REEVES IH 20 (0003-06-103)

Items: 73

County: REEVES
Length: 0.0000 MILES
Highway: IH 20
District: ODESSA
Control Number: 0003-06-103
DBE Goal: 0.0%
Project: F 2024(536)
Guaranty: $100,000.00
Time: 240 WORKING DAYS
Engineer's Estimate: $37,995,861.93
Date: 11/07/2024 (1 year ago)
Contract Number: 11243203
Type: ROADWAY REHABILITATION
Project ID: A00180194
Project Description: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$37,995,861.93
$31,497,131.45
Over/Under Est: -17.1% -$6,498,730.48
Over/Under Est: -11.97% -$4,548,642.74
Amt Left: 6.19% $1,950,087.74
$35,097,370.90
Over/Under Est: -7.63% -$2,898,491.03
Amt Left: 11.43% $3,600,239.45
Delta: -4.93% -$1,650,151.71
Over/Under Est: -6.65% -$2,524,958.33
Amt Left: 12.62% $3,973,772.15
Delta: -1.06% -$373,532.70
$36,207,690.97
Over/Under Est: -4.71% -$1,788,170.96
Amt Left: 14.96% $4,710,559.52
Delta: -2.08% -$736,787.37
Over/Under Est: -1.88% -$715,366.05
Amt Left: 18.36% $5,783,364.43
Delta: -2.96% -$1,072,804.91
Subcontractor Percentage Amount
THE TRUESDELL CORPORATION 6.38% $2,233,633.87
RENTERIA BROTHER'S CLEANING SERVICE LLC 4.16% $1,456,413.31
MAKIN' IT MOVE TRANSPORT,LLC 3.50% $1,225,347.73
AOC HAULERS LLC 3.24% $1,134,321.90
A BROTHERS MILLING, LLC 2.70% $945,268.25
J H TRUCKING 2.70% $945,268.25
RPV CONSTRUCTION, LLC 1.57% $549,655.98
TRP CONSTRUCTION GROUP, LLC 1.39% $486,638.10
HJC FARMS, INC. 0.39% $136,538.75
AARON CONCRETE CONTRACTORS, LLC 0.36% $126,035.77
COUGHLIN COMPANY I, INC. 0.14% $49,013.91
WEST TEXAS ROCK RESOURCES, LLC 0.07% $24,506.95
TOTAL SITE, INC. 0.05% $17,504.97
JVH4 SERVICES, LLC 0.05% $17,504.97
FC TRAFFIC CONTROL, INC. 0.03% $10,502.98
ROYAL REBAR INC 0.02% $7,001.99
Total: 26.75% $9,365,157.68

Bid Items & Bid Tabulations

73 Total 0 of 73
REEVES  |  IH 20  |  ODESSA  |  0003-06-103  |  11/07/2024  |  $37,995,861.93  |  F 2024(536)  |  ROADWAY REHAB  |  240 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
FNF CONSTRUCTION, INC.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
CK NEWBERRY, LLC
KIEWIT INFRASTRUCTURE SOUTH CO.
A. L. HELMCAMP, INC.
RAGLE CONSTRUCTION, INC.
