (EXEMPT)
TON 296.000 $160.000 $190.000 $210.000 $205.000 $170.000 $180.000 $169.790 $175.000 $240.000 $184.800 $335.640 $171.600 $206.500
TACK COAT
GAL 460.000 $4.000 $4.200 $8.000 $7.500 $6.000 $4.000 $8.080 $6.500 $10.000 $3.700 $10.770 $4.640 $7.670
CEM STABIL BKFL
CY 38.000 $250.000 $140.000 $200.000 $85.000 $172.000 $325.000 $216.080 $252.000 $220.000 $125.000 $196.700 $250.000 $287.950
DRILL SHAFT (24 IN)
LF 588.000 $200.000 $180.000 $220.000 $205.000 $220.000 $200.000 $183.200 $210.000 $240.000 $280.000 $265.000 $267.000 $422.220
CL C CONC (ABUT)
CY 26.600 $1,300.000 $1,000.000 $1,300.000 $1,050.000 $1,500.000 $2,000.000 $1,858.340 $1,225.000 $1,900.000 $1,236.100 $1,215.200 $1,850.000 $1,303.510
CL C CONC (CAP)
CY 20.800 $1,750.000 $1,400.000 $1,300.000 $1,650.000 $2,400.000 $1,725.000 $2,090.900 $1,600.000 $2,600.000 $1,505.850 $1,442.560 $1,750.000 $1,617.190
CL C CONC (COLUMN)
CY 7.000 $1,500.000 $1,300.000 $1,400.000 $1,500.000 $2,300.000 $2,100.000 $3,227.960 $1,850.000 $3,100.000 $835.400 $2,072.000 $1,850.000 $1,860.760
REINF CONC SLAB (SLAB BEAM)
SF 3,793.000 $26.000 $22.500 $20.000 $24.000 $26.000 $33.000 $34.930 $20.300 $30.000 $23.500 $23.880 $26.000 $22.140
APPROACH SLAB
CY 64.400 $1,250.000 $615.000 $800.000 $1,110.000 $960.000 $750.000 $926.380 $950.000 $800.000 $855.000 $789.600 $700.000 $561.800
PRESTR CONC SLAB BEAM (4SB15)
LF 265.500 $225.000 $223.000 $270.000 $270.000 $270.000 $250.000 $292.310 $285.000 $290.000 $267.500 $312.480 $220.000 $252.740
PRESTR CONC SLAB BEAM (5SB15)
LF 531.000 $250.000 $200.000 $290.000 $245.000 $270.000 $225.000 $245.360 $285.000 $260.000 $267.500 $337.120 $220.000 $223.380
RIPRAP (CONC)(5 IN)
CY 57.000 $550.000 $560.000 $600.000 $590.000 $765.000 $650.000 $730.840 $775.000 $550.000 $550.000 $652.960 $950.000 $755.460
RIPRAP (MOW STRIP)(4 IN)
CY 92.300 $560.000 $535.000 $600.000 $650.000 $765.000 $650.000 $738.710 $875.000 $500.000 $505.000 $658.560 $950.000 $722.250
RAIL (TY T223)
LF 204.000 $200.000 $135.000 $200.000 $150.000 $400.000 $250.000 $254.410 $195.000 $230.000 $162.500 $208.320 $150.000 $176.940
ARMOR JOINT (SEALED)
LF 76.000 $150.000 $150.000 $200.000 $125.000 $145.000 $175.000 $189.270 $145.000 $200.000 $104.550 $209.440 $250.000 $122.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 1.000 $2,500.000 $2,100.000 $1,200.000 $1,800.000 $2,700.000 $4,000.000 $1,775.300 $950.000 $2,000.000 $1,285.500 $2,800.000 $4,500.000 $2,526.390
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $27,500.000 $25,000.000 $20,000.000 $27,000.000 $60,000.000 $50,198.780 $25,734.000 $40,000.000 $92,500.000 $140,996.940 $33,190.040 $32,405.650
MOBILIZATION
LS 1.000 $160,000.000 $129,000.000 $150,000.000 $154,000.000 $90,000.000 $200,000.000 $203,491.590 $196,000.000 $180,000.000 $225,000.000 $185,648.040 $231,523.340 $241,908.560
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $7,000.000 $3,350.000 $5,000.000 $3,000.000 $3,000.000 $10,000.000 $1,564.790 $1,200.000 $3,500.000 $5,850.000 $3,920.000 $5,330.630 $7,322.730
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $14,000.000 $10,500.000 $5,000.000 $5,000.000 $4,200.000 $10,000.000 $12,649.950 $6,000.000 $10,000.000 $12,500.000 $8,556.110 $5,000.890 $7,422.230
TMA (STATIONARY)
DAY 60.000 $350.000 $200.000 $300.000 $165.000 $295.000 $25.000 $185.410 $275.000 $1.000 $505.000 $285.200 $200.040 $1.000
TMA (MOBILE OPERATION)
