Show Job Controls
Bid Cobra

POLK OLD BERRING RD (0911-04-098)

Items: 56

County: POLK
Length: 0.0000 MILES
Highway: OLD BERRING RD
District: LUFKIN
Control Number: 0911-04-098
DBE Goal: 3.0%
Project: F 2B23(184)
Guaranty: $40,000.00
Time: 167 WORKING DAYS
Engineer's Estimate: $1,912,208.50
Date: 06/05/2025 (1 year ago)
Contract Number: 6253228
Type: BRIDGE REPLACEMENT
Project ID: A00185669
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLINT JONES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$1,912,208.50
$1,653,086.45
Over/Under Est: -13.55% -$259,122.05
$1,750,520.20
Over/Under Est: -8.46% -$161,688.30
Amt Left: 5.89% $97,433.75
$1,853,190.20
Over/Under Est: -3.09% -$59,018.30
Amt Left: 12.1% $200,103.75
Delta: -5.87% -$102,670.00
$1,856,686.00
Over/Under Est: -2.9% -$55,522.50
Amt Left: 12.32% $203,599.55
Delta: -0.19% -$3,495.80
Over/Under Est: 3.25% $62,121.90
Amt Left: 19.43% $321,243.95
Delta: -6.34% -$117,644.40
Over/Under Est: 3.35% $64,003.70
Amt Left: 19.55% $323,125.75
Delta: -0.10% -$1,881.80
Over/Under Est: 3.62% $69,149.00
Amt Left: 19.86% $328,271.05
Delta: -0.26% -$5,145.30
$2,579,857.42
Over/Under Est: 34.92% $667,648.92
Amt Left: 56.06% $926,770.97
Delta: -30.21% -$598,499.92
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 8.70% $143,818.52
J. H. ODEN CONTRACTING COMPANY 3.25% $53,725.31
MORRIS COUNTY CONTRACTORS, L.L.C. 3.01% $49,757.90
FLEX SUPPLY, LLC 1.03% $17,026.79
Total: 15.99% $264,328.52

