Show Job Controls
Bid Cobra

ROBERTSON SH 7 (0382-04-022)

Items: 86

County: ROBERTSON
Length: N/A
Highway: SH 7
District: BRYAN
Control Number: 0382-04-022
DBE Goal: N/A
Project: BR 2023(763)
Guaranty: N/A
Time: 279 WORKING DAYS
Engineer's Estimate: $5,009,226.09
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JAMES ROBBINS
JOSEPH GREIVE
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,009,226.09
$4,998,006.86
Over/Under Est: -0.22% -$11,219.23
$5,792,653.61
Over/Under Est: 15.64% $783,427.52
Amt Left: 15.9% $794,646.75
Over/Under Est: 15.93% $797,813.36
Amt Left: 16.19% $809,032.59
Delta: -0.25% -$14,385.84
Over/Under Est: 31.13% $1,559,483.91
Amt Left: 31.43% $1,570,703.14
Delta: -13.12% -$761,670.55
Subcontractor Percentage Amount
LARRY YOUNG PAVING, INC. 3.63% $200,990.67
GMJ PAVING CO. 2.78% $153,926.74
AARON CONCRETE CONTRACTORS, LLC 1.73% $95,788.94
WILLOW CITY SIGN & RAIL, INC. 1.29% $71,426.44
STRIPING TECHNOLOGY, L.P. 0.90% $49,832.40
PENHALL COMPANY 0.59% $32,667.91
WATERS CONSTRUCTION COMPANY, INC. 0.42% $23,255.12
SEMARCK LANDSCAPE SERVICES, INC. 0.36% $19,932.96
TRAFFIC SIGNS & LINES, LLC 0.33% $18,271.88
WEST TEXAS ROCK RESOURCES, LLC 0.18% $9,966.48
Total: 12.21% $676,059.54

