MEDINA SH 173 (0421-02-034)

Items: 56

County: MEDINA
Length: 1.5830 MILES
Highway: SH 173
District: SAN ANTONIO
Control Number: 0421-02-034
DBE Goal: 0.0%
Project: F 2026(464)
Guaranty: $40,000.00
Time: 100 WORKING DAYS
Engineer's Estimate: $1,990,895.74
Date: 03/04/2026 (3 months ago)
Contract Number: 3263012
Type: RESURFACE ROADWAY
Project ID: A00189338
Contract Type: Federal
Project Description: MILL AND INLAY, BASE REPAIR AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
FRANCES MERECKA
ENRIQUE MANUEL GONZALEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$1,990,895.74
$1,524,647.42
Over/Under Est: -23.42% -$466,248.32
Over/Under Est: -20.62% -$410,545.18
Amt Left: 3.65% $55,703.14
$1,641,496.58
Over/Under Est: -17.55% -$349,399.16
Amt Left: 7.66% $116,849.16
Delta: -3.87% -$61,146.02
Over/Under Est: -16.71% -$332,616.39
Amt Left: 8.76% $133,631.93
Delta: -1.02% -$16,782.77
$1,843,752.03
Over/Under Est: -7.39% -$147,143.71
Amt Left: 20.93% $319,104.61
Delta: -11.18% -$185,472.68
Over/Under Est: -5.18% -$103,030.54
Amt Left: 23.82% $363,217.78
Delta: -2.39% -$44,113.17
Over/Under Est: -3.18% -$63,375.62
Amt Left: 26.42% $402,872.70
Delta: -2.10% -$39,654.92
Over/Under Est: 0.58% $11,485.65
Amt Left: 31.33% $477,733.97
Delta: -3.88% -$74,861.27
Over/Under Est: 15.97% $317,967.26
Amt Left: 51.44% $784,215.58
Delta: -15.31% -$306,481.61
$2,343,883.55
Over/Under Est: 17.73% $352,987.81
Amt Left: 53.73% $819,236.13
Delta: -1.52% -$35,020.55
Over/Under Est: 31.9% $635,180.34
Amt Left: 72.24% $1,101,428.66
Delta: -12.04% -$282,192.53

Bid Items & Bid Tabulations

56 Total 0 of 56
MEDINA  |  SH 173  |  SAN ANTONIO  |  0421-02-034  |  03/04/2026  |  $1,990,895.74  |  F 2026(464)  |  RESURF ROADWAY  |  100 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CLARK CONSTRUCTION OF TEXAS, INC.
HUNTER INDUSTRIES, LTD.
BOBCAT SERVICES, INC.
TEXAS MATERIALS GROUP, INC.
ALLEN KELLER COMPANY
H. L. ZUMWALT CONSTRUCTION, INC.
LONE STAR PAVING COMPANY
DEAN WORD COMPANY, LTD.
ANDERSON COLUMBIA CO., INC.
CK NEWBERRY, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
REMOV CONC (CURB RAMP)
SY 249.000 $100.000 $30.000 $22.050 $47.480 $78.000 $21.240 $12.000 $46.000 $31.500 $56.000 $25.000 $31.450
REMOV CONC (CURB)
LF 50.000 $5.000 $18.000 $15.750 $17.270 $20.000 $15.170 $15.000 $16.500 $24.500 $32.000 $20.000 $9.920
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 817.000 $100.000 $112.610 $66.340 $107.120 $100.000 $100.550 $100.000 $117.000 $195.000 $132.000 $160.000 $145.870
SP MIXES SP-C SAC-B PG76-22
TON 5,930.000 $95.000 $104.270 $90.420 $77.150 $105.000 $104.180 $110.000 $110.000 $112.500 $120.000 $120.000 $105.450
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 9,957.000 $50.000 $36.640 $37.720 $31.730 $40.000 $39.460 $40.000 $46.000 $46.500 $55.000 $65.000 $70.430
PLANE ASPH CONC PAV(0" TO 0.5")
SY 37,922.000 $1.420 $0.850 $0.350 $0.460 $1.000 $0.950 $1.500 $0.800 $1.250 $1.800 $1.000 $3.110
PLANE ASPH CONC PAV(2")
SY 51,576.000 $2.250 $1.340 $1.440 $2.400 $1.850 $1.060 $2.000 $1.600 $2.000 $2.000 $1.000 $4.480
RAIL (HANDRAIL)(TY A)
LF 233.000 $150.000 $155.000 $106.040 $266.530 $115.000 $102.120 $190.000 $255.000 $119.250 $110.000 $130.000 $165.410
ADJUSTING MANHOLES
EA 4.000 $1,300.000 $1,050.000 $2,417.600 $2,158.160 $900.000 $2,063.460 $1,500.000 $2,500.000 $939.250 $2,800.000 $3,500.000 $2,186.200
CLEAN EXIST CULVERTS
EA 4.000 $3,000.000 $5,000.000 $1,994.760 $3,114.220 $2,500.000 $1,921.080 $2,500.000 $2,886.000 $2,715.500 $3,000.000 $2,500.000 $2,430.030
REMOVE STR (RAIL)
LF 233.000 $20.000 $38.000 $42.620 $59.350 $6.000 $50.560 $25.000 $40.000 $51.500 $21.000 $15.000 $18.000
