Bid Cobra

RUSK US0079 (6500-38-001)

Items: 19

County: RUSK
Length: 0.0100 MILES
Highway: US0079
District: TYLER
Control Number: 6500-38-001
DBE Goal: 0.0%
Project: RMC - A00220774
Guaranty: $75,000.00
Time: 50 WORKING DAYS
Engineer's Estimate: $3,970,361.90
Date: 06/03/2026 (7 days ago) Changed
Contract Number: 6264203
Type: MILL AND INLAY
Project ID: A00220774
Project Description: MILL & INLAY FOR FY 2027 FOR NORTH COUNTIES (GREGG, RUSK, VAN ZANDT, WOOD)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANNY HENDERSON
STACY WYLIE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,970,361.90
Over/Under Est: 6.23% $247,501.35
Over/Under Est: 7.45% $295,945.25
Amt Left: 1.15% $48,443.90
Over/Under Est: 11.8% $468,411.50
Amt Left: 5.24% $220,910.15
Delta: -4.04% -$172,466.25
Over/Under Est: 13.23% $525,382.34
Amt Left: 6.59% $277,880.99
Delta: -1.28% -$56,970.84

Bid Items & Bid Tabulations

19 Total 0 of 19
RUSK  |  US0079  |  TYLER  |  6500-38-001  |  06/03/2026  |  $3,970,361.90  |  RMC - A00220774  |  MILL AND INLAY  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
MADDEN CONTRACTING COMPANY, LLC.
LONGVIEW BRIDGE AND ROAD, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SP MIXES SP-C SAC-A PG70-22
TON 14,726.000 $170.000 $189.000 $200.000 $194.000 $194.000
TBFC (MEMBRANE)
GAL 8,641.000 $4.500 $5.500 $5.000 $5.000 $4.500
TBFC PG76-22 SAC-A TY C
TON 1,783.000 $200.000 $225.000 $220.000 $238.000 $221.250
PLANE ASPH CONC PAV(2")
SY 84,839.000 $3.000 $3.000 $3.500 $3.850 $3.910
PLANE ASPH CONC PAV(3")
SY 43,205.000 $4.000 $3.750 $3.500 $5.350 $4.250
MOBILIZATION
LS 1.000 $360,000.000 $200,000.000 $185,100.000 $300,000.000 $375,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $20,000.000 $7,100.000 $6,600.000 $32,678.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 140.000 $150.000 $200.000 $100.000 $135.000 $150.000
TMA (STATIONARY)
DAY 30.000 $250.000 $300.000 $300.000 $330.000 $50.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 2,763.000 $2.000 $3.000 $1.850 $2.000 $1.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 1,036.000 $2.000 $3.000 $1.850 $2.000 $1.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 1,455.000 $10.000 $12.000 $7.400 $5.500 $3.250
WK ZN PAV MRK REMOV (W)(ARROW)
EA 63.000 $250.000 $250.000 $35.000 $33.000 $200.000
WK ZN PAV MRK REMOV (W)(RR XING)
EA 2.000 $250.000 $300.000 $100.000 $132.000 $500.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 30.000 $250.000 $250.000 $100.000 $66.000 $200.000
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 3,210.000 $2.000 $3.000 $1.850 $2.000 $1.500
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 9,670.000 $2.000 $3.000 $1.850 $2.000 $1.500
MEMBRANE UNDERSEAL
GAL 32,012.000 $5.200 $5.500 $5.000 $5.000 $4.500
MAINTENANCE SPEED LIMIT SIGNING
EA 5.000 $500.000 $1,000.000 $200.000 $450.000 $250.000
Totals: $3,970,361.900 $4,217,863.250 $4,266,307.150 $4,438,773.400 $4,495,744.240