Bid Items & Bid Tabulations

56 Total 0 of 56
POLK  |  OLD BERRING RD  |  LUFKIN  |  0911-04-098  |  06/05/2025  |  $1,912,208.50  |  F 2B23(184)  |  BRIDGE REPL  |  167 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRUE ROADS CONSTRUCTION, LLC
THK CONSTRUCTION LLC
SKYLINE BRIDGE LLC
STX CIVIL
EAST TEXAS BRIDGE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
ISI CONTRACTING, INC.
PREPARING ROW
STA 7.930 $2,000.000 $2,300.000 $2,000.000 $5,500.000 $3,000.000 $5,000.000 $6,500.000 $5,500.000 $5,854.000
EXCAV (ROADWAY)
CY 938.000 $20.000 $25.000 $20.000 $22.000 $30.000 $25.000 $25.000 $25.000 $76.000
EMBANK (FNL)(OC)(TY B)
CY 628.000 $30.000 $30.000 $20.000 $42.000 $20.000 $35.000 $25.000 $35.000 $63.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 2.000 $150.000 $430.000 $150.000 $500.000 $160.000 $150.000 $20.000 $1,000.000 $2,749.000
FURN & PLACE TOPSOIL (4")
SY 2,526.000 $4.000 $5.000 $3.500 $4.500 $4.000 $4.000 $4.000 $6.000 $11.000
BROADCAST SEED (TEMP_WARM)
SY 1,250.000 $2.500 $0.100 $0.710 $1.000 $1.000 $0.800 $1.000 $1.000 $0.500
BROADCAST SEED (TEMP_COOL)
SY 1,250.000 $2.500 $0.100 $0.740 $1.000 $1.000 $0.800 $1.000 $1.000 $0.500
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 2,499.000 $2.500 $5.500 $1.240 $1.500 $1.000 $1.350 $2.000 $1.500 $0.900
VEGETATIVE WATERING
TGL 103.200 $10.000 $26.000 $10.000 $1.000 $50.000 $25.000 $1.000 $50.000 $24.000
SOIL RET BLKT(SL_MOD_SAND_WLDLFE)
SY 999.000 $5.000 $5.500 $2.070 $2.500 $8.000 $2.500 $3.000 $3.000 $6.400
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 1,564.000 $45.000 $28.000 $57.500 $70.000 $60.000 $25.000 $45.000 $30.000 $23.000
CEM STABIL BKFL
CY 156.300 $350.000 $325.000 $350.000 $325.000 $220.000 $350.000 $250.000 $250.000 $91.000
DRILL SHAFT (30 IN)
LF 765.000 $350.000 $360.000 $333.960 $275.000 $300.000 $375.000 $290.000 $400.000 $465.000
CL C CONC (ABUT)
CY 54.400 $1,200.000 $1,425.000 $1,100.000 $1,350.000 $1,000.000 $1,500.000 $1,600.000 $1,550.000 $2,524.000
CL C CONC (CAP)
CY 17.800 $2,000.000 $1,575.000 $1,500.000 $1,800.000 $1,200.000 $1,500.000 $1,800.000 $1,550.000 $4,161.000
CL C CONC (COLUMN)
CY 10.900 $2,000.000 $2,100.000 $2,500.000 $2,200.000 $1,500.000 $1,500.000 $2,400.000 $2,000.000 $3,440.000
CL C CONC (RAC-R)
CY 21.000 $2,600.000 $1,475.000 $1,000.000 $1,500.000 $1,750.000 $1,000.000 $1,500.000 $1,500.000 $906.000
REINF CONC SLAB (BOX BEAM)
SF 4,690.000 $35.000 $21.000 $21.000 $30.000 $28.000 $30.000 $30.000 $32.000 $43.000
SHEAR KEY
CY 16.000 $1,000.000 $700.000 $800.000 $900.000 $700.000 $1,000.000 $800.000 $650.000 $314.000
PRESTR CONC BOX BEAM (4B20)
LF 712.000 $325.000 $290.000 $286.000 $290.000 $405.000 $295.000 $400.000 $300.000 $495.000
PRESTR CONC BOX BEAM (5B20)
LF 356.000 $350.000 $290.000 $286.000 $350.000 $430.000 $295.000 $400.000 $315.000 $589.000
RIPRAP (CONC)(5 IN)
CY 4.400 $1,000.000 $1,100.000 $1,300.000 $2,000.000 $800.000 $1,000.000 $850.000 $2,000.000 $1,808.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 42.000 $300.000 $240.000 $184.000 $220.000 $190.000 $230.000 $250.000 $230.000 $262.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 969.000 $225.000 $190.000 $184.000 $200.000 $210.000 $240.000 $190.000 $195.000 $252.000
RAIL (TY T223)
LF 272.000 $200.000 $160.000 $170.000 $165.000 $210.000 $185.000 $160.000 $200.000 $254.000
RAIL (TY T631LS)
LF 249.000 $80.000 $70.000 $75.890 $75.000 $55.000 $75.000 $70.000 $130.000 $94.000
TYPE A JOINT
LF 52.000 $50.000 $30.000 $20.000 $125.000 $70.000 $100.000 $100.000 $30.000 $152.000
RC PIPE (CL III)(36 IN)
LF 120.000 $220.000 $160.000 $185.000 $275.000 $290.000 $200.000 $150.000 $175.000 $296.000
