RUSK US 79 (0246-01-037)
Items: 25
County: RUSK
Length: N/A
Highway: US 79
District: TYLER
Control Number: 0246-01-037
DBE Goal: 0.0%
Project: F 2B24(254)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $757,497.00
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: EMBANKMENT STABILIZATION
Mail/Deliver Bids To: N/A
KYLE DYKES
STACY WYLIE1
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$757,497.00 | |||
| $718,631.00 |
-5.13%
-$38,866.00
|
|||
| $738,382.70 |
-2.52%
-$19,114.30
|
2.75%
$19,751.70
|
||
| $1,027,998.50 |
35.71%
$270,501.50
|
43.05%
$309,367.50
|
-39.22%
-$289,615.80
|
|
| $1,150,710.00 |
51.91%
$393,213.00
|
60.13%
$432,079.00
|
-11.94%
-$122,711.50
|
|
| $1,246,384.00 |
64.54%
$488,887.00
|
73.44%
$527,753.00
|
-8.31%
-$95,674.00
|
E
Engineer's Estimate
$757,497.00
1
Awarded
$718,631.00
Over/Under Est:
-5.13%
-$38,866.00
$738,382.70
Over/Under Est:
-2.52%
-$19,114.30
Amt Left:
2.75%
$19,751.70
$1,027,998.50
Over/Under Est:
35.71%
$270,501.50
Amt Left:
43.05%
$309,367.50
Delta:
-39.22%
-$289,615.80
$1,150,710.00
Over/Under Est:
51.91%
$393,213.00
Amt Left:
60.13%
$432,079.00
Delta:
-11.94%
-$122,711.50
$1,246,384.00
Over/Under Est:
64.54%
$488,887.00
Amt Left:
73.44%
$527,753.00
Delta:
-8.31%
-$95,674.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| J. H. ODEN CONTRACTING COMPANY | 0.42% | $3,152.34 |
| Total: | 0.42% | $3,152.34 |
Bid Items & Bid Tabulations
25
Total
0 of 25