REMOV CONC (CURB)
LF 1,240.000 $5.000 $15.000 $13.000 $7.500 $5.750 $25.000 $5.500
RMV (7") TRT/UNTRT BASE & ASPH PAV
SY 329,531.000 $5.000 $6.750 $8.200 $5.000 $4.230 $8.000 $13.000
SUBGR WIDEN (OC)
STA 35.000 $3,000.000 $1,195.000 $4,200.000 $1,000.000 $1,664.080 $950.000 $1,450.000
BLADING
HR 70.000 $250.000 $275.000 $400.000 $200.000 $284.670 $180.000 $146.900
PROOF ROLLING
HR 70.000 $150.000 $100.000 $150.000 $70.000 $217.750 $180.000 $94.970
FL BS (CMP IN PLC)(TY A OR B GR 4)(6")
SY 24,611.000 $10.000 $14.000 $17.500 $12.000 $11.210 $16.000 $21.500
REWORK BS MTL (TY D)(8")(ORD COMP)
SY 329,531.000 $1.000 $0.500 $1.850 $1.000 $0.740 $0.250 $2.500
PRIME COAT (AE-P)
GAL 70,828.000 $4.500 $6.000 $4.870 $5.000 $5.200 $5.000 $5.000
ASPH (AC-20-5TR)
GAL 127,280.000 $4.690 $4.500 $4.680 $3.500 $4.410 $4.500 $5.000
AGGR (TY-PB, GR-4)(SAC-A)
CY 4,280.000 $135.000 $114.000 $105.000 $122.000 $109.210 $120.000 $125.000
SP MIXES SP-B SAC-B PG70-22
TON 119,534.000 $128.000 $83.000 $94.000 $113.000 $95.000 $111.000 $98.860
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 55,224.000 $165.000 $0.000 $0.000 $140.000 $140.000 $153.000 $112.000
PLANE & TEXT ASPH CONC PAV(0" TO 6")
SY 11,103.000 $6.120 $6.000 $8.500 $7.000 $9.040 $14.000 $5.200
PLANE & TEXT ASPH CONC PAV(2")
SY 609,233.000 $1.600 $2.000 $2.350 $2.000 $1.920 $1.650 $2.560
DRILL SHAFT (24 IN)
LF 4.000 $200.000 $360.000 $402.500 $85.000 $400.380 $367.000 $78.000
DRILL SHAFT (SIGN MTS) (12 IN)
LF 15.000 $135.000 $560.000 $632.500 $200.000 $629.170 $577.000 $184.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 3,150.000 $75.000 $35.000 $83.260 $73.000 $93.490 $57.000 $20.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 1,350.000 $150.000 $95.000 $165.370 $145.000 $190.620 $86.000 $70.000
RIPRAP (MOW STRIP)(4 IN)
CY 102.000 $700.000 $1,150.000 $747.500 $775.000 $915.150 $682.000 $825.000
CLEANING AND SEALING EXISTING JOINTS
LF 4,558.000 $45.000 $32.000 $37.160 $33.000 $36.960 $16.000 $45.000
POLYESTER POLYMER CONC OVERLAY (2")
SY 11,103.000 $150.000 $259.000 $276.660 $202.000 $292.010 $295.000 $201.000
JOINT SEALANT
LF 4,558.000 $20.000 $9.000 $1.150 $33.000 $36.960 $35.000 $22.000
MOBILIZATION
LS 1.000 $3,488,076.000 $3,149,000.000 $1,300,000.000 $3,500,000.000 $3,746,849.970 $2,150,000.000 $3,700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $30,000.000 $59,600.000 $30,000.000 $10,000.000 $52,704.590 $30,000.000 $120,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $15,000.000 $7,000.000 $16,500.000 $15,000.000 $22,391.760 $18,000.000 $25,000.000
TMA (STATIONARY)
DAY 368.000 $150.000 $300.000 $165.000 $325.000 $538.670 $500.000 $346.000
TMA (MOBILE OPERATION)
DAY 736.000 $160.000 $495.000 $350.000 $150.000 $1,018.670 $200.000 $844.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,320.000 $13.750 $13.000 $15.000 $11.000 $12.300 $9.000 $11.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,320.000 $2.000 $3.000 $8.000 $3.000 $3.150 $3.000 $3.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,023.000 $100.000 $85.000 $28.750 $60.000 $140.040 $62.000 $100.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 1,023.000 $20.000 $6.000 $23.000 $30.000 $7.930 $21.000 $14.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,023.000 $20.000 $7.000 $28.750 $30.000 $9.440 $26.000 $19.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 1,350.000 $93.000 $140.000 $155.250 $150.000 $176.860 $166.000 $129.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 255,552.000 $0.170 $0.100 $0.180 $0.200 $0.210 $0.250 $0.160
MTL W-BEAM GD FEN (STEEL POST)
LF 10,950.000 $37.500 $29.000 $34.210 $30.000 $30.890 $31.000 $29.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 21.000 $3,500.000 $2,500.000 $3,450.000 $2,100.000 $2,917.050 $3,150.000 $2,656.000
TERMINAL ANCHOR SECTION
EA 10.000 $100.000 $1,600.000 $1,351.250 $1,100.000 $1,715.910 $1,200.000 $1,010.000
REMOVE METAL BEAM GUARD FENCE