HR 32.000 $110.000 $100.000 $50.000 $1.000 $64.000 $25.000 $87.120 $500.000 $1.000 $75.000 $72.800 $100.020 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $40.000 $50.000 $40.000 $40.000 $48.000 $70.000 $74.750 $70.000 $65.000 $82.950 $39.200 $79.000 $82.310
ROCK FILTER DAMS (REMOVE)
LF 80.000 $20.000 $15.000 $10.000 $1.000 $24.000 $23.000 $17.000 $15.000 $30.000 $25.200 $11.200 $24.000 $26.880
TEMP SEDMT CONT FENCE (INSTALL)
LF 160.000 $5.000 $5.000 $5.000 $3.000 $4.000 $10.000 $5.870 $5.000 $10.000 $12.600 $9.610 $12.000 $9.490
TEMP SEDMT CONT FENCE (REMOVE)
LF 160.000 $2.000 $2.000 $1.000 $1.000 $2.000 $2.000 $1.670 $2.000 $4.000 $1.050 $3.910 $1.000 $1.690
CONSTRUCTING DETOURS
SY 2,974.000 $65.000 $139.000 $90.000 $155.000 $150.000 $130.000 $127.250 $169.000 $155.000 $175.000 $155.860 $92.000 $169.090
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 2,514.000 $1.000 $3.600 $1.100 $1.000 $4.000 $3.000 $3.190 $2.100 $4.000 $3.600 $4.480 $3.400 $1.230
FILL MILLED ASPH RUMBLE STRIPS (SHLDR)
LF 1,772.000 $9.000 $2.000 $1.750 $5.500 $1.000 $3.500 $1.630 $3.500 $3.250 $3.300 $3.360 $11.620 $3.010
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $28.000 $34.500 $40.000 $30.000 $35.000 $29.000 $31.320 $30.000 $28.000 $31.350 $28.000 $30.340 $26.550
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,500.000 $2,475.000 $1,500.000 $2,150.000 $2,500.000 $2,100.000 $2,416.650 $2,254.000 $2,000.000 $2,359.900 $2,296.000 $2,185.500 $2,164.120
MTL W-BEAM GD FEN ADJUSTMENT
LF 816.000 $12.000 $19.500 $5.000 $10.000 $19.000 $16.500 $13.770 $13.000 $16.000 $17.550 $15.120 $17.240 $34.430
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,600.000 $1,385.000 $1,500.000 $1,700.000 $1,400.000 $1,200.000 $1,778.840 $1,599.000 $1,150.000 $1,606.500 $1,568.000 $1,225.370 $1,492.700
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $5.000 $3.000 $1.000 $1.000 $3.000 $3.250 $5.580 $5.000 $3.000 $4.450 $2.800 $3.180 $1.970
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $250.000 $500.000 $500.000 $235.000 $280.000 $250.000 $414.890 $300.000 $230.000 $635.250 $280.000 $244.010 $197.060
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 2.000 $410.000 $300.000 $100.000 $275.000 $320.000 $275.000 $364.950 $300.000 $230.000 $469.900 $280.000 $275.840 $295.000
CABLE BARRIER SYSTEM (INSTALL)(TL-4)
LF 1,947.000 $16.000 $25.000 $15.000 $18.000 $25.000 $21.000 $24.200 $23.000 $20.000 $22.050 $15.680 $22.070 $24.540
CABLE BARRIER TERM SEC (INSTL)(TL-4)
EA 2.000 $3,700.000 $3,525.000 $3,000.000 $3,250.000 $3,500.000 $3,000.000 $3,462.450 $3,250.000 $2,900.000 $3,278.650 $3,136.000 $3,113.810 $3,463.300
CABLE BARRIER (REMOVE)
LF 1,947.000 $5.000 $3.850 $5.000 $6.000 $4.000 $4.000 $5.830 $5.750 $3.900 $4.250 $3.360 $4.080 $4.540
CABLE BARRIER TERMINAL SECTION (REMOVE)
EA 1.000 $550.000 $500.000 $500.000 $785.000 $470.000 $400.000 $414.890 $300.000 $385.000 $798.000 $767.200 $408.460 $454.300
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,800.000 $3,960.000 $3,500.000 $3,750.000 $4,000.000 $3,300.000 $4,157.200 $3,928.000 $3,300.000 $3,596.250 $3,752.000 $3,501.050 $2,950.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $400.000 $250.000 $500.000 $800.000 $400.000 $325.000 $348.300 $300.000 $330.000 $477.750 $280.000 $350.100 $147.500
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $1,000.000 $1,250.000 $800.000 $525.000 $1,500.000 $1,250.000 $1,362.450 $1,250.000 $1,000.000 $1,047.400 $1,400.000 $859.350 $1,194.880
