REEVES IH 20 (0003-06-101)
Items: 70
County: REEVES
Length: 0.0000 MILES
Highway: IH 20
District: ODESSA
Control Number: 0003-06-101
DBE Goal: 0.0%
Project: F 2024(535)
Guaranty: $100,000.00
Time: 240 WORKING DAYS
Engineer's Estimate: $41,098,806.79
Date: 11/06/2024 (1 year ago)
Contract Number: 11243004
Type: HIGHWAY IMPROVEMENT
Project ID: A00178419
Project Description: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
ODA-PRELETTINGQUESTIONS
REEVES IH 20 (0003-06-101)
Project Name: N/A
Project: F 2024(535)
Length: 0.0000 MILES
Project Type: REHABILITATION OF EXISTING ROAD
Limits From: 0.35 MILES W OF CR 210
Limits To: 0.15 MI W OF CR 209
Project Description: ROADWAY REHABILITATION
REEVES IH 20 (0003-07-062)
Project Name: IH20_0.15MI_W_CR209_COUNTRY_CLUB
Project: F 2024(535)
Length: 0.0000 MILES
Project Type: REHABILITATION OF EXISTING ROAD
Limits From: 0.15 MI WEST OF CR 209
Limits To: COUNTRY CLUB
Project Description: ROADWAY REHABILITATION
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$41,098,806.79 | |||
| $27,943,634.65 |
-32.01%
-$13,155,172.14
|
|||
| $33,068,620.67 |
-19.54%
-$8,030,186.12
|
18.34%
$5,124,986.02
|
||
| $36,005,377.72 |
-12.39%
-$5,093,429.07
|
28.85%
$8,061,743.07
|
-8.88%
-$2,936,757.05
|
|
| $37,424,324.55 |
-8.94%
-$3,674,482.24
|
33.93%
$9,480,689.90
|
-3.94%
-$1,418,946.83
|
|
| $38,336,381.95 |
-6.72%
-$2,762,424.84
|
37.19%
$10,392,747.30
|
-2.44%
-$912,057.40
|
|
| $41,282,655.33 |
0.45%
$183,848.54
|
47.74%
$13,339,020.68
|
-7.69%
-$2,946,273.38
|
E
Engineer's Estimate
$41,098,806.79
1
Awarded
$27,943,634.65
Over/Under Est:
-32.01%
-$13,155,172.14
$33,068,620.67
Over/Under Est:
-19.54%
-$8,030,186.12
Amt Left:
18.34%
$5,124,986.02
$36,005,377.72
Over/Under Est:
-12.39%
-$5,093,429.07
Amt Left:
28.85%
$8,061,743.07
Delta:
-8.88%
-$2,936,757.05
$37,424,324.55
Over/Under Est:
-8.94%
-$3,674,482.24
Amt Left:
33.93%
$9,480,689.90
Delta:
-3.94%
-$1,418,946.83
$38,336,381.95
Over/Under Est:
-6.72%
-$2,762,424.84
Amt Left:
37.19%
$10,392,747.30
Delta:
-2.44%
-$912,057.40
$41,282,655.33
Over/Under Est:
0.45%
$183,848.54
Amt Left:
47.74%
$13,339,020.68
Delta:
-7.69%
-$2,946,273.38
| Subcontractor | Percentage | Amount |
|---|---|---|
| THE TRUESDELL CORPORATION | 5.68% | $1,759,750.46 |
| RENTERIA BROTHER'S CLEANING SERVICE LLC | 4.22% | $1,307,420.24 |
| MAKIN' IT MOVE TRANSPORT,LLC | 3.31% | $1,025,488.39 |
| AOC HAULERS LLC | 3.22% | $997,605.02 |
| A BROTHERS MILLING, LLC | 2.58% | $799,323.27 |
| RPV CONSTRUCTION, LLC | 2.01% | $622,728.60 |
| TRP CONSTRUCTION GROUP, LLC | 1.37% | $424,446.85 |
| J H TRUCKING | 0.92% | $285,030.00 |
| DK CONTRACTING, LLC | 0.70% | $216,870.66 |
| BARRICADES UNLIMITED | 0.19% | $58,864.89 |
| WEST TEXAS ROCK RESOURCES, LLC | 0.11% | $34,079.67 |
| COUGHLIN COMPANY I, INC. | 0.08% | $24,785.22 |
| JVH4 SERVICES, LLC | 0.03% | $9,294.46 |
| FC TRAFFIC CONTROL, INC. | 0.03% | $9,294.46 |
| Total: | 24.45% | $7,574,982.19 |
Bid Items & Bid Tabulations
70
Total
0 of 70