Bid Cobra

PANOLA US 79 (0247-01-058)

Items: 59

County: PANOLA
Length: 13.9860 MILES
Highway: US 79
District: ATLANTA
Control Number: 0247-01-058
DBE Goal: 4.0%
Project: STP 2025(566)HES
Guaranty: $100,000.00
Time: 131 WORKING DAYS
Engineer's Estimate: $9,792,223.51
Date: 02/06/2025 (1 year ago)
Contract Number: 2253023
Type: RESURFACE ROADWAY
Project ID: A00184154
Contract Type: Federal
Project Description: INSTALL CONTINUOUS TURN LANE, MILLED EDGELINE RUMBLE STRIPS
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$9,792,223.51
$8,013,112.06
Over/Under Est: -18.17% -$1,779,111.45
Over/Under Est: -6.49% -$635,953.57
Amt Left: 14.27% $1,143,157.88
Over/Under Est: -0.99% -$96,776.34
Amt Left: 20.99% $1,682,335.11
Delta: -5.89% -$539,177.23
Over/Under Est: 3.43% $335,627.49
Amt Left: 26.39% $2,114,738.94
Delta: -4.46% -$432,403.83
Subcontractor Percentage Amount
DREWERY CONSTRUCTION COMPANY, INCORPORATED 7.90% $635,675.12
DREWERY BROS. TREE SERVICE, INC. 7.39% $594,637.87
STRIPING TECHNOLOGY, L.P. 6.03% $485,205.19
R & G CONSTRUCTION, LLC 4.27% $343,586.43
KENT TREE SERVICE LLC 3.70% $297,721.26
SOUTHWEST ENVIRONMENT SERVICES LLC 1.72% $138,400.15
WMS R AND B, L.L.C. 0.87% $70,004.73
PANOLA SIGN & BARRICADE, INC. 0.15% $12,069.78
CAP RIVER LLC 0.13% $10,460.48
AWP SAFETY 0.05% $4,023.26
Total: 32.21% $2,591,784.27

