MILLS FM 45 (0480-07-014)

Items: 175

County: MILLS
Length: N/A
Highway: FM 45
District: BROWNWOOD
Control Number: 0480-07-014
DBE Goal: 400.0%
Project: BR 2B24(034)
Guaranty: N/A
Time: 510 WORKING DAYS
Engineer's Estimate: $28,367,743.87
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: RECONSTRUCT EXISTING ROADWAY
Mail/Deliver Bids To: N/A
NATNAEL ASFAW
JASON SCANTLING
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$28,367,743.87
$32,511,818.26
Over/Under Est: 14.61% $4,144,074.39
$36,946,649.58
Over/Under Est: 30.24% $8,578,905.71
Amt Left: 13.64% $4,434,831.32
Over/Under Est: 30.74% $8,719,685.36
Amt Left: 14.07% $4,575,610.97
Delta: -0.38% -$140,779.65
Over/Under Est: 41.16% $11,675,503.07
Amt Left: 23.17% $7,531,428.68
Delta: -7.97% -$2,955,817.71
Subcontractor Percentage Amount
DELGADO'S CONTRACTORS, LLC 24.50% $7,864,193.25
ERFURT BLASTING COMPANY, INC. 1.68% $539,258.97
D. I. J. CONSTRUCTION, INC. 1.63% $523,209.59
A K FUQUAY CONSTRUCTION 1.40% $449,382.47
RPV CONSTRUCTION, LLC 1.27% $407,654.10
PRATER DIRT WORK LLC 0.84% $269,629.48
TORO BRAVO CONSTRUCTION, LLC 0.33% $105,925.87
DK CONTRACTING, LLC 0.26% $83,456.74
KELLER TRUCKING, INC. 0.25% $80,246.87
4E TREE WORX LLC 0.08% $25,679.00
PROFESSIONAL TRAFFIC CONTROL LLC 0.04% $12,839.50
PRIMATE CONSTRUCTION, LP 0.00% $0.00
ROYAL REBAR INC 0.00% $0.00
AARON CONCRETE CONTRACTORS, LLC 0.00% $0.00
Total: 32.28% $10,361,475.84

Bid Items & Bid Tabulations

175 Total 0 of 175
MILLS  |  FM 45  |  BROWNWOOD  |  0480-07-014  |  06/05/2024  |  $28,367,743.87  |  BR 2B24(034)  |  RECON EXIST ROADWAY  |  510 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN KELLER COMPANY
FNF CONSTRUCTION, INC.
BIG CREEK CONSTRUCTION, LTD.
JAMES CONSTRUCTION GROUP, LLC
PREPARING ROW
STA 633.000 $1,700.000 $1,202.560 $800.000 $5,000.000 $6,300.000
REMOVING CONC (CURB)
LF 150.000 $200.000 $28.600 $3.500 $14.000 $3.860
EXCAVATION (ROADWAY)
CY 233,761.000 $10.000 $9.630 $14.500 $15.000 $15.000
EXCAVATION (CHANNEL)
CY 799.000 $30.000 $16.380 $30.000 $50.000 $18.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 144,533.000 $4.000 $3.620 $5.750 $10.000 $17.000
FURNISHING AND PLACING TOPSOIL (12")
SY 13,316.000 $10.000 $6.310 $2.500 $5.000 $0.780
BROADCAST SEED (TEMP) (WARM)
SY 82,960.000 $0.300 $0.240 $0.200 $0.200 $0.160
BROADCAST SEED (TEMP) (COOL)
SY 82,960.000 $0.300 $0.240 $0.200 $0.210 $0.160
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
SY 82,960.000 $1.000 $0.830 $0.450 $0.600 $0.400
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 74,111.000 $0.300 $0.340 $0.200 $0.220 $0.180
DRILL SEEDING (TEMP) (WARM)
SY 82,960.000 $1.000 $0.290 $0.150 $0.210 $0.140
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 74,111.000 $0.300 $0.240 $0.180 $0.210 $0.160
VEGETATIVE WATERING
MG 6,713.000 $18.000 $31.530 $33.000 $25.000 $38.080
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 13,316.000 $5.000 $2.000 $1.300 $2.000 $1.250
SOIL RETENTION BLANKETS (CL 2) (TY H)
SY 5,120.000 $5.000 $7.480 $2.100 $5.000 $2.000
PROOF ROLLING
HR 7.000 $150.000 $178.190 $150.000 $200.000 $124.320
FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS)
CY 28,874.000 $50.000 $72.450 $56.000 $75.000 $59.690
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 26,426.000 $50.000 $72.450 $56.000 $75.000 $59.590
CM TRT(PT MX)(CL M)(TY A)(GR 4)(FN POS)
CY 119.500 $300.000 $315.790 $200.000 $250.000 $116.730
PRIME COAT (MC-30)
GAL 46,124.000 $6.950 $6.890 $5.500 $5.000 $6.250
ASPH (AC-20XP)
GAL 57,656.000 $5.350 $5.430 $5.000 $5.000 $5.000
