MEDINA CR (0915-45-056)

Items: 48

County: MEDINA
Length: N/A
Highway: CR
District: SAN ANTONIO
Control Number: 0915-45-056
DBE Goal: N/A
Project: BR 2022(416)
Guaranty: N/A
Time: 149 WORKING DAYS
Engineer's Estimate: $718,847.77
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
CHRISTEN LONGORIA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$718,847.77
$730,221.00
Over/Under Est: 1.58% $11,373.23
$831,628.00
Over/Under Est: 15.69% $112,780.23
Amt Left: 13.89% $101,407.00
Over/Under Est: 20.27% $145,733.57
Amt Left: 18.4% $134,360.34
Delta: -3.96% -$32,953.34
Over/Under Est: 61.57% $442,610.23
Amt Left: 59.06% $431,237.00
Delta: -34.34% -$296,876.66
Subcontractor Percentage Amount
BEAIRD DRILLING 6.40% $49,673.51
SPENCER PIER DRILLING CO 6.29% $48,819.75
DIIBS SPECIALISTS, LLC 4.20% $32,598.24
TRP CONSTRUCTION GROUP, LLC 2.91% $22,585.93
A K FUQUAY CONSTRUCTION 1.12% $8,692.87
FLASHER EQUIPMENT COMPANY 1.12% $8,692.87
Total: 22.04% $171,063.17

Bid Items & Bid Tabulations

48 Total 0 of 48
MEDINA  |  CR  |  SAN ANTONIO  |  0915-45-056  |  06/01/2023  |  $718,847.77  |  BR 2022(416)  |  BRIDGE REPL  |  149 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACEE CONSTRUCTION LLC.
J3 COMPANY, LLC
E-Z BEL CONSTRUCTION, LLC
DELGADO'S CONTRACTORS, LLC
PREPARING ROW
STA 4.000 $3,000.000 $6,250.000 $3,000.000 $7,275.000 $2,250.000
REMOVING CONC (PAV)
SY 451.000 $14.000 $21.500 $20.000 $28.000 $35.000
REMOVING CONC (RIPRAP)
SY 218.000 $8.000 $8.150 $20.000 $26.000 $45.000
REMOVING CONC (CURB)
LF 174.000 $4.000 $3.200 $5.000 $16.000 $25.000
REMOVING CONC (MISC)
SY 3.000 $15.000 $100.000 $20.000 $162.000 $50.000
REMOVING STAB BASE & ASPH PAV (0"-10")
SY 300.000 $8.000 $6.500 $25.000 $15.000 $35.000
EXCAVATION (ROADWAY)
CY 210.000 $10.000 $22.500 $40.000 $28.000 $35.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 160.000 $20.000 $30.000 $40.000 $20.000 $85.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 538.000 $1.000 $3.150 $3.000 $1.000 $1.000
CELL FBR MLCH SEED(TEMP)(WARM)
SY 134.500 $1.000 $9.800 $10.000 $0.750 $1.000
CELL FBR MLCH SEED(TEMP)(COOL)
SY 134.500 $1.000 $9.800 $10.000 $0.750 $1.000
VEGETATIVE WATERING
MG 9.000 $20.000 $264.500 $100.000 $268.000 $200.000
CONC PVMT (CONT REINF - CRCP) (7")
SY 806.000 $130.000 $105.000 $95.000 $137.000 $200.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 840.000 $82.000 $9.000 $22.000 $20.000 $20.000
DRILL SHAFT (30 IN)
LF 207.000 $300.000 $287.500 $350.000 $332.000 $1,000.000
CL C CONC (ABUT)
CY 18.900 $1,600.000 $1,140.600 $1,500.000 $1,691.000 $1,800.000
CL C CONC (CAP)
CY 8.700 $1,600.000 $1,092.250 $2,500.000 $1,486.000 $2,000.000
CL C CONC (COLUMN)
CY 2.200 $1,600.000 $1,321.950 $4,000.000 $2,944.000 $2,000.000
REINF CONC SLAB (SLAB BEAM)
SF 1,820.000 $17.000 $19.500 $35.000 $30.000 $35.000
APPROACH SLAB
CY 38.500 $500.000 $650.000 $750.000 $979.000 $1,000.000
PRESTR CONC SLAB BEAM (5SB12)
LF 345.000 $250.000 $255.000 $325.000 $367.000 $260.000
RIPRAP (CONC)(CL B)(5 IN)
CY 67.100 $500.000 $485.000 $700.000 $972.000 $600.000
RIPRAP (MOW STRIP)(4 IN)
CY 50.600 $580.000 $485.000 $700.000 $960.000 $600.000
STR STEEL (MISC NON - BRIDGE)
LB 135.000 $16.000 $25.200 $35.000 $4.000 $30.000
RAIL (TY T223)
LF 164.000 $100.000 $133.100 $175.000 $239.000 $185.000
ARMOR JOINT (SEALED)
LF 44.000 $125.720 $199.850 $200.000 $166.000 $250.000
PIPE (PVC) (SCH 80) (8 IN)
LF 25.000 $75.000 $37.100 $55.000 $68.000 $10.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $21,000.000 $22,500.000 $54,000.000 $33,149.000 $75,000.000
MOBILIZATION
LS 1.000 $46,975.090 $71,000.000 $40,000.000 $15,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $2,000.000 $4,500.000 $2,500.000 $3,000.000 $2,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 657.000 $3.000 $5.250 $5.000 $4.500 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 657.000 $1.000 $2.050 $2.000 $1.500 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 650.000 $25.000 $28.700 $30.000 $25.000 $35.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,500.000 $1,412.250 $1,250.000 $1,051.000 $1,400.000
REMOVE METAL BEAM GUARD FENCE
LF 190.000 $4.000 $3.150 $8.000 $2.500 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $200.000 $236.250 $1,000.000 $250.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,200.000 $3,470.250 $3,500.000 $3,380.000 $4,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 11.000 $600.000 $719.250 $685.000 $685.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $700.000 $787.500 $750.000 $750.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 8.000 $120.000 $120.750 $115.000 $115.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 2.000 $25.000 $31.500 $30.000 $30.000 $50.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $6.000 $10.500 $10.000 $10.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $30.000 $31.500 $30.000 $30.000 $50.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 746.000 $1.000 $9.150 $5.000 $4.000 $10.000
REFL PAV MRKR TY II-A-A
EA 8.000 $7.000 $10.500 $50.000 $25.000 $20.000
D-GR HMA TY-B PG64-22
TON 186.000 $80.000 $121.600 $150.000 $150.000 $225.000
D-GR HMA TY-D PG64-22
TON 36.000 $80.000 $185.750 $295.000 $250.000 $225.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $14,000.000 $4,000.000 $3,550.000 $12,000.000
Totals: $718,847.770 $730,221.005 $831,628.000 $864,581.350 $1,161,458.000