Show Job Controls
Bid Cobra

REEVES US 285 (0139-02-025)

Items: 143

County: REEVES
Length: N/A
Highway: US 285
District: ODESSA
Control Number: 0139-02-025
DBE Goal: N/A
Project: NH 2018(774)
Guaranty: N/A
Time: 545 WORKING DAYS
Engineer's Estimate: $32,404,200.25
Date: 04/04/2018 (8 years ago)
Contract Number: N/A
Type: ROADWAY WIDENING TO A MODIFIED SUPER 2
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$32,404,200.25
$32,027,183.64
Over/Under Est: -1.16% -$377,016.61
Over/Under Est: -0.07% -$22,909.86
Amt Left: 1.11% $354,106.75
Over/Under Est: 0.88% $285,171.34
Amt Left: 2.07% $662,187.95
Delta: -0.95% -$308,081.20
$33,940,860.51
Over/Under Est: 4.74% $1,536,660.26
Amt Left: 5.98% $1,913,676.87
Delta: -3.83% -$1,251,488.92

Bid Items & Bid Tabulations

143 Total 0 of 143
REEVES  |  US 285  |  ODESSA  |  0139-02-025  |  04/04/2018  |  $32,404,200.25  |  NH 2018(774)  |  ROADWAY WIDENING TO A MODIFIED SUPER...  |  545 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNF CONSTRUCTION, INC.
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
JAMES HAMILTON CONSTRUCTION CO.
CI CONSTRUCTORS, INC.
PREPARING ROW
STA 774.000 $75.000 $350.000 $400.000 $350.000 $500.000
REMOVE CONC (RAIL)
LF 128.000 $95.000 $40.400 $41.500 $45.000 $150.000
EXCAVATION (ROADWAY)
CY 81,346.000 $13.000 $8.800 $7.000 $15.000 $10.000
EXCAVATION (CHANNEL)
CY 1,534.000 $12.000 $4.680 $8.000 $15.000 $12.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 53,624.000 $13.000 $4.250 $8.500 $10.000 $10.000
BLADING
HR 72.000 $200.000 $245.000 $250.000 $250.000 $150.000
PROOF ROLLING
HR 72.000 $100.000 $119.000 $80.000 $130.000 $120.000
FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS)
CY 1,472.000 $30.000 $48.300 $42.000 $49.000 $75.000
FL BS (RDWY DEL) (TY A GR 4) (IN VEH)
CY 3,030.000 $45.000 $47.500 $35.000 $34.000 $55.000
FL BS (CMP IN PLACE)(TY A GR 4)(9")
SY 163,189.000 $16.150 $14.000 $14.000 $13.000 $13.250
REWORK BS MATL (TY C)(9")(ORD COMP)
SY 367,434.000 $3.250 $2.180 $2.600 $2.750 $2.000
EMULS ASPH (PRIME)(AE-P)
GAL 97,584.000 $3.500 $4.200 $3.750 $3.000 $3.000
ASPH (AC-20-5TR)
GAL 25,926.000 $4.000 $3.500 $3.700 $3.100 $3.000
ASPH (RC-250)
GAL 25,926.000 $4.000 $4.250 $3.700 $3.700 $3.000
AGGR(TY-B GR-5 SAC-A)
CY 961.000 $100.000 $84.000 $85.000 $80.000 $96.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 92,318.000 $75.000 $77.000 $92.000 $75.000 $82.500
SUPERPAVE MIXTURES SP-D SAC-A PG70-22
TON 52,683.000 $75.000 $90.000 $93.000 $77.000 $85.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 2,000.000 $20.000 $80.000 $40.000 $30.000 $55.000
CEM STABIL BKFL
CY 1,211.000 $300.000 $165.000 $200.000 $230.000 $250.000
TEMPORARY SPL SHORING
SF 10,095.000 $50.000 $5.000 $16.000 $54.000 $55.000
DRILL SHAFT (18 IN)
LF 146.000 $70.000 $175.000 $55.000 $210.000 $222.000
DRILL SHAFT (36 IN)
LF 1,533.000 $155.000 $300.000 $160.000 $410.000 $444.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 64.000 $250.000 $357.000 $50.000 $155.000 $400.000
CL C CONC (ABUT)
CY 81.800 $1,500.000 $1,912.000 $800.000 $2,050.000 $2,220.000
CL C CONC (CAP)
CY 70.800 $1,500.000 $2,023.000 $1,300.000 $2,050.000 $2,220.000
CL C CONC (COLUMN)
CY 62.900 $1,500.000 $1,640.000 $850.000 $2,050.000 $2,220.000
REINF CONC SLAB
SF 24,840.000 $30.000 $27.500 $18.000 $32.000 $33.300
APPROACH SLAB
CY 83.400 $850.000 $1,012.000 $600.000 $2,050.000 $2,220.000
PRESTR CONC GIRDER (TX54)
LF 3,664.000 $130.000 $217.000 $170.000 $260.000 $277.500
SILICONE RESIN PAINT FINISH
SF 1,660.000 $5.250 $5.240 $8.500 $5.300 $10.000
CONC STR REPAIR (EPOXY MORTAR)
