PREPARING ROW
|
STA
|
179.000
|
$2,000.000
|
$40,839.370
|
|
|
REMOVING STAB BASE & ASPH PAV(14")
|
SY
|
49,639.000
|
$8.000
|
$9.800
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
26.200
|
$2,000.000
|
$1,310.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
23,833.000
|
$13.000
|
$24.600
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
237,693.000
|
$11.000
|
$18.700
|
|
|
DRILL SEEDING (PERM)(WARM OR COOL)
|
SY
|
172,756.000
|
$0.250
|
$0.300
|
|
|
PROOF ROLLING
|
HR
|
50.000
|
$200.000
|
$300.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 4) (6")
|
SY
|
86,113.000
|
$15.000
|
$31.500
|
|
|
PRIME COAT (MC-30)
|
GAL
|
17,223.000
|
$5.000
|
$7.150
|
|
|
EMULS ASPH (EROSN CONT)(CSS-1H)
|
GAL
|
38,006.000
|
$5.000
|
$4.950
|
|
|
FOG SEAL (CSS-1H)
|
GAL
|
16,960.000
|
$5.000
|
$6.160
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
80,257.000
|
$5.000
|
$6.600
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
1,820.000
|
$150.000
|
$236.500
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
1,000.000
|
$50.000
|
$126.500
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
|
SY
|
1,000.000
|
$30.000
|
$99.000
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
33,756.000
|
$5.000
|
$4.500
|
|
|
CEM STABIL BKFL
|
CY
|
984.000
|
$250.000
|
$222.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
2,545.000
|
$350.000
|
$422.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
1,800.000
|
$450.000
|
$475.000
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
7.000
|
$150.000
|
$98.000
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
36.000
|
$200.000
|
$242.000
|
|
|
DRILL SHAFT (HIGH MAST POLE) (60 IN)
|
LF
|
120.000
|
$1,000.000
|
$1,160.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
80.000
|
$300.000
|
$423.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
127.000
|
$2,000.000
|
$2,340.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
427.200
|
$2,400.000
|
$2,680.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
559.700
|
$2,100.000
|
$1,690.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
407.000
|
$800.000
|
$865.000
|
|
|
CL C CONC (VEH DEFL WALL)
|
CY
|
140.600
|
$2,000.000
|
$2,600.000
|
|
|
REINF CONC SLAB
|
SF
|
78,427.000
|
$35.000
|
$54.650
|
|
|
APPROACH SLAB
|
CY
|
175.500
|
$850.000
|
$1,180.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
30,623.000
|
$55.000
|
$155.300
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
10,496.280
|
$280.000
|
$440.000
|
|
|
SILICONE RESIN PAINT FINISH
|
SF
|
11,520.000
|
$20.000
|
$10.250
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
2,443.000
|
$550.000
|
$670.000
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
375.000
|
$750.000
|
$775.000
|
|
|
CLEANING AND SEALING JOINTS
|
LF
|
15,930.000
|
$10.000
|
$14.500
|
|
|
RAIL (TY SSTR)
|
LF
|
5,996.800
|
$100.000
|
$105.000
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
1,925.000
|
$120.000
|
$105.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
526.000
|
$250.000
|
$227.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,024.000
|
$200.000
|
$228.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
296.000
|
$250.000
|
$264.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
216.000
|
$300.000
|
$312.000
|
|
|
INLET (COMPL) (DROP) (SPL)
|
EA
|
6.000
|
$5,000.000
|
$14,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
3.000
|
$3,000.000
|
$5,750.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
11.000
|
$3,000.000
|
$6,470.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$3,000.000
|
$6,470.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$4,000.000
|
$7,080.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
6.000
|
$5,000.000
|
$10,940.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
13.000
|
$2,500.000
|
$11,490.000
|
|
|
REMOV STR (PIPE)
|
EA
|
4.000
|
$2,000.000
|
$8,980.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$3,511,000.000
|
$6,900,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
44.000
|
$25,000.000
|
