POTTER IH 40 (0275-01-204)

Items: 52

County: POTTER
Length: N/A
Highway: IH 40
District: AMARILLO
Control Number: 0275-01-204
DBE Goal: N/A
Project: STP 1902(138)HES
Guaranty: N/A
Time: 168 WORKING DAYS
Engineer's Estimate: $4,330,373.70
Date: 07/10/2019 (6 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$4,330,373.70
$4,995,101.00
Over/Under Est: 15.35% $664,727.30
$4,996,329.75
Over/Under Est: 15.38% $665,956.05
Amt Left: 0.02% $1,228.75
Over/Under Est: 30.4% $1,316,523.65
Amt Left: 13.05% $651,796.35
Delta: -13.02% -$650,567.60

Bid Items & Bid Tabulations

52 Total 0 of 52
POTTER  |  IH 40  |  AMARILLO  |  0275-01-204  |  07/10/2019  |  $4,330,373.70  |  STP 1902(138)HES  |  INSTL MEDIAN BARRIER  |  168 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA CONSTRUCTION INC.
HJC FARMS, INC.
SCR CIVIL CONSTRUCTION, LLC
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 8.000 $900.000 $1,500.000 $1,000.000 $1,400.000
REMOVING CONC (RIPRAP)
SY 576.000 $12.000 $11.000 $15.000 $81.000
REMOVING CONC (CTB)
LF 950.000 $6.500 $46.000 $50.000 $77.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 2,105.000 $18.000 $33.000 $20.000 $71.600
DRILL SEED (TEMP)(WARM OR COOL)
SY 11,725.000 $0.500 $0.400 $0.200 $0.340
EMULS ASPH (EROSN CONT)(MS-2)
GAL 733.000 $7.000 $5.000 $5.000 $11.000
CL A CONC (MISC)
CY 2.000 $700.000 $850.000 $600.000 $6,600.000
RIPRAP (CONC)(4 IN)
CY 134.000 $450.000 $520.000 $600.000 $907.000
RIPRAP (MOW STRIP)(4 IN)
CY 3,924.000 $445.000 $395.000 $650.000 $544.000
GABION MATTRESSES (GALV)(12 IN)
SY 64.000 $150.000 $88.000 $90.000 $409.000
MOBILIZATION
LS 1.000 $350,000.000 $441,022.000 $100,000.000 $210,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $15,000.000 $24,000.000 $5,000.000 $19,250.000
PORT CTB (DES SOURCE) (SAFETY SH)(TY 2)
LF 1,500.000 $8.000 $16.000 $20.000 $26.150
PORT CTB (STKPL)(SAFETY SH)
LF 1,500.000 $8.000 $16.000 $20.000 $26.150
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 150.000 $55.000 $175.000 $75.000 $357.000
PERM CTB (SGL SLOPE) (TY 3) (42 )
LF 180.000 $90.000 $192.000 $180.000 $440.000
PERM CTB (SGL SLOPE) (TY 4) (42 )
LF 10.000 $110.000 $582.000 $150.000 $1,288.000
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 1,190.000 $90.000 $180.000 $105.000 $184.000
PERM CTB (SGL SLOPE)(TY 1)(TRANSITION)
LF 60.000 $210.000 $228.000 $225.000 $976.250
MTL W-BEAM GD FEN (STEEL POST)
LF 21,375.000 $26.000 $33.000 $25.390 $28.550
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 28.000 $2,200.000 $2,600.000 $2,184.000 $2,906.000
MTL BEAM GD FEN TRANS (T101)
EA 16.000 $1,150.000 $1,750.000 $1,411.000 $1,873.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 37.000 $1,200.000 $1,400.000 $1,141.000 $1,415.000
MTL BM GD FEN TRANS (NON - SYM)
EA 13.000 $870.000 $700.000 $890.000 $720.000
REMOVE METAL BEAM GUARD FENCE
LF 20,175.000 $3.000 $4.000 $3.500 $3.400
REMOVE TERMINAL ANCHOR SECTION
EA 41.000 $250.000 $500.000 $350.000 $447.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 25.000 $250.000 $400.000 $300.000 $336.000
RM MTL BM GD FEN TRANS (T101)
EA 12.000 $300.000 $400.000 $300.000 $336.000
CABLE BARRIER SYSTEM (TL-4)
LF 53,843.000 $11.000 $12.000 $10.000 $11.700
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 24.000 $2,200.000 $4,000.000 $4,000.000 $2,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 48.000 $2,900.000 $3,600.000 $3,000.000 $3,745.000
GUARDRAIL END TREATMENT (REMOVE)
EA 52.000 $300.000 $400.000 $300.000 $400.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $3,500.000 $1,000.000 $4,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 3.000 $11,000.000 $42,000.000 $30,000.000 $45,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $9,000.000 $15,000.000 $10,500.000 $12,000.000
REMOVE RD IL ASM (TRANS-BASE)
EA 1.000 $1,000.000 $550.000 $1,650.000 $1,700.000
IN RD IL (TY SP) 38S-8-8 (250W EQ) LED
EA 1.000 $4,500.000 $4,600.000 $11,000.000 $11,200.000
CONDT (PVC) (SCH 40) (2")
LF 150.000 $9.000 $10.000 $33.000 $33.500
ELEC CONDR (NO.6) BARE
LF 470.000 $2.000 $2.000 $6.600 $6.700
ELEC CONDR (NO.6) INSULATED
LF 940.000 $2.250 $2.000 $6.600 $6.700
GROUND BOX TY A (122311)W/APRON
EA 1.000 $950.000 $1,200.000 $2,750.000 $2,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $800.000 $500.000 $1,000.000 $1,120.000
REMOVE SM RD SN SUP&AM
EA 1.000 $110.000 $100.000 $125.000 $230.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 40.000 $20.000 $30.000 $20.000 $35.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 72.000 $20.000 $32.000 $20.000 $35.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 807.000 $30.000 $33.000 $35.000 $35.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 1,730.000 $1.000 $3.500 $3.500 $3.350
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 640.000 $0.330 $16.000 $16.500 $16.800
ELIM EXT PAV MRK & MRKS (4")
LF 640.000 $1.400 $4.000 $5.000 $3.350
REMOVAL OF CABLES
LF 1,410.000 $0.300 $3.000 $2.000 $0.600
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 336.000 $90.000 $90.000 $50.000 $155.000
TMA (STATIONARY)
DAY 336.000 $300.000 $200.000 $250.000 $325.000
Totals: $4,330,373.700 $4,995,101.000 $4,996,329.750 $5,646,897.350