Show Job Controls
Bid Cobra

SAN PATRICIO IH 37 (0074-05-104)

Items: 64

County: SAN PATRICIO
Length: 0.0000 MILES
Highway: IH 37
District: CORPUS CHRISTI
Control Number: 0074-05-104
DBE Goal: 0.0%
Project: F 2025(281)
Guaranty: $50,000.00
Time: 91 WORKING DAYS
Engineer's Estimate: $2,366,694.85
Date: 03/04/2026 (3 months ago)
Contract Number: 3263021
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00209031
Contract Type: Federal
Project Description: REHAB & WIDEN (W FRONTAGE ROADS)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RENE ZAVALA
CHANDLER WILLIAMS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,366,694.85
$2,258,368.22
Over/Under Est: -4.58% -$108,326.63
Over/Under Est: 10.89% $257,815.88
Amt Left: 16.21% $366,142.51
Over/Under Est: 11.53% $272,955.84
Amt Left: 16.88% $381,282.47
Delta: -0.58% -$15,139.96
Over/Under Est: 27.95% $661,377.15
Amt Left: 34.08% $769,703.78
Delta: -14.71% -$388,421.31
Over/Under Est: 37.97% $898,651.15
Amt Left: 44.59% $1,006,977.78
Delta: -7.84% -$237,274.00
$3,270,230.85
Over/Under Est: 38.18% $903,536.00
Amt Left: 44.81% $1,011,862.63
Delta: -0.15% -$4,884.85
Over/Under Est: 51.52% $1,219,351.45
Amt Left: 58.79% $1,327,678.08
Delta: -9.66% -$315,815.45