$75,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
1,560.000
|
$35.000
|
$66.750
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
1,560.000
|
$10.000
|
$17.100
|
|
|
SANDBAGS FOR EROSION CONTROL
|
EA
|
378.000
|
$10.000
|
$28.800
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
4,800.000
|
$5.000
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,400.000
|
$1.000
|
$1.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
9,180.000
|
$10.000
|
$11.300
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
4,590.000
|
$5.000
|
$1.500
|
|
|
CONSTRUCTING DETOURS
|
SY
|
25,215.000
|
$60.000
|
$148.500
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
3,000.000
|
$100.000
|
$114.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
7,060.000
|
$20.000
|
$10.200
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
3,000.000
|
$30.000
|
$12.300
|
|
|
PCTB MOVE&RESET(F-SHAPE OR SNGL SLPTY1
|
LF
|
3,240.000
|
$30.000
|
$15.900
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (54 )
|
LF
|
5,044.000
|
$110.000
|
$121.000
|
|
|
PERM CTB (SGL SLOPE) (TY 3) (54 )
|
LF
|
125.000
|
$200.000
|
$331.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
526.000
|
$100.000
|
$231.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
103,936.000
|
$0.500
|
$0.100
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
7.000
|
$2,000.000
|
$3,020.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$1,400.000
|
$1,810.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
4.000
|
$40,000.000
|
$42,330.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$10,000.000
|
$9,070.000
|
|
|
IN RD IL (TY SA) 50T-12 (400W EQ) LED
|
EA
|
8.000
|
$4,000.000
|
$7,470.000
|
|
|
HI MST IL POLE (150 FT)(100 MPH)
|
EA
|
3.000
|
$60,000.000
|
$89,100.000
|
|
|
TEMP RD IL (RD IL ASM)
|
EA
|
8.000
|
$10,000.000
|
$18,530.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
10,414.000
|
$15.000
|
$28.700
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
276.000
|
$30.000
|
$35.000
|
|
|
ELEC CONDR (NO.4) BARE
|
LF
|
10,786.000
|
$3.000
|
$4.000
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
27,850.000
|
$3.500
|
$4.100
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
14.000
|
$1,500.000
|
$1,610.000
|
|
|
ELC SRV TY A 240/480 100(NS)SS(E)SP(U)
|
EA
|
2.000
|
$8,000.000
|
$8,340.000
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
210.000
|
$50.000
|
$39.250
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
8.000
|
$850.000
|
$1,390.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
9.000
|
$900.000
|
$1,510.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
47.000
|
$900.000
|
$1,380.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
|
EA
|
1.000
|
$1,200.000
|
$1,807.480
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
3.000
|
$1,000.000
|
$2,270.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
46.000
|
$120.000
|
$121.000
|
|
|
IN SRSS & AM (RAIL)(130 MPH)(P MOUNT)
|
EA
|
2.000
|
$5,000.000
|
$10,880.000
|
|
|
IN SRSS & AM (RAIL)(130 MPH)(T MOUNT)
|
EA
|
8.000
|
$5,000.000
|
$10,880.000
|
|
|
IN SRSS & AM (RAIL)(130 MPH)(U MOUNT)
|
EA
|
1.000
|
$5,000.000
|
$10,280.000
|
|
|
IN SRSS & AM (RAIL)(130 MPH)(U-BM MNT)
|
EA
|
3.000
|
$5,000.000
|
$10,280.000
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
2,186.000
|
$10.000
|
$10.300
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
39.000
|
$60.000
|
$24.200
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
13.000
|
$60.000
|
$24.200
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
22.000
|
$60.000
|
$18.100
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
|
EA
|
38.000
|
$90.000
|
$24.200
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BR)
|
EA
|
34.000
|
$90.000
|
$24.200
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
23.000
|
$90.000
|
$181.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
29,150.000
|
$0.300
|
$0.450
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
147,610.000
|
$0.300
|
$0.350
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
14,050.000
|
$0.600
|