ASPH (CRS-2)
GAL 57,656.000 $5.000 $4.550 $3.750 $4.000 $5.000
ASPH (AC-20-5TR)
TON 117.000 $1,000.000 $1,358.990 $1,400.000 $1,200.000 $1,200.000
AGGR(TY-PB GR-3 SAC-B)
CY 1,810.000 $135.000 $206.050 $160.000 $160.000 $350.000
AGGR(TY-PB GR-4 SAC-B)
CY 2,181.000 $140.000 $161.320 $165.000 $160.000 $400.000
HMCL ACP TY-F AC-1.5
TON 59.300 $250.000 $145.680 $550.000 $350.000 $100.000
CEM STABIL BKFL
CY 420.000 $300.000 $310.910 $310.000 $250.000 $235.870
FLOWABLE BACKFILL
CY 549.000 $300.000 $300.640 $430.000 $250.000 $214.480
TRENCH EXCAVATION PROTECTION
LF 486.000 $25.000 $23.070 $38.000 $10.000 $46.350
DRILL SHAFT (18 IN)
LF 412.000 $200.000 $186.490 $310.000 $215.000 $189.150
DRILL SHAFT (36 IN)
LF 2,128.000 $275.000 $310.910 $475.000 $410.000 $302.560
DRILL SHAFT (42 IN)
LF 126.000 $400.000 $538.710 $565.000 $640.000 $369.350
DRILL SHAFT (54 IN)
LF 320.000 $650.000 $829.080 $815.000 $1,000.000 $827.640
CL B CONC (FLUME)
CY 136.000 $550.000 $758.690 $3,000.000 $1,000.000 $1,346.180
CL C CONC (ABUT)
CY 67.800 $1,500.000 $1,867.390 $2,400.000 $1,400.000 $963.820
CL C CONC (ABUT)(HPC)
CY 66.300 $1,650.000 $1,867.390 $2,700.000 $1,400.000 $979.700
CL C CONC (CAP)
CY 19.900 $1,600.000 $1,867.390 $2,700.000 $1,900.000 $1,867.780
CL C CONC (CAP)(HPC)
CY 177.100 $1,700.000 $1,867.390 $4,300.000 $1,900.000 $1,660.800
CL C CONC (COLUMN)
CY 8.400 $1,600.000 $2,072.710 $2,700.000 $2,200.000 $3,421.490
CL C CONC (COLUMN)(HPC)
CY 310.600 $1,700.000 $2,278.020 $1,700.000 $1,500.000 $1,579.100
CL C CONC (CULV)
CY 385.500 $2,000.000 $1,280.780 $3,800.000 $2,500.000 $2,377.610
CL C CONC (TIE BEAM)
CY 36.000 $1,700.000 $2,072.710 $5,200.000 $2,800.000 $2,822.730
REINF CONC SLAB
SF 11,587.500 $35.000 $30.210 $45.000 $25.000 $23.530
REINF CONC SLAB (HPC)
SF 40,480.000 $28.000 $36.270 $39.000 $35.000 $32.000
APPROACH SLAB
CY 65.200 $1,000.000 $1,662.080 $1,200.000 $1,000.000 $746.210
APPROACH SLAB (HPC)
CY 70.600 $625.000 $1,662.080 $1,200.000 $1,000.000 $729.010
PRESTR CONC GIRDER (TX46)
LF 4,775.000 $150.000 $289.890 $310.000 $230.000 $259.000
PRESTR CONC GIRDER (TX54)
LF 906.000 $275.000 $289.890 $400.000 $270.000 $259.000
RIPRAP (CONC)(5 IN)
CY 1,097.900 $500.000 $778.240 $850.000 $700.000 $719.860
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 174.000 $525.000 $750.870 $1,270.000 $700.000 $500.560
RIPRAP (STONE PROTECTION)(12 IN)
CY 238.000 $250.000 $165.470 $210.000 $155.000 $287.980
RIPRAP (STONE PROTECTION)(18 IN)
CY 330.000 $300.000 $164.010 $201.000 $160.000 $285.490
RIPRAP (STONE PROTECTION)(30 IN)
CY 3,340.000 $185.000 $162.300 $270.000 $170.000 $285.490
RIPRAP (MOW STRIP)(4 IN)
CY 256.000 $700.000 $770.420 $950.000 $700.000 $661.570
RAIL (TY SSTR)
LF 484.000 $100.000 $207.270 $175.000 $100.000 $97.780
RAIL (TY SSTR)(HPC)
LF 1,824.000 $100.000 $207.270 $185.000 $100.000 $101.460
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 272.000 $175.000 $259.090 $400.000 $235.000 $203.590
WATERPROOFING (TY 10)
SY 64.200 $15.000 $11.340 $110.000 $100.000 $42.740
CMP AR (GAL STL DES 2)
LF 620.000 $85.000 $117.320 $165.000 $72.000 $225.000
CONC BOX CULV (3 FT X 2 FT)
LF 448.100 $350.000 $354.900 $550.000 $320.000 $600.000
CONC BOX CULV (3 FT X 3 FT)
LF 117.300 $450.000 $391.570 $700.000 $365.000 $650.000
CONC BOX CULV (4 FT X 3 FT)
LF 153.350 $800.000 $433.610 $725.000 $420.000 $700.000
CONC BOX CULV (4 FT X 4 FT)
LF 112.200 $450.000 $462.940 $900.000 $450.000 $750.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 112.200 $800.000 $613.990 $800.000 $555.000 $1,500.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 25.000 $700.000 $835.930 $1,000.000 $700.000 $1,500.000
