PREPARING ROW
|
STA
|
3.000
|
$3,400.000
|
$1,500.000
|
$5,000.000
|
$2,900.000
|
$1,004.290
|
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-8")
|
SY
|
5,953.000
|
$5.250
|
$1.740
|
$7.000
|
$7.000
|
$4.220
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,037.000
|
$10.500
|
$14.000
|
$20.000
|
$30.000
|
$36.050
|
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
6,283.000
|
$12.000
|
$17.500
|
$20.000
|
$20.000
|
$48.500
|
|
|
|
BLADING
|
STA
|
11.000
|
$230.000
|
$565.000
|
$400.000
|
$1,340.000
|
$596.470
|
|
|
|
ROLL SODDING
|
SY
|
82,628.000
|
$4.000
|
$3.400
|
$3.500
|
$3.340
|
$6.010
|
|
|
|
VEGETATIVE WATERING
|
MG
|
224.000
|
$15.000
|
$36.000
|
$25.000
|
$60.000
|
$25.880
|
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
7,100.000
|
$46.000
|
$54.100
|
$57.000
|
$57.000
|
$98.290
|
|
|
|
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
|
CY
|
1,782.000
|
$57.000
|
$45.000
|
$65.000
|
$41.610
|
$87.320
|
|
|
|
REWORK BS MTL (TY C) (8") (ORD COMP)
|
SY
|
53,769.000
|
$3.000
|
$1.850
|
$2.500
|
$1.030
|
$1.060
|
|
|
|
CEMENT
|
TON
|
637.000
|
$185.000
|
$230.000
|
$250.000
|
$240.000
|
$270.670
|
|
|
|
CEMENT TREAT (EXIST MATL) (6")
|
SY
|
69,843.000
|
$7.250
|
$2.000
|
$2.750
|
$2.600
|
$1.660
|
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
12,466.000
|
$4.600
|
$4.400
|
$6.000
|
$4.700
|
$5.140
|
|
|
|
ASPH (CRS-2)
|
GAL
|
27,997.000
|
$3.000
|
$3.750
|
$3.600
|
$3.700
|
$4.500
|
|
|
|
AGGR(TY-D GR-4 OR TY-L GR-4)
|
CY
|
472.000
|
$140.000
|
$155.000
|
$100.000
|
$140.000
|
$179.010
|
|
|
|
PLANE ASPH CONC PAV(0" TO 3")
|
SY
|
2,199.000
|
$2.000
|
$4.300
|
$3.000
|
$4.200
|
$5.710
|
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
6,619.000
|
$2.000
|
$2.200
|
$2.500
|
$2.000
|
$1.900
|
|
|
|
CEM STABIL BKFL
|
CY
|
86.000
|
$106.000
|
$250.000
|
$225.000
|
$200.000
|
$240.600
|
|
|
|
CUT & RESTORING PAV
|
SY
|
31.000
|
$100.000
|
$100.000
|
$90.000
|
$225.000
|
$270.670
|
|
|
|
FLOWABLE BACKFILL
|
CY
|
7.000
|
$105.000
|
$2,200.000
|
$3,000.000
|
$450.000
|
$541.340
|
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
23.000
|
$4.000
|
$7.500
|
$10.000
|
$15.000
|
$18.040
|
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,916.000
|
$25.000
|
$20.000
|
$25.000
|
$40.000
|
$78.190
|
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
31.000
|
$450.000
|
$800.000
|
$800.000
|
$600.000
|
$842.090
|
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
259.000
|
$140.000
|
$190.000
|
$135.000
|
$200.000
|
$300.750
|
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
57.000
|
$495.000
|
$625.000
|
$600.000
|
$650.000
|
$842.090
|
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
48.000
|
$20.000
|
$115.000
|
$150.000
|
$104.000
|
$192.480
|
|
|
|
RETROFIT RAIL (TY SSTR)
|
LF
|
276.000
|
$155.000
|
$350.000
|
$200.000
|
$225.000
|
$240.600
|
|
|
|
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
|
LF
|
20.000
|
$600.000
|
$838.000
|
$850.000
|
$600.000
|
$721.790
|
|
|
|
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
|
LF
|
28.000
|
$775.000
|
$698.000
|
$700.000
|
$650.000
|
$781.940
|
|
|
|
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
|
LF
|
4.000
|
$1,800.000
|
$1,169.000