LF 10,950.000 $2.500 $3.000 $2.300 $3.000 $2.860 $2.100 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $875.000 $110.000 $230.000 $200.000 $114.390 $210.000 $200.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $300.000 $110.000 $230.000 $225.000 $114.390 $210.000 $210.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 19.000 $205.000 $210.000 $230.000 $250.000 $228.790 $210.000 $235.000
GUARDRAIL END TREATMENT (INSTALL)
EA 17.000 $4,000.000 $3,100.000 $3,335.000 $3,000.000 $3,431.820 $3,045.000 $2,860.000
GUARDRAIL END TREATMENT (REMOVE)
EA 17.000 $335.000 $210.000 $230.000 $300.000 $228.790 $210.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 12.000 $1,500.000 $240.000 $2,587.500 $1,400.000 $583.360 $2,362.000 $1,385.000
CRASH CUSH ATTEN (REMOVE)
EA 12.000 $1,500.000 $345.000 $1,437.500 $800.000 $466.500 $1,312.000 $735.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 14.000 $10,555.000 $1,000.000 $9,487.500 $8,000.000 $7,076.190 $8,662.000 $7,660.000
ALUMINUM SIGNS (TY G)
SF 1,428.000 $35.000 $17.000 $18.400 $28.000 $18.300 $16.800 $27.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 52.000 $840.000 $915.000 $1,035.000 $700.000 $1,029.550 $945.000 $665.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $1,000.000 $1,020.000 $1,150.000 $900.000 $1,143.940 $1,050.000 $880.000
REMOVE SM RD SN SUP&AM
EA 62.000 $152.000 $105.000 $180.000 $85.000 $114.390 $105.000 $80.000
INSTALL LRSS (STRUCT STEEL)
LB 6,454.000 $8.000 $3.000 $3.450 $6.000 $3.430 $3.150 $5.850
REMOVE LRSA
EA 17.000 $1,275.000 $255.000 $287.500 $700.000 $285.990 $262.000 $670.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BR)
EA 24.000 $23.000 $42.000 $69.000 $45.000 $68.640 $63.000 $43.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 100.000 $40.000 $42.000 $17.250 $45.000 $45.760 $15.750 $43.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BR)
EA 32.000 $22.000 $42.000 $69.000 $45.000 $68.640 $63.000 $43.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 100.000 $30.000 $42.000 $28.750 $45.000 $45.760 $26.250 $43.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 32.000 $120.000 $145.000 $172.500 $100.000 $171.590 $157.500 $94.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 210.000 $35.000 $15.000 $75.000 $15.000 $17.160 $15.750 $15.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 31,944.000 $0.800 $0.500 $0.400 $0.350 $0.400 $0.390 $0.350
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 127,776.000 $0.310 $0.500 $0.400 $0.350 $0.400 $0.390 $0.350
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 127,776.000 $0.320 $0.500 $0.400 $0.350 $0.400 $0.390 $0.350
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,597.000 $2.950 $0.500 $3.000 $5.000 $2.310 $1.110 $2.370
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 69,100.000 $0.750 $1.000 $0.980 $0.850 $0.970 $0.940 $0.850
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 270.000 $8.000 $12.000 $14.380 $12.500 $14.300 $13.890 $12.500
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 31,944.000 $0.700 $0.750 $0.810 $0.700 $0.800 $0.780 $0.700
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 127,776.000 $0.850 $0.750 $0.750 $0.650 $0.740 $0.720 $0.650
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 127,776.000 $0.850 $0.750 $0.750 $0.650 $0.740 $0.720 $0.650
REFL PAV MRKR TY I-R
EA 84.000 $15.000 $10.000 $11.500 $10.000 $11.440 $11.110 $10.000
REFL PAV MRKR TY II-C-R
EA 2,158.000 $6.750 $5.000 $5.750 $5.000 $5.720 $5.560 $5.000
ELIM EXT PM & MRKS (4")
LF 127,776.000 $0.800 $0.750 $0.750 $0.700 $1.150 $0.720 $0.650
ELIM EXT PM & MRKS (8")
LF 30,439.000 $1.000 $1.000 $0.980 $0.900 $1.160 $0.940 $0.850
BONDING COURSE
GAL 61,041.000 $5.200 $6.000 $4.650 $5.000 $5.070 $3.500 $4.800
1
STONE-MTRX-ASPH SMAR-F SAC-A
TON 55,224.000 $165.000 $116.000 $135.000 $0.000 $0.000 $0.000 $0.000
Totals: $47,107,821.930 $31,497,131.450 $33,447,219.190 $35,097,370.900 $35,470,903.600 $36,207,690.970 $37,280,495.880