SF 115.000 $300.000 $130.000 $100.000 $230.000 $228.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 60.000 $235.000 $168.000 $135.000 $250.000 $282.000
CONC STR REPAIR (STANDARD)
SF 185.000 $180.000 $123.000 $120.000 $220.000 $198.000
RIPRAP (CONC)(4 IN)
CY 3.000 $500.000 $1,009.000 $600.000 $720.000 $600.000
RIPRAP (CONC)(5 IN)
CY 248.000 $550.000 $627.000 $500.000 $750.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 196.000 $525.000 $729.000 $550.000 $540.000 $500.000
RIPRAP (STONE TY F)(DRY)(18")
CY 92.000 $220.000 $642.000 $160.000 $120.000 $200.000
RAIL (TY SSTR)
LF 992.000 $40.000 $95.000 $85.000 $105.000 $111.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 158.000 $95.000 $175.000 $100.000 $110.000 $111.000
CMP (GAL STL 24 IN)
LF 424.000 $80.000 $56.000 $45.000 $110.000 $60.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 127.000 $820.000 $811.000 $650.000 $900.000 $426.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 352.000 $800.000 $620.000 $675.000 $690.000 $492.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 937.000 $1,130.000 $680.000 $680.000 $640.000 $630.000
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 463.000 $1,000.000 $820.000 $685.000 $740.000 $630.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 258.000 $1,000.000 $812.000 $695.000 $820.000 $690.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 288.000 $1,800.000 $870.000 $725.000 $880.000 $780.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 48.000 $1,020.000 $1,120.000 $750.000 $1,250.000 $690.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 389.000 $1,700.000 $970.000 $730.000 $1,130.000 $756.000
RC PIPE (CL IV)(24 IN)
LF 108.000 $210.000 $177.000 $60.000 $210.000 $150.000
WINGWALL (PW - 1) (HW=5 FT)
EA 4.000 $12,000.000 $25,000.000 $13,000.000 $13,000.000 $15,000.000
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(C)
EA 22.000 $4,875.000 $6,700.000 $4,500.000 $5,850.000 $4,200.000
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 1.000 $6,000.000 $8,420.000 $4,000.000 $7,000.000 $4,560.000
SET (TY I)(S=3 FT)(HW= 4 FT)(6:1)(C)
EA 37.000 $6,500.000 $6,150.000 $4,500.000 $4,400.000 $4,740.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
EA 6.000 $7,550.000 $6,650.000 $6,000.000 $9,300.000 $5,100.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(6:1) (C)
EA 89.000 $6,850.000 $6,850.000 $7,500.000 $5,080.000 $7,440.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1) (C)
EA 14.000 $6,700.000 $5,950.000 $7,000.000 $7,280.000 $4,800.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (C)
EA 26.000 $8,550.000 $8,100.000 $7,500.000 $7,500.000 $6,840.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(6:1) (C)
EA 7.000 $12,500.000 $9,800.000 $8,500.000 $10,500.000 $8,880.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1) (C)
EA 15.000 $7,500.000 $8,600.000 $6,000.000 $8,080.000 $6,240.000
SET (TY I)(S= 5 FT)(HW= 6 FT)(6:1) (C)
EA 15.000 $12,400.000 $11,900.000 $8,000.000 $9,820.000 $9,000.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 4.000 $9,600.000 $6,600.000 $6,000.000 $7,300.000 $5,160.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(6:1) (C)
EA 4.000 $8,500.000 $8,200.000 $9,000.000 $8,500.000 $7,560.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C)
EA 16.000 $9,000.000 $7,200.000 $9,500.000 $7,480.000 $7,800.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(6:1) (C)
EA 19.000 $15,000.000 $9,600.000 $10,000.000 $9,250.000 $10,800.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 6.000 $1,500.000 $4,410.000 $1,300.000 $2,000.000 $1,920.000
SET (TY II) (24 IN) (RCP) (5: 1) (P)