|
$1,150.000
|
$700.000
|
$842.090
|
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
40.000
|
$750.000
|
$591.000
|
$600.000
|
$750.000
|
$902.240
|
|
|
|
CONC BOX CULV (7 FT X 6 FT)(EXTEND)
|
LF
|
7.000
|
$720.000
|
$1,132.000
|
$1,150.000
|
$850.000
|
$1,022.540
|
|
|
|
CONC BOX CULV (8 FT X 4 FT)(EXTEND)
|
LF
|
7.000
|
$900.000
|
$1,172.000
|
$1,150.000
|
$950.000
|
$1,142.830
|
|
|
|
CONC BOX CULV (10 FT X 5 FT)(EXTEND)
|
LF
|
25.000
|
$1,050.000
|
$1,540.000
|
$1,500.000
|
$1,000.000
|
$1,443.580
|
|
|
|
CONC BOX CULV (10 FT X 3 FT)(EXTEND)
|
LF
|
4.000
|
$1,000.000
|
$876.000
|
$850.000
|
$950.000
|
$1,202.980
|
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
392.000
|
$35.000
|
$63.000
|
$64.000
|
$50.000
|
$0.000
|
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
392.000
|
$49.000
|
$84.000
|
$85.000
|
$135.000
|
$0.000
|
|
|
|
RC PIPE (CL IV)(30 IN)
|
LF
|
68.000
|
$105.000
|
$183.000
|
$180.000
|
$200.000
|
$270.670
|
|
|
|
WINGWALL (FW - S) (HW=8 FT)
|
EA
|
1.000
|
$20,900.000
|
$13,200.000
|
$13,000.000
|
$10,000.000
|
$14,435.790
|
|
|
|
WINGWALL (PW - 1) (HW=10 FT)
|
EA
|
1.000
|
$40,000.000
|
$32,300.000
|
$31,000.000
|
$32,000.000
|
$40,901.410
|
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
3.000
|
$14,000.000
|
$11,000.000
|
$11,000.000
|
$9,500.000
|
$12,029.830
|
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
3.000
|
$20,000.000
|
$13,900.000
|
$14,000.000
|
$16,000.000
|
$20,450.710
|
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
3.000
|
$27,000.000
|
$23,400.000
|
$24,000.000
|
$19,500.000
|
$25,262.640
|
|
|
|
SET (TY I)(S=10 FT)(HW=4FT)(4:1)(C)
|
EA
|
2.000
|
$25,000.000
|
$25,400.000
|
$26,000.000
|
$20,000.000
|
$26,465.630
|
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
|
EA
|
1.000
|
$11,300.000
|
$17,800.000
|
$18,000.000
|
$13,000.000
|
$15,638.780
|
|
|
|
SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C)
|
EA
|
2.000
|
$9,600.000
|
$16,100.000
|
$16,000.000
|
$11,000.000
|
$14,435.800
|
|
|
|
SET (TY I)(S= 8 FT)(HW= 6 FT)(4:1) (C)
|
EA
|
2.000
|
$13,000.000
|
$18,000.000
|
$18,000.000
|
$15,000.000
|
$19,247.730
|
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
22.000
|
$1,070.000
|
$1,275.000
|
$1,250.000
|
$800.000
|
$1,082.680
|
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
24.000
|
$1,400.000
|
$1,500.000
|
$1,500.000
|
$950.000
|
$1,443.580
|
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$2,600.000
|
$2,300.000
|
$2,200.000
|
$2,500.000
|
$3,007.460
|
|
|
|
ADJUSTING MANHOLES
|
EA
|
2.000
|
$1,450.000
|
$2,000.000
|
$3,000.000
|
$850.000
|
$1,804.480
|
|
|
|
ADJUSTING MANHOLES (WATER VALVE BOX)
|
EA
|
1.000
|
$1,150.000
|
$2,000.000
|
$2,000.000
|
$1,000.000
|
$1,202.990
|
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
11.000
|
$3,400.000
|
$1,600.000
|
$1,650.000
|
$1,500.000
|
$3,007.460
|
|
|
|
REMOV STR (HEADWALL)
|
EA
|
18.000
|
$1,000.000
|
$1,350.000
|
$1,400.000
|
$850.000
|
$1,804.470
|
|
|
|
REMOV STR (PIPE)
|
LF
|
627.900
|
$16.000
|
$10.500
|
$12.000
|
$35.000
|
$48.120
|
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
40.000
|
$56.000
|
$160.000
|
$170.000
|
$225.000
|
$300.750
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$314,000.000
