NAVARRO SH 22 (0121-05-050)
Items: 42
County: NAVARRO
Length: N/A
Highway: SH 22
District: DALLAS
Control Number: 0121-05-050
DBE Goal: N/A
Project: STP 2017(921)
Guaranty: N/A
Time: 56 WORKING DAYS
Engineer's Estimate: $2,427,471.70
Date: 04/05/2017 (9 years ago)
Contract Number: N/A
Type: FOR THE CONSTRUCTION OF MILL & INLAY HMAC, FDRCP
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,427,471.70 | |||
| $1,989,594.44 |
-18.04%
-$437,877.26
|
|||
| $2,023,615.79 |
-16.64%
-$403,855.91
|
1.71%
$34,021.35
|
||
| $2,187,992.19 |
-9.87%
-$239,479.51
|
9.97%
$198,397.75
|
-8.12%
-$164,376.40
|
|
| $2,335,628.00 |
-3.78%
-$91,843.70
|
17.39%
$346,033.56
|
-6.75%
-$147,635.81
|
|
| $3,192,411.50 |
31.51%
$764,939.80
|
60.46%
$1,202,817.06
|
-36.68%
-$856,783.50
|
E
Engineer's Estimate
$2,427,471.70
1
Awarded
$1,989,594.44
Over/Under Est:
-18.04%
-$437,877.26
$2,023,615.79
Over/Under Est:
-16.64%
-$403,855.91
Amt Left:
1.71%
$34,021.35
$2,187,992.19
Over/Under Est:
-9.87%
-$239,479.51
Amt Left:
9.97%
$198,397.75
Delta:
-8.12%
-$164,376.40
$2,335,628.00
Over/Under Est:
-3.78%
-$91,843.70
Amt Left:
17.39%
$346,033.56
Delta:
-6.75%
-$147,635.81
$3,192,411.50
Over/Under Est:
31.51%
$764,939.80
Amt Left:
60.46%
$1,202,817.06
Delta:
-36.68%
-$856,783.50
Bid Items & Bid Tabulations
42
Total
0 of 42