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 24.400 $700.000 $1,124.350 $1,040.000 $750.000 $1,500.000
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 1.000 $9,000.000 $9,033.890 $9,700.000 $8,300.000 $13,952.690
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 5.000 $18,000.000 $10,119.120 $10,250.000 $10,600.000 $14,441.810
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 3.000 $8,500.000 $9,874.700 $10,000.000 $11,500.000 $14,678.300
SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C)
EA 10.000 $18,000.000 $11,634.540 $13,000.000 $12,200.000 $14,977.390
SET (TY I)(S=3 FT)(HW= 5 FT)(3:1)(C)
EA 4.000 $19,500.000 $14,978.250 $14,000.000 $12,900.000 $15,226.880
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 2.000 $19,500.000 $10,128.900 $10,700.000 $11,100.000 $14,672.030
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
EA 2.000 $9,000.000 $16,620.780 $16,500.000 $15,300.000 $20,137.600
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 1.000 $8,000.000 $18,233.980 $15,000.000 $11,900.000 $19,068.840
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $8,000.000 $18,986.800 $16,500.000 $13,700.000 $19,870.610
SET (TY I)(S= 4 FT)(HW= 6 FT)(3:1) (C)
EA 2.000 $9,000.000 $18,849.920 $15,000.000 $13,500.000 $24,169.990
SET (TY I)(S= 5 FT)(HW= 7 FT)(3:1) (C)
EA 3.000 $25,000.000 $27,189.640 $22,800.000 $23,300.000 $23,873.410
SET (TY I)(S= 5 FT)(HW= 7 FT)(4:1) (C)
EA 1.000 $26,000.000 $38,560.210 $30,000.000 $33,500.000 $25,155.890
SET (TY II) (DES 2) (CMP) (6: 1) (C)
EA 50.000 $2,700.000 $2,092.260 $1,100.000 $1,900.000 $952.510
REMOV STR (BOX CULVERT)
EA 3.000 $14,000.000 $11,145.700 $30,000.000 $8,500.000 $1,683.160
REMOV STR (PIPE)
LF 292.000 $65.000 $42.580 $40.000 $21.000 $28.630
REMOV STR (BOX CULVERT)
LF 26.900 $150.000 $525.020 $450.000 $300.000 $178.920
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $45,000.000 $51,798.170 $100,000.000 $72,000.000 $250,000.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $500,000.000 $370,878.000 $500,000.000 $487,000.000 $500,000.000
REMOV STR (PIPE)
EA 7.000 $1,400.000 $4,223.630 $1,500.000 $825.000 $1,381.900
REMOV STR (CATTLE GUARD)
EA 2.000 $500.000 $4,438.730 $2,700.000 $1,500.000 $1,289.680
REMOV STR (DRAINAGE FLUME)
EA 1.000 $15,000.000 $8,290.840 $20,000.000 $2,500.000 $5,829.710
MOBILIZATION
LS 1.000 $1,935,500.000 $2,700,000.000 $3,650,000.000 $3,700,000.000 $3,979,776.900
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 30.000 $10,000.000 $31,823.900 $29,450.000 $7,900.000 $25,864.880
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,665.000 $30.000 $44.920 $40.000 $50.000 $37.000
ROCK FILTER DAMS (REMOVE)
LF 1,665.000 $10.000 $16.720 $13.000 $21.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 405.000 $35.000 $28.700 $37.000 $50.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 405.000 $15.000 $13.350 $13.000 $15.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 18,474.000 $4.500 $4.160 $4.000 $4.000 $3.750
TEMP SEDMT CONT FENCE (REMOVE)
LF 18,474.000 $1.500 $0.780 $0.750 $1.600 $0.600
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 240.000 $4.000 $5.720 $4.250 $8.000 $4.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,700.000 $5.000 $5.960 $5.250 $12.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,940.000 $1.700 $1.030 $1.100 $3.000 $1.000
CONSTRUCTING DETOURS
SY 1,060.000 $31.000 $36.170 $60.000 $50.000 $113.690