MOBILIZATION
LS 1.000 $176,109.750 $21,000.000 $121,898.060 $97,676.070 $65,000.000 $175,000.000 $100,000.000 $155,000.000 $115,000.000 $265,000.000 $225,000.000 $182,466.400
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $1,623.750 $3,483.140 $5,527.580 $7,000.000 $4,905.310 $4,500.000 $850.000 $12,500.000 $2,340.000 $15,000.000 $7,751.260
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $9,000.000 $116.650 $4,545.950 $12,139.640 $1,000.000 $5,059.450 $1,200.000 $1,800.000 $8,621.750 $8,600.000 $10,000.000 $11,365.340
TMA (STATIONARY)
DAY 58.000 $250.000 $88.000 $170.470 $377.680 $50.000 $278.270 $150.000 $250.000 $373.000 $290.000 $400.000 $167.550
TMA (MOBILE OPERATION)
DAY 23.000 $135.000 $88.000 $284.120 $377.680 $50.000 $796.970 $300.000 $250.000 $111.500 $666.000 $100.000 $975.040
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 344.000 $6.000 $5.830 $12.600 $8.630 $12.000 $5.960 $6.000 $8.000 $14.250 $8.000 $12.000 $13.480
BIODEG EROSN CONT LOGS (REMOVE)
LF 344.000 $1.500 $1.170 $2.100 $2.160 $1.000 $1.500 $2.000 $2.000 $2.250 $2.200 $2.000 $3.580
ONE-WAY TRAF CONT (PILOT CAR)
HR 200.000 $100.000 $58.320 $93.500 $68.310 $25.000 $208.480 $100.000 $105.000 $1.000 $220.000 $150.000 $130.600
CONC CURB & GUTTER (TY II)
LF 50.000 $35.000 $138.000 $57.740 $97.120 $90.000 $55.610 $60.000 $93.000 $65.000 $54.000 $60.000 $96.390
CONCRETE C&G (VALLEY GUTTER)
LF 89.000 $70.000 $130.000 $58.790 $85.250 $79.000 $55.610 $85.000 $85.000 $65.000 $81.000 $60.000 $121.720
CURB RAMPS (TY 1)
EA 10.000 $2,800.000 $2,500.000 $1,879.270 $3,010.630 $2,790.000 $1,809.860 $2,600.000 $2,850.000 $2,391.750 $2,430.000 $2,000.000 $2,286.000
CURB RAMPS (TY 5)
EA 3.000 $3,500.000 $2,500.000 $3,359.590 $4,586.090 $4,250.000 $3,235.500 $4,000.000 $4,300.000 $4,058.000 $3,720.000 $3,500.000 $2,653.160
CURB RAMPS (TY 7)
EA 2.000 $3,100.000 $2,500.000 $1,994.760 $3,010.630 $2,790.000 $1,921.080 $3,100.000 $2,900.000 $2,522.000 $2,860.000 $2,000.000 $2,188.500
CURB RAMPS (TY 10)
EA 14.000 $3,000.000 $2,500.000 $1,994.760 $3,010.630 $2,790.000 $1,921.070 $2,900.000 $2,850.000 $2,522.000 $2,650.000 $2,000.000 $2,749.810
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 33.000 $730.000 $667.750 $671.920 $760.750 $640.000 $647.100 $1,000.000 $667.750 $756.250 $690.000 $700.000 $785.010
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 21.000 $800.000 $750.000 $876.640 $906.430 $835.000 $844.270 $1,100.000 $750.000 $880.250 $900.000 $900.000 $933.510
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 8.000 $1,000.000 $900.000 $1,107.620 $1,073.680 $1,055.000 $1,066.710 $1,200.000 $900.000 $1,122.500 $1,140.000 $1,200.000 $1,104.010
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 1.000 $1,200.000 $1,500.000 $944.890 $1,429.780 $900.000 $909.980 $1,300.000 $1,500.000 $1,181.750 $970.000 $1,000.000 $1,467.010
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,200.000 $925.000 $1,186.360 $1,213.960 $1,130.000 $1,142.540 $1,400.000 $925.000 $1,279.750 $1,220.000 $1,200.000 $1,247.010
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 2.000 $1,200.000 $950.000 $1,511.820 $1,537.690 $1,440.000 $1,455.980 $1,850.000 $950.000 $1,471.250 $1,555.000 $1,500.000 $1,577.010
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $2,500.000 $1,050.000 $2,419.960 $3,237.240 $2,305.000 $2,330.580 $2,800.000 $2,000.000 $3,220.000 $2,500.000 $2,500.000 $1,697.530
REMOVE SM RD SN SUP&AM
EA 68.000 $120.000 $100.000 $104.990 $129.490 $100.000 $101.110 $28.000 $100.000 $114.500 $108.000 $100.000 $174.510
INSTL OM ASSM (OM-3L)(TWT)GNDLL