EA 6.000 $1,700.000 $5,200.000 $1,800.000 $3,000.000 $2,400.000
CLEAN EXIST CULVERTS
EA 36.000 $2,100.000 $1,200.000 $1,500.000 $1,300.000 $1,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $85,000.000 $400,000.000 $55,000.000 $500,000.000 $444,000.000
REMOV STR (SMALL FENCE)
LF 196.000 $10.000 $2.500 $15.000 $10.500 $12.000
MOBILIZATION
LS 1.000 $2,227,647.780 $3,135,000.000 $3,000,000.000 $2,500,000.000 $2,850,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 29.000 $10,000.000 $5,000.000 $7,000.000 $9,000.000 $10,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 200.000 $20.000 $32.500 $20.000 $35.000 $19.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 54.000 $100.000 $116.000 $150.000 $125.000 $70.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 8,940.000 $6.000 $6.200 $6.000 $6.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 8,940.000 $2.000 $0.750 $1.750 $1.000 $0.700
CONSTRUCTING DETOURS
SY 5,263.000 $10.000 $24.000 $30.000 $22.000 $35.000
PTB (FRN&INSTL)(SGL SLP)(TY 1) OR (STL)
LF 7,740.000 $57.000 $47.000 $57.000 $110.000 $108.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 12,360.000 $17.000 $7.000 $18.000 $10.000 $18.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 6,075.000 $22.000 $9.000 $16.000 $11.000 $22.000
DRIVEWAYS (CONC)
SY 71.000 $150.000 $128.000 $190.000 $90.000 $130.000
CURB RAMPS (TY 22)
SY 40.000 $250.000 $134.000 $315.000 $85.000 $150.000
RUMBLE STRIPS (SHOULDER)
LF 152,700.000 $0.130 $0.140 $0.090 $0.080 $0.080
RUMBLE STRIPS (CENTERLINE)
LF 74,569.000 $0.210 $0.150 $0.090 $0.080 $0.080
CONC MEDIAN
SY 2,780.000 $75.000 $102.000 $71.000 $60.000 $100.000
CONC DIRECTIONAL ISLAND
SY 1,091.000 $150.000 $84.000 $63.000 $72.000 $100.000
MTL W-BEAM GD FEN (STEEL POST)
LF 3,600.000 $23.000 $27.000 $25.000 $26.000 $31.200
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,000.000 $2,500.000 $2,200.000 $3,400.000 $2,940.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,600.000 $1,700.000 $1,800.000 $1,200.000 $1,920.000
REMOVE METAL BEAM GUARD FENCE
LF 8,112.000 $4.000 $5.000 $4.000 $4.250 $4.800
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,800.000 $3,600.000 $2,900.000 $2,250.000 $4,200.000
CRASH CUSH ATTEN (INSTL)
EA 26.000 $17,300.000 $5,000.000 $5,500.000 $16,000.000 $20,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 48.000 $2,500.000 $1,500.000 $3,800.000 $3,000.000 $4,200.000
CRASH CUSH ATTEN (REMOVE)
EA 20.000 $1,200.000 $1,000.000 $1,800.000 $1,000.000 $2,500.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 8.000 $4,300.000 $3,800.000 $4,270.000 $4,400.000 $3,500.000
CONDT (PVC) (SCH 40) (1 1/4")
LF 199.000 $8.000 $12.500 $12.500 $6.300 $16.000
CONDT (PVC) (SCH 40) (2")
LF 1,280.000 $6.400 $15.500 $5.500 $7.300 $16.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 6,005.000 $20.000 $21.000 $30.000 $15.000 $15.000
ELEC CONDR (NO.10) BARE
LF 1,885.000 $1.000 $1.100 $1.660 $0.540 $1.200
ELEC CONDR (NO.10) INSULATED
LF 3,770.000 $1.000 $1.100 $1.660 $0.540 $1.100
GROUND BOX TY A (122311)W/APRON
EA 4.000 $1,050.000 $1,100.000 $1,140.000 $700.000 $1,400.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $6,000.000 $4,600.000 $7,350.000 $7,800.000 $6,300.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 94.000 $700.000 $920.000 $504.000 $450.000 $510.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 12.000 $850.000 $2,100.000 $1,640.000 $1,450.000 $1,658.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 8.000 $1,600.000 $1,800.000 $1,440.000 $1,300.000 $1,458.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 11.000 $1,600.000 $1,400.000 $985.000 $890.000 $996.000