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 2.000 $1,200.000 $1,500.000 $800.000 $625.000 $1,800.000 $1,500.000 $1,624.950 $1,500.000 $140.000 $1,378.150 $1,680.000 $1,193.540 $1,200.610
REMOVE SM RD SN SUP&AM
EA 4.000 $170.000 $50.000 $500.000 $120.000 $490.000 $175.000 $208.720 $175.000 $200.000 $213.950 $196.000 $116.700 $160.340
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 3.000 $40.000 $50.000 $40.000 $25.000 $67.000 $55.000 $91.050 $55.000 $100.000 $141.750 $61.600 $47.740 $106.060
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 3.000 $40.000 $50.000 $40.000 $25.000 $16.000 $55.000 $91.050 $55.000 $100.000 $141.750 $61.600 $47.740 $107.970
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,831.000 $2.000 $0.500 $1.200 $0.450 $1.000 $1.000 $0.450 $0.450 $0.500 $0.450 $0.470 $0.500 $1.060
WK ZN PAV MRK REMOV (Y)6"(SLD W/MRKR)
LF 7,636.000 $4.000 $0.500 $1.200 $0.450 $1.000 $1.000 $0.450 $0.450 $0.500 $0.450 $0.470 $0.500 $2.240
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 1,401.000 $1.600 $1.060 $1.000 $0.950 $1.000 $1.000 $1.000 $0.900 $1.000 $0.950 $0.990 $1.050 $1.180
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 72.000 $10.000 $19.500 $11.500 $18.000 $19.000 $16.000 $18.190 $8.000 $19.250 $16.800 $17.920 $19.040 $8.260
PAVEMENT SLER 6"
LF 290.000 $0.600 $4.200 $0.820 $5.000 $4.000 $3.500 $4.020 $3.500 $4.250 $3.700 $3.920 $4.160 $1.180
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 2,150.000 $1.500 $1.320 $0.820 $1.150 $1.000 $1.250 $1.200 $1.100 $1.250 $1.200 $1.230 $1.310 $0.730
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 8,559.000 $1.500 $0.790 $0.820 $0.780 $1.000 $1.000 $0.770 $0.750 $0.850 $0.800 $0.810 $0.860 $0.730
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 8,339.000 $1.500 $0.790 $0.820 $0.780 $1.000 $1.000 $0.770 $0.750 $0.850 $0.800 $0.810 $0.860 $0.730
PREFAB PM TY C (W)(ARROW)
EA 4.000 $350.000 $220.000 $235.000 $250.000 $240.000 $200.000 $234.970 $200.000 $240.000 $210.000 $224.000 $237.950 $224.200
PREFAB PM TY C (W)(WORD)
EA 4.000 $390.000 $330.000 $300.000 $350.000 $360.000 $300.000 $339.970 $300.000 $360.000 $315.000 $336.000 $356.930 $259.600
PREFAB PM TY C (W)(36")(YLD TRI)
EA 14.000 $70.000 $27.500 $45.000 $30.000 $30.000 $25.000 $33.390 $25.000 $30.000 $26.250 $28.000 $29.740 $59.000
REFL PAV MRKR TY I-C
EA 71.000 $8.000 $8.000 $4.700 $8.500 $9.000 $8.000 $9.280 $7.500 $9.000 $7.900 $8.400 $8.920 $7.080
REFL PAV MRKR TY II-C-R
EA 109.000 $10.000 $8.000 $4.700 $8.500 $9.000 $8.000 $8.790 $8.000 $9.000 $7.900 $8.400 $8.920 $7.080
ELIM EXT PM & MRKS (4")
LF 8,047.000 $1.300 $0.420 $1.000 $0.500 $1.000 $1.000 $0.380 $0.350 $0.450 $0.400 $0.390 $0.420 $0.770
ELIM EXT PM & MRKS (8")
LF 810.000 $2.000 $0.780 $1.200 $0.700 $1.000 $1.000 $0.810 $0.850 $0.750 $0.700 $0.730 $0.770 $0.770
ELIM EXT PM & MRKS (ARROW)
EA 1.000 $110.000 $80.000 $70.000 $85.000 $90.000 $75.000 $178.640 $75.000 $90.000 $78.750 $84.000 $89.230 $59.000
ELIM EXT PM & MRKS (WORD)
EA 1.000 $120.000 $80.000 $70.000 $85.000 $90.000 $75.000 $178.640 $75.000 $90.000 $78.750 $84.000 $89.230 $59.000
Totals: $1,908,594.700 $1,812,289.670 $1,927,563.960 $2,039,744.540 $2,064,230.300 $2,098,584.500 $2,156,548.276 $2,174,689.000 $2,248,902.750 $2,282,402.540 $2,349,103.022 $2,372,409.590 $2,437,987.939
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $3,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $100,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $150,000.00
Total: $253,000.00