$0.750
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
203,000.000
|
$0.300
|
$0.350
|
|
|
WK ZN PAV MRK REMOV (W)(UTURN ARROW)
|
EA
|
2.000
|
$100.000
|
$1,140.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
3,732.000
|
$2.000
|
$2.300
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,368.000
|
$2.000
|
$1.850
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
155.000
|
$0.600
|
$0.950
|
|
REFL PAV MRK TY I (W)6"(LNDP)(100MIL)
|
LF
|
672.000
|
$0.600
|
$0.950
|
|
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
|
LF
|
1,329.000
|
$0.750
|
$1.800
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
4,980.000
|
$0.750
|
$1.800
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
13,065.000
|
$0.500
|
$0.950
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
61,500.000
|
$0.500
|
$0.950
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
61,973.000
|
$0.500
|
$0.950
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)
|
LF
|
70.000
|
$5.000
|
$10.900
|
|
PREFAB PAV MRK TY B (W)(6")(SLD)
|
LF
|
1,209.000
|
$5.000
|
$10.900
|
|
PREFAB PAV MRK TY B (W)(8")(SLD)
|
LF
|
244.000
|
$8.000
|
$12.100
|
|
PREFAB PAV MRK TY B (W)(24")(SLD)
|
LF
|
550.000
|
$20.000
|
$42.250
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
2.000
|
$400.000
|
$907.000
|
|
PREFAB PAV MRK TY B (Y)(6")(SLD)
|
LF
|
2,928.000
|
$5.000
|
$10.900
|
|
PREFAB PAV MRK TY C (W) (12") (SLD)
|
LF
|
388.000
|
$10.000
|
$9.650
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
1,345.000
|
$20.000
|
$14.500
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
24.000
|
$400.000
|
$302.000
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
2.000
|
$750.000
|
$665.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
2.000
|
$450.000
|
$423.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
1.000
|
$500.000
|
$1,030.000
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
103.000
|
$50.000
|
$66.500
|
|
REFL PAV MRKR TY I-C
|
EA
|
702.000
|
$5.000
|
$6.050
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
235.000
|
$5.000
|
$6.050
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
319.000
|
$5.000
|
$6.050
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
121,575.000
|
$0.750
|
$1.050
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
10,500.000
|
$1.000
|
$1.800
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
2.000
|
$20.000
|
$121.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
4,207.000
|
$0.300
|
$1.200
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
244.000
|
$0.600
|
$2.400
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
550.000
|
$2.000
|
$6.050
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
2.000
|
$15.000
|
$121.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
2.000
|
$3,000.000
|
$6,860.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
8.000
|
$5,000.000
|
$7,850.000
|
|
|
LITTER REMOVAL
|
CYC
|
8.000
|
$3,000.000
|
$3,720.000
|
|
|
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
|
SY
|
57,923.000
|
$6.500
|
$7.700
|
|
|
ASPH FOR REINF FAB (PG76-28)
|
GAL
|
8,109.000
|
$5.000
|
$10.450
|
|
|
D-GR HMA TY-B PG70-28
|
TON
|
31,038.000
|
$130.000
|
$238.500
|
|
|
TACK COAT
|
GAL
|
11,901.000
|
$6.000
|
$7.150
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-28
|
TON
|
8,747.000
|
$170.000
|
$286.000
|
|
|
TACK COAT
|
GAL
|
2,897.000
|
$6.000
|
$7.150
|
|
|
SMA-D SAC-A PG76-28 (NO TRAFFIC)
|
TON
|
1,245.000
|
$170.000
|
$286.000
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
6.000
|
$1,000.000
|
$727.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
2,640.000
|
$100.000
|
$25.900
|
|
|
LONG CHANNEL MOUNT CURB SYS (INSTALL)
|
LF
|
80.000
|
$110.000
|
$181.000
|
|
|
LED HI MST IL ASM (6 FIXT)(SYM)(TY S)
|
EA
|
3.000
|
$35,000.000
|
$60,300.000
|
|
|
TMA (STATIONARY)
|
DAY
|
1,442.000
|
$150.000
|
$126.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
126.000
|
$500.000
|
$136.000
|
|
|
TEMP SPEED MONITOR SYS
|
EA
|
2.000
|
$15,000.000
|
$21,890.000
|
|
Totals: |
$38,625,086.600
|
$69,925,101.460
|