Bid Items & Bid Tabulations

59 Total 0 of 59
PANOLA  |  US 79  |  ATLANTA  |  0247-01-058  |  02/06/2025  |  $9,792,223.51  |  STP 2025(566)HES  |  RESURF ROADWAY  |  131 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
LONGVIEW BRIDGE AND ROAD, LTD.
EAST TEXAS BRIDGE, INC.
GREY SKY CONSTRUCTION LLC
PREPARING ROW
STA 417.000 $3,500.000 $1,600.000 $3,000.000 $4,000.000 $2,398.000
BLADING
LF 5,625.000 $1.800 $7.650 $10.000 $24.000 $20.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 35,565.000 $1.000 $0.170 $0.190 $0.200 $0.500
BROADCAST SEED (TEMP_WARM_COOL)
SY 35,565.000 $0.400 $0.120 $0.150 $0.200 $0.500
VEGETATIVE WATERING
TGL 6,769.000 $21.500 $1.000 $24.000 $5.000 $25.000
SP MIXES SP-D SAC-A PG76-22
TON 25,975.000 $165.000 $172.500 $170.000 $185.000 $200.000
TACK COAT
GAL 37,781.000 $5.500 $0.010 $4.750 $8.000 $3.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,800.000 $72.000 $87.500 $100.000 $85.000 $75.000
PLANE & TEXT ASPH CONC PAV(1")
SY 308,088.000 $4.000 $2.800 $2.750 $2.450 $3.000
PLANE ASPH CONC PAV (0" TO 1.5")
SY 6,750.000 $9.400 $2.800 $5.000 $3.750 $6.000
CUT & RESTORE ASPH PAVING
SY 56.000 $140.000 $110.000 $200.000 $200.000 $250.000
CL C CONC (COLLAR)
EA 20.000 $810.000 $900.000 $1,750.000 $1,200.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 320.000 $67.000 $54.000 $70.000 $65.000 $85.000
RC PIPE (CL III)(42 IN)
LF 24.000 $220.000 $249.000 $250.000 $225.000 $450.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 202.000 $1,030.000 $837.000 $1,150.000 $900.000 $1,250.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 14.000 $1,450.000 $1,160.000 $1,600.000 $1,300.000 $2,500.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 5.000 $3,100.000 $2,110.000 $2,500.000 $2,500.000 $3,500.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 2.000 $6,200.000 $9,110.000 $8,000.000 $12,000.000 $6,500.000
REMOV STR (SET)
EA 1.000 $360.000 $1,000.000 $1,000.000 $1,000.000 $500.000
REMOV STR (PIPE)
LF 284.000 $16.000 $12.000 $25.000 $20.000 $50.000
MOBILIZATION
LS 1.000 $901,491.850 $704,500.000 $750,000.000 $400,000.000 $900,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $15,000.000 $10,000.000 $8,000.000 $20,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $20,700.000 $20,000.000 $20,000.000 $20,000.000 $16,500.000
TMA (STATIONARY)
DAY 90.000 $195.000 $300.000 $275.000 $300.000 $250.000
TMA (MOBILE OPERATION)
DAY 45.000 $300.000 $0.010 $350.000 $300.000 $550.000
ALUMINUM SIGNS (TY A)
SF 1,262.490 $55.000 $10.000 $11.000 $55.000 $50.000
ALUMINUM SIGNS (TY G)
SF 52.000 $39.000 $16.000 $18.000 $130.000 $50.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 19.000 $770.000 $671.000 $750.000 $800.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $860.000 $920.000 $1,050.000 $900.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,100.000 $923.000 $1,050.000 $1,100.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 2.000 $950.000 $842.000 $950.000 $900.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $1,100.000 $1,093.000 $1,300.000 $1,000.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 7.000 $1,130.000 $1,046.000 $1,200.000 $1,300.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SB(P-BM)
EA 1.000 $1,260.000 $1,050.000 $1,200.000 $1,100.000 $1,100.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 99.000 $550.000 $494.000 $550.000 $600.000 $1,100.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 23.000 $750.000 $514.000 $575.000 $700.000 $1,100.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 21.000 $410.000 $243.000 $270.000 $300.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 7.000 $130.000 $110.000 $125.000 $130.000 $500.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 18,148.000 $0.400 $0.250 $0.300 $0.280 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 119,537.000 $0.400 $0.200 $0.250 $0.220 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 119,537.000 $0.350 $0.200 $0.250 $0.220 $1.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 333.000 $4.400 $4.500 $5.000 $5.000 $6.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 436.000 $4.310 $3.700 $4.250 $4.000 $6.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 436.000 $4.600 $3.700 $4.250 $4.000 $6.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 29,880.000 $1.750 $1.000 $1.200 $2.500 $0.750
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 17,160.000 $2.700 $1.000 $1.200 $2.500 $0.750
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 12,720.000 $2.700 $1.000 $1.200 $2.500 $0.750
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 121,710.000 $0.750 $0.850 $1.000 $0.950 $0.750
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 32,036.000 $0.750 $0.900 $1.000 $1.000 $0.750
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 121,830.000 $0.750 $0.850 $1.000 $0.950 $0.750
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 40,610.000 $0.750 $0.900 $1.000 $1.000 $0.750
PAVEMENT SLER 6"
LF 6,516.000 $0.800 $0.500 $0.600 $0.550 $1.000
PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE)
LF 28,638.000 $3.750 $3.850 $4.500 $4.000 $1.000
PREFAB PM TY C (W)(ARROW)
EA 40.000 $230.000 $212.000 $240.000 $250.000 $250.000
PREFAB PM TY C (W)(LN REDUCT ARROW)
EA 22.000 $260.000 $285.000 $320.000 $300.000 $250.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $280.000 $262.000 $290.000 $300.000 $250.000
REFL PAV MRKR TY I-C
EA 771.000 $5.600 $4.500 $5.000 $5.000 $6.000
REFL PAV MRKR TY II-A-A
EA 3,608.000 $4.900 $4.500 $5.000 $5.000 $6.000
ELIM EXT PM & MRKS (6")
LF 6,516.000 $0.700 $1.000 $1.200 $1.100 $1.500
Totals: $9,792,223.510 $8,013,112.060 $9,156,269.940 $9,695,447.170 $10,127,851.000