|
$455,000.000
|
$463,000.000
|
$498,000.000
|
$917,450.200
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$8,100.000
|
$15,700.000
|
$10,000.000
|
$28,610.000
|
$13,079.880
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,090.000
|
$30.000
|
$33.500
|
$30.000
|
$35.690
|
$43.310
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,090.000
|
$6.250
|
$12.000
|
$6.500
|
$36.170
|
$16.840
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
1,200.000
|
$30.000
|
$6.000
|
$22.000
|
$8.890
|
$43.310
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
1,200.000
|
$10.000
|
$2.000
|
$6.000
|
$13.120
|
$10.830
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
4,760.000
|
$2.800
|
$5.000
|
$3.500
|
$5.480
|
$6.620
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
4,760.000
|
$0.700
|
$1.000
|
$0.750
|
$0.770
|
$1.200
|
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
2.000
|
$3,400.000
|
$6,500.000
|
$5,500.000
|
$4,760.000
|
$6,014.910
|
|
|
|
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
|
LF
|
210.000
|
$18.000
|
$47.000
|
$18.500
|
$41.000
|
$102.840
|
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
210.000
|
$5.000
|
$22.000
|
$5.000
|
$21.000
|
$16.470
|
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
210.000
|
$13.000
|
$46.000
|
$14.000
|
$40.000
|
$59.390
|
|
|
|
INTERSECTIONS (ACP)
|
SY
|
732.000
|
$50.000
|
$42.000
|
$43.000
|
$43.000
|
$13.620
|
|
|
|
DRIVEWAYS (ACP)(TYPE 1)
|
SY
|
2,644.000
|
$32.000
|
$38.000
|
$35.000
|
$45.000
|
$56.360
|
|
|
|
DRIVEWAYS (ACP) (TYPE 2)
|
SY
|
2,329.000
|
$45.000
|
$46.000
|
$32.000
|
$45.000
|
$52.290
|
|
|
|
DRIVEWAYS (ACP)(TYPE 3)
|
SY
|
248.000
|
$55.000
|
$46.000
|
$30.000
|
$38.000
|
$41.330
|
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
35,631.000
|
$0.180
|
$0.350
|
$0.230
|
$0.160
|
$0.340
|
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
16,498.000
|
$0.200
|
$0.350
|
$0.230
|
$0.200
|
$0.340
|
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
362.500
|
$30.000
|
$32.000
|
$42.000
|
$29.500
|
$47.100
|
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,250.000
|
$3,000.000
|
$2,800.000
|
$2,200.000
|
$3,116.460
|
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
200.000
|
$2.500
|
$3.250
|
$2.500
|
$3.000
|
$10.710
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,000.000
|
$3,150.000
|
$4,000.000
|
$2,900.000
|
$3,838.250
|
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$260.000
|
$325.000
|
$300.000
|
$300.000
|
$535.700
|
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,400.000
|
$2,000.000
|
$1,300.000
|
$1,000.000
|
$1,324.210
|
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
2.000
|
$850.000
|
$1,000.000
|
$850.000
|
$850.000
|
$1,324.210
|
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$8,500.000
|
$9,000.000
|
$9,400.000
|
$7,700.000
|
$12,752.550
|
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
8.000
|
$230.000
|
$217.000
|
$290.000
|
$375.000
|
$451.120
|
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
1.000
|
$265.000
|
$271.000
|
$400.000
|
$425.000
|
$511.270
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$700.000
|
$652.000
|
$1,000.000
|
$1,250.000