Bid Items & Bid Tabulations

86 Total 0 of 86
ROBERTSON  |  SH 7  |  BRYAN  |  0382-04-022  |  06/02/2023  |  $5,009,226.09  |  BR 2023(763)  |  BRIDGE REPL  |  279 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
R CONSTRUCTION CIVIL, LLC
A. L. HELMCAMP, INC.
TEXAS MATERIALS GROUP, INC.
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 11.000 $4,000.000 $5,000.000 $1,000.000 $48,000.000 $51,000.000
REMOVING CONC (RIPRAP)
CY 98.000 $60.000 $7.000 $300.000 $190.000 $175.000
REMOVE STAB BASE & ASPH PAV (13"-18")
SY 1,152.000 $15.000 $20.000 $30.000 $28.000 $22.000
EXCAVATION (ROADWAY)
CY 549.000 $25.000 $15.000 $50.000 $50.000 $42.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 2,018.000 $60.000 $16.000 $40.000 $50.000 $45.000
FURNISHING AND PLACING TOPSOIL (4")
SY 7,177.000 $3.500 $4.000 $6.000 $2.500 $0.470
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 7,177.000 $1.000 $0.900 $0.570 $0.540 $0.540
CELL FBR MLCH SEED(TEMP)(WARM)
SY 3,589.000 $0.850 $3.000 $0.570 $0.540 $0.540
CELL FBR MLCH SEED(TEMP)(COOL)
SY 3,589.000 $0.850 $4.000 $0.570 $0.540 $0.540
VEGETATIVE WATERING
MG 215.300 $50.000 $42.000 $5.000 $24.000 $26.580
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 2,824.000 $2.500 $4.000 $1.300 $1.250 $1.250
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
SY 1,731.000 $35.000 $46.000 $45.000 $41.000 $72.860
CEMENT
TON 32.000 $260.000 $312.000 $305.000 $289.000 $344.310
CEMENT TREAT (NEW BASE)(12")
SY 1,731.000 $4.000 $8.000 $16.000 $23.000 $27.490
ASPH (AC-10-2TR)
GAL 953.000 $7.500 $9.500 $16.000 $9.000 $9.000
ASPH (RC-250)
GAL 433.000 $25.000 $24.500 $16.000 $23.000 $24.000
AGGR(TY-PB GR-4 SAC-B)
CY 20.000 $180.000 $565.000 $2,500.000 $1,200.000 $560.000
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 13.000 $300.000 $1,500.000 $2,500.000 $1,600.000 $1,465.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,496.000 $6.000 $11.000 $12.000 $15.000 $3.800
PLANE ASPH CONC PAV (2")
SY 253.000 $4.000 $20.000 $22.000 $15.000 $3.800
CEM STABIL BKFL
CY 285.000 $200.000 $272.000 $300.000 $270.000 $250.000
TRENCH EXCAVATION PROTECTION
LF 476.000 $12.000 $2.000 $25.000 $10.000 $150.000
TEMPORARY SPL SHORING
SF 408.000 $40.000 $10.000 $250.000 $125.000 $175.000
DRILL SHAFT (18 IN)
LF 120.000 $222.000 $90.000 $300.000 $165.000 $110.000
DRILL SHAFT (36 IN)
LF 1,627.000 $350.000 $340.000 $275.000 $341.000 $300.000
CL C CONC (ABUT)
CY 77.600 $1,500.000 $1,535.000 $2,250.000 $2,000.000 $1,500.000
CL C CONC (CAP)
CY 129.000 $2,000.000 $1,999.000 $2,750.000 $2,300.000 $1,750.000
CL C CONC (COLUMN)
CY 76.500 $2,000.000 $2,762.000 $1,750.000 $2,300.000 $2,000.000
REINF CONC SLAB
SF 26,970.000 $30.000 $25.000 $35.000 $32.000 $45.500
APPROACH SLAB
CY 84.000 $1,000.000 $876.000 $1,700.000 $800.000 $725.000
PRESTR CONC GIRDER (TX34)
LF 3,234.000 $250.000 $204.000 $195.000 $200.000 $220.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 2,125.000 $200.000 $190.000 $120.000 $165.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 53.000 $650.000 $450.000 $800.000 $750.000 $660.000
RAIL (TY T223)
LF 1,010.000 $175.000 $117.000 $180.000 $140.000 $110.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 174.000 $220.000 $169.000 $200.000 $230.000 $223.400
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $80,000.000 $165,421.000 $200,000.000 $135,000.000 $296,165.000
MOBILIZATION
LS 1.000 $465,851.640 $495,000.000 $575,000.000 $550,000.000 $656,871.810
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $3,000.000 $3,500.000 $15,000.000 $10,000.000 $4,616.030
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 52.000 $40.000 $40.000 $40.000 $38.000 $38.000
ROCK FILTER DAMS (REMOVE)
LF 52.000 $12.000 $2.000 $13.000 $12.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 240.000 $30.000 $30.000 $10.000 $35.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 240.000 $20.000 $2.000 $5.000 $14.000 $14.000
CONSTRUCTION PERIMETER FENCE
LF 551.000 $2.500 $3.000 $4.000 $3.500 $3.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,038.000 $5.000 $4.000 $4.500 $4.250 $4.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,038.000 $1.500 $1.000 $1.000 $1.000 $1.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 9.000 $4,000.000 $3,705.000 $5,000.000 $4,500.000 $3,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,170.000 $70.000 $96.000 $100.000 $48.000 $67.560
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,110.000 $10.000 $3.000 $15.000 $22.000 $3.830
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,170.000 $15.000 $9.000 $25.000 $27.000 $11.380
RUMBLE STRIPS (SHOULDER)
LF 1,070.000 $0.300 $7.000 $7.000 $4.000 $1.230
RUMBLE STRIPS (CENTERLINE)
LF 535.000 $0.400 $7.000 $7.000 $8.000 $2.450
MTL W-BEAM GD FEN (TIM POST)
LF 1,025.000 $31.000 $26.000 $22.000 $24.000 $23.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,300.000 $2,284.000 $1,800.000 $2,500.000 $2,050.000
MTL BM GD FEN TRANS (31"-28")
EA 2.000 $725.000 $1,031.000 $1,130.000 $930.000 $925.000
REMOVE METAL BEAM GUARD FENCE
LF 1,225.000 $3.500 $3.000 $3.150 $2.500 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,300.000 $3,120.000 $2,992.500 $2,800.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $223.000 $315.000 $200.000 $200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,200.000 $2,061.000 $1,100.000 $1,000.000 $1,850.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,200.000 $1,003.000 $2,100.000 $700.000 $900.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $9,805.000 $10,000.000 $7,500.000 $8,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $825.000 $656.710 $945.000 $600.000 $625.000
REMOVE SM RD SN SUP&AM
EA 1.000 $125.000 $111.000 $157.500 $100.000 $85.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 10.000 $30.000 $35.000 $26.250 $25.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $50.000 $7.000 $33.600 $35.000 $35.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 3,112.000 $0.500 $1.000 $1.220 $1.100 $1.050
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 2,519.000 $0.500 $1.000 $1.220 $1.100 $1.050
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 1,599.000 $0.700 $2.000 $1.220 $1.100 $1.050
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $10.000 $17.000 $23.250 $20.000 $20.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 8,750.000 $1.000 $2.000 $1.220 $1.100 $1.050
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 104.000 $1.750 $2.000 $0.830 $1.000 $1.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 19.000 $10.000 $28.000 $23.240 $20.000 $20.000
PAVEMENT SEALER 6"
LF 3,515.000 $0.300 $1.000 $0.580 $0.500 $0.500
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 3,807.000 $0.700 $2.000 $3.080 $2.700 $2.650
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 2,006.000 $0.850 $2.000 $0.870 $0.750 $0.750
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 1,457.000 $0.800 $2.000 $1.160 $1.000 $1.000
REFL PAV MRKR TY II-A-A
EA 317.000 $6.000 $6.000 $3.490 $3.000 $3.000
ELIM EXT PAV MRK & MRKS (4")
LF 2,513.000 $1.000 $1.000 $1.450 $1.300 $1.250
PAV SURF PREP FOR MRK (6")
LF 3,515.000 $0.150 $0.050 $0.290 $0.250 $0.250
D-GR HMA TY-C PG64-22 (LEVEL-UP)
TON 28.000 $140.000 $404.000 $750.000 $400.000 $370.000
SP MIXES SP-C SAC-A PG64-22
TON 386.000 $140.000 $350.000 $300.000 $270.000 $333.000
SP MIXES SP-C SAC-B PG64-22
TON 231.000 $130.000 $380.000 $450.000 $250.000 $361.400
BONDING COURSE
GAL 525.000 $6.000 $21.500 $8.000 $10.000 $20.500
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $387.000 $2,500.000 $300.000 $750.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $16,000.000 $20,000.000 $10,000.000 $8,767.050
TMA (STATIONARY)
DAY 267.000 $250.000 $300.000 $300.000 $150.000 $838.450
TMA (MOBILE OPERATION)
DAY 24.000 $300.000 $500.000 $300.000 $150.000 $125.790
Totals: $5,009,226.090 $4,998,006.860 $5,792,653.610 $5,807,039.450 $6,568,710.004