HEADWALL (CH - FW - 45) (DIA= 36 IN)
EA 2.000 $10,000.000 $14,500.000 $30,000.000 $15,000.000 $20,000.000 $20,000.000 $15,000.000 $15,000.000 $22,693.000
CLEAN EXIST CULVERTS
EA 1.000 $2,500.000 $8,000.000 $4,000.000 $12,000.000 $3,500.000 $10,000.000 $10,000.000 $10,000.000 $7,538.000
REMOV STR (PIPE)
LF 28.000 $75.000 $75.000 $20.000 $20.000 $25.000 $100.000 $4,000.000 $150.000 $66.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $16,000.000 $57,500.000 $20,000.000 $17,500.000 $30,000.000 $30,000.000 $22,000.000 $34,481.000
MOBILIZATION
LS 1.000 $175,000.000 $140,000.000 $160,000.000 $165,000.000 $155,000.000 $195,000.000 $185,000.000 $200,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $2,000.000 $1,000.000 $969.160 $2,000.000 $2,800.000 $5,000.000 $2,000.000 $4,500.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 438.000 $50.000 $44.000 $42.120 $65.000 $40.000 $60.000 $1.000 $51.500 $48.000
ROCK FILTER DAMS (REMOVE)
LF 438.000 $15.000 $12.000 $10.800 $10.000 $5.000 $14.000 $1.000 $13.200 $21.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 167.000 $30.000 $38.000 $42.120 $20.000 $25.000 $75.000 $1.000 $51.500 $48.000
CONSTRUCTION EXITS (REMOVE)
SY 167.000 $10.000 $10.000 $10.800 $5.000 $10.000 $17.000 $1.000 $13.200 $21.000
CONSTRUCTION PERIMETER FENCE
LF 669.000 $10.000 $5.500 $5.000 $12.000 $1.000 $7.000 $1.000 $12.500 $2.700
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,495.000 $4.000 $4.750 $4.320 $4.000 $5.000 $6.000 $1.000 $5.300 $4.700
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,495.000 $1.000 $1.200 $1.080 $1.500 $1.000 $1.350 $1.000 $1.300 $1.600
DRIVEWAYS (BASE)
SY 80.000 $65.000 $46.000 $50.000 $75.000 $40.000 $60.000 $75.000 $41.000 $81.000
MTL W-BEAM GD FEN (TIM POST)
LF 331.000 $35.000 $27.500 $27.000 $29.000 $30.000 $28.000 $26.000 $41.000 $26.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,900.000 $1,863.000 $2,000.000 $2,100.000 $2,000.000 $1,800.000 $3,000.000 $2,045.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,500.000 $1,550.000 $1,539.000 $1,750.000 $1,300.000 $1,600.000 $1,500.000 $1,750.000 $1,329.000
REMOVE METAL BEAM GUARD FENCE
LF 125.000 $10.000 $3.300 $10.000 $5.000 $1.000 $3.000 $2.000 $4.000 $10.600
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,500.000 $3,400.000 $3,375.000 $3,600.000 $3,000.000 $3,500.000 $3,200.000 $4,600.000 $3,094.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $500.000 $385.000 $100.000 $800.000 $250.000 $300.000 $500.000 $450.000 $1,439.000
WIRE FENCE (TY A)
LF 97.000 $50.000 $36.000 $40.000 $50.000 $30.000 $50.000 $25.000 $50.000 $22.000
WIRE FENCE (TY C)
LF 130.000 $50.000 $36.000 $40.000 $50.000 $25.000 $50.000 $25.000 $50.000 $28.000
WIRE FENCE (WATER GAP)
LF 60.000 $50.000 $64.000 $75.000 $200.000 $25.000 $100.000 $80.000 $80.000 $160.000
REMOVE SM RD SN SUP&AM
EA 1.000 $250.000 $110.000 $250.000 $200.000 $1.000 $150.000 $50.000 $145.000 $95.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 4.000 $40.000 $47.000 $46.440 $50.000 $35.000 $50.000 $45.000 $50.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $30.000 $42.000 $41.040 $35.000 $60.000 $50.000 $40.000 $40.000 $25.000
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 4.000 $125.000 $88.000 $86.400 $50.000 $95.000 $100.000 $500.000 $103.000 $25.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 2.000 $200.000 $330.000 $426.600 $50.000 $400.000 $300.000 $500.000 $350.000 $433.000
Totals: $1,912,208.500 $1,653,086.450 $1,750,520.200 $1,853,190.200 $1,856,686.000 $1,974,330.400 $1,976,212.200 $1,981,357.500 $2,579,857.420
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $3,000.00