POLK US0059 (6327-78-001)

Items: 24

County: POLK
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6327-78-001
DBE Goal: N/A
Project: RMC - 632778001
Guaranty: N/A
Time: 30 W
Engineer's Estimate: $202,539.80
Date: 11/12/2018 (7 years ago)
Contract Number: N/A
Type: FHWA_DISASTER RELIEF MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$202,539.80
$236,942.00
Over/Under Est: 16.99% $34,402.20
$237,332.85
Over/Under Est: 17.18% $34,793.05
Amt Left: 0.16% $390.85
Over/Under Est: 31.97% $64,759.70
Amt Left: 12.81% $30,357.50
Delta: -12.63% -$29,966.65

Bid Items & Bid Tabulations

24 Total 0 of 24
POLK  |  US0059  |  LUFKIN  |  6327-78-001  |  11/12/2018  |  $202,539.80  |  RMC - 632778001  |  FHWA_DISASTER RELIEF MAINT  |  30 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
CHAMPION INFRASTRUCTURE, LLC
CDM HOLDINGS, LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (MISC)
SY 15.000 $150.000 $120.000 $65.000 $100.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 1,409.000 $32.000 $40.000 $45.000 $35.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 55.000 $140.000 $150.000 $130.000 $150.000
FURNISHING AND PLACING TOPSOIL (4")
SY 283.000 $6.000 $5.000 $7.000 $10.000
COMPOST MANUF TOPSOIL (4")
SY 480.000 $2.000 $5.000 $10.000 $20.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 3,791.000 $0.800 $1.000 $1.750 $1.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 480.000 $2.000 $5.000 $2.000 $2.000
VEGETATIVE WATERING
MG 85.900 $150.000 $110.000 $50.000 $100.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 4,179.000 $3.000 $3.000 $2.400 $6.500
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 92.000 $12.000 $20.000 $4.000 $20.000
D-GR HMA(SQ) TY-D PG64-22 NON-MOW STRIP
SY 9.000 $225.000 $160.000 $275.000 $200.000
CEM STABIL BKFL
CY 10.000 $350.000 $210.000 $400.000 $350.000
FLOWABLE BACKFILL
CY 14.000 $400.000 $200.000 $400.000 $450.000
RIPRAP (CONC)(CL B)
CY 4.000 $1,000.000 $640.000 $750.000 $650.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 16.000 $400.000 $400.000 $210.000 $185.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 240.000 $200.000 $320.000 $235.000 $250.000
MOBILIZATION
LS 1.000 $17,500.000 $22,000.000 $22,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $3,200.000 $10,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,000.000 $4.000 $3.000 $3.900 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $2.000 $1.000 $1.500 $2.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,000.000 $2,300.000 $2,000.000 $2,000.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $400.000 $300.000 $500.000 $1,500.000
TREE REMOVAL (4" - 12" DIA)
EA 1.000 $500.000 $800.000 $1,000.000 $5,000.000
TMA (STATIONARY)
DAY 16.000 $400.000 $300.000 $350.000 $550.000
Totals: $202,539.800 $236,942.000 $237,332.850 $267,299.500