REMOVE SM RD SN SUP&AM
EA 63.000 $125.000 $102.000 $90.000 $80.000 $90.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 141.000 $40.000 $153.000 $72.000 $80.000 $90.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 104.000 $53.000 $153.000 $65.000 $80.000 $90.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 52.000 $37.000 $51.000 $40.000 $107.000 $26.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 338,584.000 $0.160 $0.150 $0.110 $0.120 $0.130
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
LF 800.000 $0.700 $0.550 $0.250 $0.240 $0.260
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 2,510.000 $0.700 $0.360 $0.250 $0.240 $0.260
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 336,644.000 $0.160 $0.150 $0.110 $0.120 $0.130
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 18,554.000 $3.500 $4.250 $4.500 $3.200 $3.600
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 17,799.000 $3.500 $4.250 $4.500 $3.200 $3.600
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 39,135.000 $0.500 $0.850 $1.900 $0.800 $0.900
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 14,461.000 $0.500 $0.850 $1.900 $0.800 $0.900
WK ZN PAV MRK REMOV (Y)24"(SLD)
LF 9,754.000 $5.000 $4.250 $15.100 $4.300 $4.800
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,236.000 $2.050 $2.000 $1.250 $1.500 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 8,262.000 $2.100 $2.000 $1.250 $1.500 $0.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 2,290.000 $0.750 $1.250 $0.950 $0.650 $0.720
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 9,833.000 $0.750 $0.800 $0.950 $0.650 $0.720
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 18.000 $40.000 $21.000 $16.500 $22.500 $25.200
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 61,129.000 $0.450 $0.400 $0.500 $0.320 $0.360
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 152,700.000 $0.300 $0.350 $0.500 $0.320 $0.360
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 171,344.000 $0.300 $0.350 $0.500 $0.320 $0.360
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 323.000 $10.000 $17.000 $17.000 $22.500 $25.200
PREFAB PAV MRK TY C (W) (ARROW)
EA 28.000 $220.000 $234.000 $258.000 $260.000 $300.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 12.000 $400.000 $360.000 $610.000 $890.000 $996.000
PREFAB PAV MRK TY C (W) (WORD)
EA 28.000 $250.000 $254.000 $345.000 $510.000 $570.000
REFL PAV MRKR TY I-C
EA 2,018.000 $3.650 $2.800 $3.600 $3.200 $3.600
REFL PAV MRKR TY II-A-A
EA 2,678.000 $3.000 $2.800 $3.600 $3.200 $3.600
ELIM EXT PAV MRK & MRKS (4")
LF 312,902.000 $0.600 $0.400 $0.750 $0.700 $0.780
ELIM EXT PAV MRK & MRKS (24")
LF 3,443.000 $2.750 $2.600 $12.000 $3.700 $4.100
TEMP TRAF SIGNALS
EA 4.000 $25,000.000 $50,000.000 $51,000.000 $40,000.000 $22,000.000
VEH SIG SEC (12")LED(YEL)
EA 4.000 $225.000 $305.000 $265.000 $390.000 $400.000
TRF SIG CBL (TY A)(8 AWG)(4 CONDR)
LF 135.000 $5.500 $6.100 $3.250 $1.100 $4.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $8,500.000 $9,100.000 $6,044.000 $6,250.000 $5,700.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $15,000.000 $25,000.000 $16,100.000 $20,000.000 $9,000.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $10,000.000 $8,000.000 $10,100.000 $10,000.000 $9,500.000
TMA (STATIONARY)
EA 3.000 $1,500.000 $85,000.000 $19,700.000 $70,000.000 $15,000.000
TMA (MOBILE OPERATION)
HR 480.000 $100.000 $72.000 $265.000 $100.000 $108.000
SOLAR POWERED LED ROADSIDE SIGN
EA 2.000 $4,000.000 $5,100.000 $5,000.000 $4,000.000 $2,800.000
Totals: $32,404,200.250 $32,027,183.640 $32,381,290.390 $32,689,371.590 $33,940,860.510