CONSTRUCTING DETOURS (TY 1)
SY 63,771.000 $35.000 $35.690 $41.000 $50.000 $36.920
CONSTRUCTING DETOURS (TY 2)
SY 30,037.000 $3.000 $3.030 $8.000 $7.000 $9.110
ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG)
DAY 84.000 $300.000 $256.160 $300.000 $300.000 $180.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,740.000 $35.000 $42.870 $60.000 $85.000 $63.630
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 540.000 $35.000 $42.920 $18.000 $20.000 $16.210
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 2,040.000 $25.000 $28.940 $18.000 $9.500 $4.950
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,740.000 $27.000 $53.870 $17.000 $17.000 $7.590
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 540.000 $27.000 $45.510 $18.000 $17.000 $16.210
CONC CURB (MOD) (TYPE I)
LF 348.000 $75.000 $71.180 $45.000 $40.000 $41.090
INTERSECTIONS (ACP)
SY 891.000 $85.000 $68.150 $45.000 $60.000 $52.860
DRIVEWAYS (SURF TREAT)
SY 4,052.000 $65.000 $32.260 $31.000 $35.000 $59.860
RUMBLE STRIPS (SHOULDER)
LF 66,786.000 $0.300 $0.050 $0.150 $0.200 $0.120
RUMBLE STRIPS (CENTERLINE)
LF 37,057.000 $0.300 $0.100 $0.150 $0.200 $0.120
MTL W-BEAM GD FEN (STEEL POST)
LF 3,030.000 $38.000 $30.550 $33.000 $35.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $3,600.000 $3,637.020 $3,000.000 $3,000.000 $2,200.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 125.000 $90.000 $84.960 $165.000 $200.000 $90.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 4.000 $1,227.000 $1,065.680 $1,600.000 $2,000.000 $1,150.000
REMOVE METAL BEAM GUARD FENCE
LF 4,820.000 $5.000 $1.560 $6.500 $7.000 $2.500
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 10.000 $300.000 $207.270 $390.000 $500.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $4,000.000 $2,884.190 $3,800.000 $4,000.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $250.000 $207.270 $525.000 $700.000 $250.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $2,500.000 $1,984.720 $1,500.000 $2,000.000 $1,145.000
CRASH CUSH ATTEN (STKPL)
EA 4.000 $1,500.000 $2,141.150 $2,300.000 $2,500.000 $1,145.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $11,000.000 $2,620.220 $1,300.000 $1,500.000 $765.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $1,500.000 $11,311.910 $10,000.000 $12,000.000 $7,310.000
WIRE FENCE (TY A)
LF 2,094.000 $25.000 $12.370 $25.000 $10.000 $22.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 9.000 $450.000 $236.110 $400.000 $350.000 $228.000
ALUMINUM SIGNS (TY A)
SF 59.000 $45.000 $32.120 $32.000 $50.000 $24.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 19.000 $850.000 $697.100 $700.000 $1,000.000 $675.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $1,000.000 $844.730 $850.000 $1,100.000 $775.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 5.000 $1,000.000 $1,095.020 $1,100.000 $1,150.000 $895.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 5.000 $1,050.000 $977.690 $1,000.000 $1,200.000 $995.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 1.000 $850.000 $1,231.890 $1,250.000 $1,250.000 $1,205.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 8.000 $1,000.000 $583.680 $600.000 $800.000 $545.000
IN SM RD SN SUP&AM TYTWT(1)UA(T)
EA 4.000 $1,000.000 $701.010 $700.000 $900.000 $635.000
IN SM RD SN SUP&AM TYTWT(1)UB(T)
EA 1.000 $1,000.000 $689.280 $700.000 $1,000.000 $665.000
REMOVE SM RD SN SUP&AM