Bid Items & Bid Tabulations

64 Total 0 of 64
SAN PATRICIO  |  IH 37  |  CORPUS CHRISTI  |  0074-05-104  |  03/04/2026  |  $2,366,694.85  |  F 2025(281)  |  REHAB EXIST ROADWAY  |  91 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
HUNTER INDUSTRIES, LTD.
J. CARROLL WEAVER, INC.
J E CONSTRUCTION SERVICES, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
CK NEWBERRY, LLC
MATAGORDA CONSTRUCTION & MATERIALS
PREPARING ROW
STA 118.360 $250.000 $100.000 $303.050 $110.000 $650.000 $265.460 $500.000 $300.000
REMOV CONC (RIPRAP)
SY 91.000 $36.000 $20.000 $22.890 $26.630 $25.000 $23.620 $50.000 $60.000
EXCAV (ROADWAY)
CY 6,533.000 $15.000 $18.000 $17.390 $11.680 $15.000 $15.760 $15.000 $19.000
SUBGR WIDEN (DC)
STA 84.000 $350.000 $180.000 $244.200 $127.990 $310.000 $460.630 $350.000 $770.000
BACKFILL (TY A OR B)
STA 101.000 $175.000 $160.000 $103.750 $103.710 $250.000 $301.000 $275.000 $384.000
GEOGRID BASE REINFORCEMENT (TYPE 2)
SY 39,856.000 $1.150 $0.900 $1.030 $0.780 $1.000 $1.620 $1.000 $1.300
LIME (COM OR QK)(SLURRY)
TON 604.000 $300.000 $260.000 $363.800 $375.120 $395.000 $384.620 $350.000 $400.000
LIME TRT(SUBGRADE)(6")
SY 40,512.000 $3.500 $3.250 $2.750 $2.430 $3.000 $2.460 $2.000 $10.000
CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(6")
SY 2,244.000 $17.000 $19.000 $23.110 $33.830 $28.000 $35.280 $35.000 $28.000
CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(8")
SY 28,726.000 $22.000 $22.000 $31.010 $32.130 $34.000 $33.010 $40.000 $38.000
CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(15")
SY 5,289.000 $42.000 $50.000 $58.970 $62.720 $71.000 $66.660 $65.000 $72.000
PRIME COAT (MC-30)
GAL 7,311.000 $5.500 $5.000 $4.400 $3.860 $4.000 $6.200 $5.000 $4.500
AGGR (TY-PB, GR-3 OR 3S)(SAC-B)
CY 1,191.000 $129.000 $95.000 $88.470 $149.030 $88.000 $196.130 $120.000 $160.000
AGGR (TY-PB, GR-4S OR 4)(SAC-B)
CY 420.000 $160.000 $225.000 $124.340 $197.420 $90.000 $196.130 $150.000 $210.000
ASPH (MULTI OPTION)
GAL 25,012.000 $4.000 $2.750 $3.180 $3.200 $4.000 $3.970 $4.000 $6.000
CEM STABIL BKFL
CY 1.500 $200.000 $325.000 $274.840 $132.990 $94.000 $1,580.520 $2,000.000 $184.000
RIPRAP (MOW STRIP)(4 IN)
CY 50.000 $630.000 $585.000 $834.430 $583.000 $650.000 $714.490 $7.250 $1,000.000
RC PIPE (CL III)(18 IN)
LF 90.000 $110.000 $145.000 $77.590 $73.510 $130.000 $146.850 $115.000 $68.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 6.000 $1,900.000 $2,260.000 $2,355.720 $1,815.000 $3,000.000 $1,170.970 $4,000.000 $1,900.000
CLEAN EXIST CULVERTS
EA 6.000 $1,700.000 $707.000 $1,687.680 $1,320.000 $1,700.000 $2,451.970 $3,000.000 $4,500.000
REMOV STR (PIPE)
LF 78.000 $30.000 $21.000 $21.250 $16.700 $22.000 $25.950 $50.000 $40.000
MOBILIZATION
LS 1.000 $210,000.000 $124,500.000 $202,544.310 $111,406.100 $243,000.000 $260,726.260 $300,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $5,040.000 $2,018.580 $2,420.000 $5,000.000 $1,139.520 $5,000.000 $4,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $10,000.000 $10,000.000 $541.250 $3,850.000 $5,000.000 $11,281.140 $7,500.000 $6,000.000
TMA (MOBILE OPERATION)
DAY 4.000 $250.000 $547.000 $108.250 $220.000 $670.000 $975.040 $100.000 $1,000.000
EXCAV (EROSN & SEDMT CONT, IN PLACE)
CY 10.000 $100.000 $55.000 $77.000 $8.390 $18.000 $67.500 $100.000 $200.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 620.000 $5.000 $6.100 $9.000 $2.860 $6.000 $4.560 $10.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 620.000 $2.000 $1.950 $2.500 $2.860 $3.000 $1.260 $3.000 $1.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 120.000 $8.000 $11.000 $9.000 $49.500 $11.000 $13.410 $10.000 $17.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $3.000 $2.080 $2.500 $2.200 $3.000 $3.960 $3.000 $1.000
CONC CURB (TY II)
LF 494.000 $29.000 $20.000 $17.960 $25.300 $14.000 $34.210 $35.000 $28.000
INTERSECTIONS (ACP)
SY 1,796.000 $33.000 $29.000 $43.400 $33.400 $70.000 $74.800 $50.000 $81.000