EA 1.000 $500.000 $350.000 $267.720 $593.490 $255.000 $257.830 $300.000 $350.000 $35.500 $275.000 $275.000 $614.510
INSTL OM ASSM (OM-3R)(TWT)GNDLL
EA 1.000 $500.000 $350.000 $267.720 $593.490 $255.000 $257.830 $300.000 $350.000 $35.500 $275.000 $275.000 $614.510
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 4,790.000 $0.320 $0.290 $0.370 $0.310 $0.850 $0.350 $1.000 $0.290 $0.300 $0.300 $0.400 $0.400
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 30,638.000 $0.200 $0.290 $0.210 $0.310 $0.280 $0.200 $0.400 $0.290 $0.300 $0.300 $0.350 $0.240
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 27,130.000 $0.400 $0.290 $0.210 $0.310 $0.280 $0.200 $0.400 $0.290 $0.300 $0.300 $0.350 $0.230
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,891.000 $1.000 $0.520 $1.380 $0.510 $0.940 $3.530 $2.000 $1.000 $2.250 $2.300 $1.000 $1.490
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 2,713.000 $1.500 $0.520 $1.380 $0.530 $0.940 $3.570 $2.000 $1.000 $2.250 $2.300 $1.000 $1.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,094.000 $0.950 $1.100 $1.310 $1.190 $1.250 $1.260 $1.500 $1.100 $1.250 $1.200 $2.250 $1.460
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,976.000 $7.000 $6.500 $8.400 $7.010 $6.250 $8.090 $7.000 $6.500 $7.750 $7.000 $9.000 $8.850
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 9.000 $150.000 $150.000 $157.480 $161.860 $145.000 $151.660 $160.000 $150.000 $177.250 $160.000 $150.000 $175.560
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 9.000 $175.000 $175.000 $173.230 $188.840 $155.000 $166.830 $175.000 $175.000 $206.750 $190.000 $160.000 $192.060
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 4.000 $450.000 $550.000 $629.920 $593.490 $325.000 $606.650 $350.000 $550.000 $650.000 $600.000 $480.000 $683.770
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 23.000 $7.500 $6.500 $8.400 $7.010 $7.000 $8.090 $9.000 $6.500 $7.750 $7.000 $14.000 $12.930
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 3.000 $275.000 $350.000 $246.720 $377.680 $300.000 $237.610 $350.000 $350.000 $413.500 $380.000 $300.000 $290.190
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 3,546.000 $0.650 $1.250 $2.100 $1.350 $2.000 $2.030 $3.000 $1.250 $1.500 $1.350 $1.000 $2.230
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 2,395.000 $0.600 $0.650 $0.790 $0.700 $0.670 $0.760 $1.000 $0.650 $0.750 $0.700 $0.750 $0.860
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 11,773.000 $0.550 $0.650 $0.730 $0.700 $0.650 $0.700 $1.000 $0.650 $0.750 $0.700 $0.750 $0.790
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 460.000 $0.750 $0.650 $0.790 $0.700 $0.670 $0.760 $1.000 $0.650 $0.750 $0.700 $0.750 $1.030
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 13,565.000 $0.550 $0.650 $0.730 $0.700 $0.650 $0.700 $1.000 $0.650 $0.750 $0.700 $0.750 $0.790
REFL PAV MRKR TY I-C
EA 174.000 $4.000 $4.500 $4.720 $4.860 $4.000 $4.550 $5.000 $4.500 $5.250 $5.000 $5.000 $5.500
REFL PAV MRKR TY II-A-A
EA 827.000 $3.750 $4.500 $4.720 $4.860 $4.000 $4.550 $5.000 $4.500 $5.250 $5.000 $4.500 $5.060
REPLACE SGT OBJECT MARKER
EA 9.000 $30.000 $0.010 $41.960 $53.950 $50.000 $101.110 $60.000 $200.000 $177.250 $37.000 $50.000 $285.560
UNDERSEAL COURSE
GAL 15,474.000 $3.500 $0.010 $3.430 $3.180 $0.100 $5.340 $5.000 $4.000 $0.010 $4.500 $4.000 $11.050
Totals: $1,990,895.740 $1,524,647.420 $1,580,350.560 $1,641,496.580 $1,658,279.350 $1,843,752.030 $1,887,865.200 $1,927,520.120 $2,002,381.390 $2,308,863.000 $2,343,883.550 $2,626,076.080
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,000.00
Total: $50,000.00