EA 36.000 $150.000 $157.650 $80.000 $150.000 $105.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 36.000 $33.000 $32.170 $16.000 $25.000 $22.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 57.000 $33.000 $36.270 $25.000 $35.000 $24.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 49.000 $33.000 $60.130 $60.000 $100.000 $58.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 12.000 $33.000 $81.830 $75.000 $100.000 $79.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 131,035.000 $0.450 $0.340 $0.400 $0.400 $0.430
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 131,744.000 $0.450 $0.340 $0.400 $0.400 $0.430
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,811.000 $4.500 $6.750 $4.000 $7.000 $5.450
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 7,500.000 $0.330 $1.520 $1.000 $1.750 $1.200
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 12,046.000 $1.500 $1.520 $0.400 $1.750 $1.450
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 7,764.000 $0.330 $1.520 $1.000 $1.750 $1.200
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 5,896.000 $1.500 $1.520 $0.400 $1.750 $1.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 10,426.000 $1.500 $1.860 $0.800 $1.500 $3.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,450.000 $1.600 $1.560 $1.300 $2.000 $1.750
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 300.000 $1.300 $3.130 $2.500 $5.000 $2.300
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,727.000 $1.100 $2.050 $2.100 $2.500 $1.450
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 16.000 $2.000 $25.910 $6.000 $30.000 $25.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 2.000 $360.000 $932.720 $185.000 $1,000.000 $440.000
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 270.000 $2.000 $12.950 $3.500 $15.000 $7.000
REFL PAV MRK TY II (W) 6" (SLD)
LF 54,298.000 $0.400 $0.240 $0.500 $0.300 $0.450
REFL PAV MRK TY II (Y) 6" (BRK)
LF 3,829.000 $0.400 $0.240 $0.500 $0.300 $0.550
REFL PAV MRK TY II (Y) 6" (SLD)
LF 34,417.000 $0.400 $0.240 $0.500 $0.300 $0.450
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 6,490.000 $0.650 $0.980 $1.100 $1.100 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 76,138.000 $0.700 $0.930 $1.100 $1.000 $0.950
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 84,332.000 $0.800 $0.930 $1.100 $1.000 $0.950
PREFAB PAV MRK TY C (W) (ARROW)
EA 9.000 $240.000 $414.540 $250.000 $500.000 $300.000
PREFAB PAV MRK TY C (W) (WORD)
EA 9.000 $270.000 $491.780 $325.000 $525.000 $400.000
REFL PAV MRKR TY I-C
EA 232.000 $4.000 $6.210 $4.500 $7.000 $8.000
REFL PAV MRKR TY II-A-A
EA 1,949.000 $3.700 $6.210 $4.250 $7.000 $7.000
ELIM EXT PAV MRK & MRKS (4")
LF 89,996.000 $0.500 $1.560 $0.500 $1.750 $0.550
ELIM EXT PAV MRK & MRKRS(PLOWABLE RPMS)
EA 49.000 $0.500 $10.360 $16.000 $25.000 $10.000
VEH SIG SEC (12")LED(YEL)
EA 4.000 $415.000 $439.470 $450.000 $650.000 $424.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $10,000.000 $13,267.290 $13,100.000 $14,000.000 $12,807.000
D-GR HMA TY-B SAC-B PG64-22
TON 6,562.000 $145.000 $162.790 $145.000 $112.000 $135.000
SP MIXES SP-D PG76-22
TON 12,653.000 $160.000 $180.630 $165.000 $130.000 $165.000
BONDING COURSE
GAL 24,297.000 $4.500 $5.720 $5.000 $4.500 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,020.000 $110.000 $92.100 $40.000 $125.000 $5.770
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 320.000 $25.000 $25.910 $4.000 $35.000 $15.000
TMA (STATIONARY)
DAY 510.000 $250.000 $188.210 $200.000 $400.000 $239.190
TMA (MOBILE OPERATION)
HR 260.000 $100.000 $193.830 $90.000 $100.000 $770.110
Totals: $28,367,743.870 $32,511,818.356 $36,946,649.580 $37,087,429.230 $40,043,246.997