POLK CR (0911-04-076)

Items: 44

County: POLK
Length: N/A
Highway: CR
District: LUFKIN
Control Number: 0911-04-076
DBE Goal: N/A
Project: BR 2016(774)
Guaranty: N/A
Time: 211 WORKING DAYS
Engineer's Estimate: $1,593,653.50
Date: 07/09/2019 (6 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,593,653.50
$1,682,521.00
Over/Under Est: 5.58% $88,867.50
Over/Under Est: 8.91% $142,044.21
Amt Left: 3.16% $53,176.71
Over/Under Est: 15.66% $249,622.00
Amt Left: 9.55% $160,754.50
Delta: -6.20% -$107,577.79
Over/Under Est: 16.35% $260,572.05
Amt Left: 10.21% $171,704.55
Delta: -0.59% -$10,950.05
$1,899,560.00
Over/Under Est: 19.2% $305,906.50
Amt Left: 12.9% $217,039.00
Delta: -2.44% -$45,334.45

Bid Items & Bid Tabulations

44 Total 0 of 44
POLK  |  CR  |  LUFKIN  |  0911-04-076  |  07/09/2019  |  $1,593,653.50  |  BR 2016(774)  |  BRIDGE REPL  |  211 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONGVIEW BRIDGE AND ROAD, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
HODGES AND SON CONSTRUCTION COMPANY, INC.
STATELINE CONSTRUCTION, LLC
PIERCE R & B LLC
PREPARING ROW
STA 15.150 $3,000.000 $5,000.000 $4,400.000 $5,000.000 $3,550.000 $3,000.000
OBLITERATING ABANDONED ROAD
SY 382.000 $15.000 $4.000 $5.000 $40.000 $115.000 $10.000
EXCAVATION (ROADWAY)
CY 711.000 $10.000 $18.000 $17.000 $20.000 $27.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 1,047.000 $5.000 $25.000 $17.000 $25.000 $19.000 $24.000
FURNISHING AND PLACING TOPSOIL (4")
SY 4,146.000 $4.000 $1.000 $4.000 $6.000 $2.250 $2.900
BROADCAST SEED (TEMP) (WARM)
SY 2,074.000 $1.000 $0.100 $0.550 $2.000 $1.000 $0.700
BROADCAST SEED (TEMP) (COOL)
SY 2,074.000 $1.000 $0.100 $0.550 $2.000 $1.000 $0.700
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 4,146.000 $1.000 $1.100 $0.550 $2.000 $2.500 $1.500
VEGETATIVE WATERING
MG 126.000 $40.000 $10.000 $0.010 $1.000 $25.000 $25.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 323.000 $3.000 $3.300 $3.150 $5.000 $4.850 $4.000
FL BS (CMP IN PLC)(TY D GR 1-2) (6")
SY 2,952.000 $28.000 $20.000 $23.500 $30.000 $32.000 $25.000
CEM STABIL BKFL
CY 204.000 $200.000 $195.000 $180.000 $250.000 $265.000 $250.000
DRILL SHAFT (24 IN)
LF 273.000 $125.000 $156.000 $132.000 $210.000 $245.000 $160.000
DRILL SHAFT (30 IN)
LF 1,095.000 $195.000 $244.000 $204.000 $200.000 $230.000 $230.000
CL C CONC (ABUT)
CY 111.000 $900.000 $965.000 $1,100.000 $1,000.000 $1,150.000 $1,200.000
REINF CONC SLAB (BOX BEAM)
SF 5,887.000 $20.000 $21.500 $21.000 $20.000 $19.000 $24.000
REINF CONC SLAB (SLAB BEAM)
SF 993.000 $15.000 $24.500 $21.000 $18.000 $19.000 $24.000
SHEAR KEY
CY 52.700 $200.000 $440.000 $370.000 $600.000 $325.000 $500.000
PRESTR CONC BOX BEAM (4B20)
LF 218.000 $210.000 $225.000 $248.000 $290.000 $225.000 $240.000
PRESTR CONC BOX BEAM (5B20)
LF 109.000 $220.000 $225.000 $248.000 $290.000 $225.000 $240.000
PRESTR CONC BOX BEAM (4B28)
LF 298.000 $215.000 $225.000 $240.000 $275.000 $225.000 $270.000
PRESTR CONC BOX BEAM (5B28)
LF 149.000 $225.000 $225.000 $240.000 $275.000 $225.000 $270.000
PRESTR CONC BOX BEAM (4B34)
LF 378.000 $220.000 $255.000 $244.000 $275.000 $225.000 $320.000
PRESTR CONC BOX BEAM (5B34)
LF 189.000 $230.000 $255.000 $244.000 $275.000 $225.000 $340.000
PRESTR CONC SLAB BEAM (4SB15)
LF 133.500 $140.000 $200.000 $263.000 $285.000 $225.000 $240.000
PRESTR CONC SLAB BEAM (5SB15)
LF 89.000 $150.000 $200.000 $263.000 $285.000 $225.000 $260.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 1,240.000 $175.000 $185.000 $165.000 $100.000 $140.000 $130.000
RAIL (TY T631LS)
LF 680.000 $65.000 $65.000 $61.000 $70.000 $95.000 $95.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $15,000.000 $10,000.000 $17,000.000 $12,000.000 $18,000.000 $14,775.000
MOBILIZATION
LS 1.000 $150,000.000 $100,000.000 $180,000.000 $170,000.000 $170,000.000 $189,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $1,500.000 $1,500.000 $1,400.000 $3,500.000 $2,250.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 176.000 $30.000 $35.000 $34.000 $40.000 $28.000 $44.000
ROCK FILTER DAMS (REMOVE)
LF 176.000 $10.000 $8.000 $8.400 $20.000 $10.000 $12.000
CONSTRUCTION PERIMETER FENCE
LF 175.000 $2.000 $3.300 $3.150 $10.000 $12.000 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,607.000 $3.000 $3.000 $2.900 $5.000 $3.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,607.000 $1.000 $1.100 $1.050 $2.000 $1.000 $1.100
MTL W-BEAM GD FEN (TIM POST)
LF 357.500 $25.000 $22.000 $21.000 $24.000 $28.000 $25.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 8.000 $1,200.000 $1,140.000 $1,100.000 $1,500.000 $1,500.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,500.000 $2,695.000 $2,600.000 $2,700.000 $2,850.000 $2,800.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $350.000 $385.000 $370.000 $800.000 $850.000 $750.450
REMOVE SM RD SN SUP&AM
EA 7.000 $80.000 $82.000 $70.000 $800.000 $500.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 13.000 $40.000 $16.500 $16.000 $30.000 $65.000 $35.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 8.000 $75.000 $50.000 $47.000 $50.000 $65.000 $65.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $50.000 $30.000 $28.000 $50.000 $65.000 $53.950
Totals: $1,593,653.500 $1,682,521.000 $1,735,697.710 $1,843,275.500 $1,854,225.550 $1,899,560.000