|
$1,503.730
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
5.000
|
$915.000
|
$760.000
|
$900.000
|
$1,120.000
|
$1,347.340
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
|
EA
|
1.000
|
$1,000.000
|
$869.000
|
$1,500.000
|
$1,640.000
|
$1,972.900
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$840.000
|
$705.000
|
$1,200.000
|
$1,490.000
|
$1,792.450
|
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
34.000
|
$400.000
|
$460.000
|
$400.000
|
$570.000
|
$685.700
|
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
9.000
|
$520.000
|
$540.000
|
$500.000
|
$680.000
|
$818.030
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
9.000
|
$95.000
|
$215.000
|
$50.000
|
$155.000
|
$186.460
|
|
|
|
RELOCATE SM RD SN SUP & AM TY TEMP
|
EA
|
48.000
|
$230.000
|
$215.000
|
$150.000
|
$210.000
|
$252.630
|
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
30.000
|
$76.000
|
$100.000
|
$50.000
|
$90.000
|
$216.540
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
7.000
|
$44.000
|
$26.000
|
$50.000
|
$24.000
|
$78.190
|
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
4.000
|
$31.000
|
$20.000
|
$30.000
|
$18.000
|
$72.180
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
3,210.000
|
$0.950
|
$0.710
|
$0.700
|
$0.650
|
$1.200
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
19,486.000
|
$0.800
|
$0.670
|
$0.700
|
$0.620
|
$1.200
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,046.000
|
$1.100
|
$1.600
|
$1.500
|
$1.100
|
$1.200
|
|
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
334.000
|
$1.000
|
$1.740
|
$1.800
|
$1.600
|
$1.200
|
|
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
228.000
|
$6.750
|
$16.850
|
$17.000
|
$15.500
|
$7.220
|
|
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
41,622.000
|
$0.380
|
$0.430
|
$0.450
|
$0.400
|
$0.660
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
5,276.000
|
$0.400
|
$0.450
|
$0.450
|
$0.410
|
$0.780
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
19,120.000
|
$0.400
|
$0.530
|
$0.550
|
$0.490
|
$0.660
|
|
|
|
REFL PAV MRKR TY I-C
|
EA
|
18.000
|
$4.700
|
$16.000
|
$16.000
|
$15.000
|
$4.810
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
604.000
|
$3.700
|
$5.000
|
$5.000
|
$4.600
|
$4.810
|
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
7,590.000
|
$86.000
|
$115.000
|
$98.000
|
$138.000
|
$168.420
|
|
|
|
UNDERSEAL COURSE
|
GAL
|
17,241.000
|
$2.300
|
$0.100
|
$2.500
|
$0.010
|
$0.010
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,000.000
|
$10,000.000
|
$11,000.000
|
$10,000.000
|
$15,794.030
|
|
|
|
TMA (STATIONARY)
|
DAY
|
120.000
|
$190.000
|
$25.000
|
$150.000
|
$260.000
|
$379.030
|
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
330.000
|
$52.000
|
$10.000
|
$90.000
|
$25.000
|
$68.410
|
|
|
|
CURB INLET SEDIMENT PROTECTION
|
LF
|
30.000
|
$13.000
|
$25.000
|
$20.000
|
$40.000
|
$30.070
|
|
1
|
|
THERMOPLASTIC PIPE(18 IN)(PP)(TYPE III)
|
LF
|
392.000
|
$35.000
|
$0.000
|
$0.000
|
$0.000
|
$75.000
|
|
2
|
|
THERMOPLASTIC PIPE(24 IN)(PP)(TYPE III)
|
LF
|
392.000
|
$49.000
|
$0.000
|
$0.000
|
$0.000
|
$95.000
|
|
Totals: |
$4,421,409.540
|
$4,553,672.460
|
$4,587,649.920
|
$4,987,799.910
|
$6,755,785.778
|