CONC DIRECTIONAL ISLAND
SY 91.000 $130.000 $117.000 $141.200 $148.500 $130.000 $138.730 $150.000 $170.000
MTL W-BEAM GD FEN (TIM POST)
LF 675.000 $26.000 $28.000 $24.640 $27.100 $39.000 $26.020 $25.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,900.000 $1,990.000 $2,271.000 $1,948.100 $2,000.000 $1,908.180 $1,800.000 $4,500.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 2.000 $1,100.000 $1,440.000 $1,283.000 $1,411.300 $900.000 $1,395.780 $1,300.000 $1,700.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $2.900 $4.500 $4.000 $4.400 $3.000 $4.360 $4.000 $5.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 2.000 $650.000 $1,730.000 $1,546.250 $1,701.700 $1,300.000 $1,672.190 $1,600.000 $3,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 25.000 $750.000 $897.000 $800.000 $880.000 $900.000 $849.730 $800.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $800.000 $1,090.000 $975.000 $1,072.500 $1,100.000 $1,033.480 $975.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $975.000 $1,430.000 $1,275.000 $1,402.500 $1,400.000 $1,348.480 $1,275.000 $800.000
REMOVE SM RD SN SUP&AM
EA 29.000 $110.000 $95.000 $85.000 $93.500 $430.000 $98.980 $85.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 17.000 $45.000 $67.000 $60.000 $66.000 $70.000 $72.730 $60.000 $40.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 20.000 $100.000 $107.000 $95.000 $104.500 $110.000 $109.480 $95.000 $130.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 1,790.000 $0.500 $0.640 $0.580 $0.640 $1.000 $0.660 $0.600 $0.800
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 21,662.000 $0.500 $0.550 $0.480 $0.530 $1.000 $0.520 $0.500 $0.800
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 52.000 $25.000 $18.000 $16.000 $17.600 $18.000 $18.670 $16.000 $23.000
WK ZN PAV MRK NON-REMOV(W)36"(YLD TRI)
EA 12.000 $21.000 $28.000 $25.000 $27.500 $29.000 $34.360 $25.000 $20.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 10,784.000 $0.550 $0.550 $0.480 $0.530 $1.000 $0.520 $0.500 $1.100
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 213.000 $2.000 $1.240 $1.060 $1.110 $4.000 $1.400 $1.250 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,090.000 $1.800 $1.240 $1.060 $1.110 $4.000 $1.250 $1.250 $3.000
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 20,614.000 $0.500 $1.000 $0.880 $0.970 $1.000 $0.930 $0.900 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 10,725.000 $0.550 $1.100 $0.960 $1.060 $1.000 $1.030 $1.000 $1.000
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 2,870.000 $0.550 $1.250 $1.100 $1.210 $1.000 $1.190 $1.100 $1.000
PREFAB PM TY C (W)(24")(SLD)
LF 48.000 $15.000 $18.000 $16.000 $17.600 $18.000 $18.830 $16.000 $20.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 12.000 $35.000 $39.000 $35.000 $38.500 $41.000 $52.960 $35.000 $47.000
REFL PAV MRKR TY II-A-A
EA 208.000 $4.500 $8.400 $7.500 $8.250 $8.000 $8.340 $7.500 $6.000
REFL PAV MRKR TY II-C-R
EA 26.000 $5.000 $8.400 $7.500 $8.250 $8.000 $11.620 $7.500 $6.000
TREE REMOVAL (4" - 12" DIA)
EA 2.000 $300.000 $224.000 $642.000 $605.960 $295.000 $3,132.200 $2,500.000 $1,200.000
TREE REMOVAL (12" - 18" DIA)
EA 1.000 $400.000 $280.000 $802.500 $727.140 $590.000 $3,288.450 $3,100.000 $1,200.000
DRAIN INLET CLEANING
EA 6.000 $100.000 $561.000 $520.970 $2,305.970 $320.000 $1,507.620 $5,000.000 $576.000
STORM SEWER CLEANING (PIPE)(19"-24"DIA)
LF 178.000 $6.500 $15.000 $20.840 $16.500 $13.000 $50.820 $50.000 $34.000
STORM SEWER CLEANING (PIPE)(31"-36"DIA)
LF 97.000 $7.500 $17.500 $20.840 $16.500 $20.000 $55.950 $60.000 $42.000
STORM SEWER CLEANING (PIPE)(37"-42"DIA)
LF 1,492.000 $8.000 $20.000 $10.420 $16.500 $10.000 $60.630 $50.000 $42.000
Totals: $2,366,694.850 $2,258,368.220 $2,624,510.728 $2,639,650.685 $3,028,072.000 $3,265,345.996 $3,270,230.850 $3,586,046.300
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $40,000.00
Total: $100,000.00