Show Job Controls
Bid Cobra

PRESIDIO US 67 (0104-09-034)

Items: 78

County: PRESIDIO
Length: 0.0000 MILES
Highway: US 67
District: EL PASO
Control Number: 0104-09-034
DBE Goal: 5.0%
Project: STP 2025(803)HES
Guaranty: $60,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $2,999,398.78
Date: 06/05/2025 (1 year ago)
Contract Number: 6253224
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184477
Contract Type: Federal
Project Description: INSTALL CONTIUOUS TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ARMANDO RAMIREZ
ALDO MADRID
MONICA RUIZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$2,999,398.78
$3,181,974.20
Over/Under Est: 6.09% $182,575.42
$4,555,691.75
Over/Under Est: 51.89% $1,556,292.97
Amt Left: 43.17% $1,373,717.55
Subcontractor Percentage Amount
MAJOR MOTION LOGISTICS, LLC 4.91% $159,172.05
PMI PAVEMENT MARKING, LLC 2.65% $85,907.52
WEST TEXAS RUMBLE STRIP LLC 0.20% $6,483.59
Total: 7.76% $251,563.16

Bid Items & Bid Tabulations

78 Total 0 of 78
PRESIDIO  |  US 67  |  EL PASO  |  0104-09-034  |  06/05/2025  |  $2,999,398.78  |  STP 2025(803)HES  |  HAZARD ELIM & SAFETY  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
CK NEWBERRY, LLC
REMOV CONC (DRIVEWAYS)
SY 132.000 $175.000 $45.000 $100.000
RMV (10") TRT/UNTRT BASE & ASPH PAV
SY 1,022.000 $12.000 $20.000 $30.000
EXCAV (ROADWAY)
CY 1,863.000 $30.000 $25.000 $32.000
SUBGR WIDEN (DC)
SY 6,338.000 $35.000 $12.000 $10.000
EMBANK (FNL)(DC)(TY A)
CY 7,422.000 $50.000 $45.000 $125.000
FL BS (CMP IN PLC)(TY A GR 1-2) (8")
SY 6,338.000 $30.000 $50.000 $50.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 48.000 $400.000 $350.000 $400.000
LIME TRT(SUBGRADE)(6")
SY 6,338.000 $3.000 $8.900 $6.000
PRIME COAT (MULTI OPTION)
GAL 4,603.000 $15.000 $6.500 $5.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 328.000 $6.000 $10.000 $15.000
FOG SEAL (CSS-1H)
GAL 253.000 $6.000 $12.000 $20.000
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 500.000 $180.000 $300.000 $400.000
SP MIXES SP-C SAC-A PG70-22
TON 2,509.000 $170.000 $275.000 $350.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 587.000 $170.000 $165.000 $200.000
PLANE ASPH CONC PAV(0" TO 0.5" MICRO)
SY 1,000.000 $7.000 $20.000 $40.000
PLANE ASPH CONC PAV(2")
SY 17,970.000 $8.000 $4.000 $6.000
RIPRAP (MOW STRIP)(4 IN)
CY 32.000 $700.000 $1,400.000 $1,500.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 531.000 $600.000 $250.000 $300.000
CMP (GAL STL 30 IN)
LF 24.000 $350.000 $350.000 $600.000
CMP (GAL STL 36 IN)
LF 7.000 $200.000 $600.000 $700.000
CMP AR (GAL STL DES 4)
LF 4.000 $300.000 $800.000 $1,100.000
RC PIPE (CL III)(18 IN)
LF 112.000 $90.000 $175.000 $200.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,450.000 $3,000.000 $8,000.000
SET (TY II) (30 IN) (CMP) (3: 1) (C)
EA 2.000 $3,000.000 $2,500.000 $10,000.000
SET (TY II) (30 IN) (CMP) (4: 1) (C)
EA 2.000 $3,500.000 $2,500.000 $12,000.000
SET (TY II) (36 IN) (CMP) (4: 1) (C)
EA 2.000 $4,000.000 $3,000.000 $15,000.000
SET (TY II) (DES 4) (CMP) (4: 1) (C)
EA 2.000 $4,000.000 $2,500.000 $20,000.000
REMOV STR (SET)
EA 8.000 $1,500.000 $600.000 $10,000.000
MOBILIZATION
LS 1.000 $266,763.530 $300,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $13,000.000 $42,500.000 $25,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $15,000.000 $12,000.000 $10,000.000
TMA (STATIONARY)
DAY 75.000 $720.000 $300.000 $500.000
TMA (MOBILE OPERATION)
DAY 2.000 $900.000 $900.000 $750.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $50.000 $140.000 $120.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 100.000 $87.000 $165.000 $160.000
ROCK FILTER DAMS (REMOVE)
LF 160.000 $17.000 $32.000 $30.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 311.000 $31.000 $55.000 $55.000
CONSTRUCTION EXITS (REMOVE)
SY 311.000 $11.500 $12.500 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,310.000 $5.500 $5.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,310.000 $1.700 $1.750 $5.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 64.000 $105.000 $75.000 $75.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 384.000 $130.000 $135.000 $150.000
DRIVEWAYS (CONC)
SY 449.000 $180.000 $155.000 $225.000
DRIVEWAYS (BASE)
SY 1,046.000 $50.000 $35.000 $40.000
DRIVEWAYS (SURF TREAT)
SY 570.000 $50.000 $100.000 $60.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 5,665.000 $0.500 $1.000 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $30.000 $45.000 $150.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,300.000 $3,500.000 $6,500.000
REMOVE METAL BEAM GUARD FENCE
LF 250.000 $7.500 $15.000 $50.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 2.000 $450.000 $450.000 $8,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $6,000.000 $5,000.000 $11,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $330.000 $450.000 $6,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 13.000 $900.000 $900.000 $900.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 2.000 $800.000 $950.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $1,000.000 $950.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $1,300.000 $1,150.000 $1,300.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 5.000 $1,200.000 $1,300.000 $1,400.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,350.000 $1,400.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 3.000 $1,300.000 $950.000 $1,100.000
REMOVE SM RD SN SUP&AM
EA 26.000 $200.000 $250.000 $500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $45.000 $105.000 $125.000
INSTL DEL ASSM (D-DW)SZ 1(WFLX)GND(BI)
EA 28.000 $220.000 $165.000 $175.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 4.000 $100.000 $145.000 $150.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 31.000 $40.000 $55.000 $60.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 430.000 $3.000 $2.300 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 430.000 $2.000 $2.300 $2.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 255.000 $2.000 $1.350 $1.500
PAVEMENT SLER 6"
LF 95.000 $1.150 $0.850 $1.000
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 7,805.000 $1.100 $0.850 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 1,435.000 $1.400 $1.050 $1.250
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 9,540.000 $2.000 $0.850 $1.000
PREFAB PM TY C (W)(24")(SLD)
LF 72.000 $20.000 $11.000 $15.000
PREFAB PM TY C (W)(ARROW)
EA 14.000 $330.000 $210.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 2.000 $400.000 $275.000 $400.000
REFL PAV MRKR TY I-C
EA 13.000 $8.000 $6.000 $8.000
REFL PAV MRKR TY II-A-A
EA 282.000 $15.000 $7.500 $10.000
ELIM EXT PM & MRKS (4")
LF 95.000 $1.200 $6.800 $25.000
PAV SURF PREP FOR MRK (6")
LF 95.000 $0.500 $0.900 $2.000
Totals: $2,999,398.780 $3,181,974.200 $4,555,691.750
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $25,000.00