MAVERICK SH 131 (0375-03-017)

Items: 45

County: MAVERICK
Length: N/A
Highway: SH 131
District: LAREDO
Control Number: 0375-03-017
DBE Goal: 400.0%
Project: STP 2B24(153)HES
Guaranty: N/A
Time: 122 WORKING DAYS
Engineer's Estimate: $2,174,751.08
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: WIDEN SHLDRS, FL BS, SURF TREAT, SETS, & PAV. MK.
Mail/Deliver Bids To: N/A
LUIS URBINA
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,174,751.08
$1,757,673.58
Over/Under Est: -19.18% -$417,077.50
Over/Under Est: -14.26% -$310,099.93
Amt Left: 6.09% $106,977.57
Over/Under Est: -13.28% -$288,827.33
Amt Left: 7.3% $128,250.17
Delta: -1.14% -$21,272.60
Over/Under Est: -13.13% -$285,602.06
Amt Left: 7.48% $131,475.44
Delta: -0.17% -$3,225.27
$1,900,747.50
Over/Under Est: -12.6% -$274,003.58
Amt Left: 8.14% $143,073.92
Delta: -0.61% -$11,598.48
$2,217,456.55
Over/Under Est: 1.96% $42,705.47
Amt Left: 26.16% $459,782.97
Delta: -16.66% -$316,709.05
Over/Under Est: 13.84% $301,003.92
Amt Left: 40.85% $718,081.42
Delta: -11.65% -$258,298.45
Subcontractor Percentage Amount
A K FUQUAY CONSTRUCTION 0.00% $0.00
CENTERLINE TECHNOLOGIES, LLC 0.00% $0.00
EGGEMEYER LAND CLEARING, LLC 0.00% $0.00
TRP CONSTRUCTION GROUP, LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

45 Total 0 of 45
MAVERICK  |  SH 131  |  LAREDO  |  0375-03-017  |  06/05/2024  |  $2,174,751.08  |  STP 2B24(153)HES  |  WIDEN SHLDRS, FL BS, SURF TREAT, SET...  |  122 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. CARROLL WEAVER, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
CLARK CONSTRUCTION OF TEXAS, INC.
HUNTER INDUSTRIES, LTD.
CK NEWBERRY, LLC
STX CIVIL
LCR TOTAL TRANSPORT LLC
PREPARING ROW
STA 162.200 $600.000 $444.000 $316.670 $450.000 $1,021.190 $500.000 $757.000 $1,152.000
SUBGRADE WIDENING (DENS CONT)
STA 162.200 $2,000.000 $283.390 $696.530 $1,118.880 $1,050.000 $800.000 $939.000 $2,860.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 8,934.000 $25.000 $23.310 $17.910 $22.920 $18.400 $20.000 $30.000 $37.250
BLADING
HR 70.000 $200.000 $49.950 $188.670 $150.000 $132.000 $150.000 $240.000 $160.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 11.200 $1,102.560 $1,960.260 $1,899.220 $1,766.000 $1,766.000 $2,000.000 $2,337.000 $1,960.000
DRILL SEEDING (TEMP) (WARM)
AC 11.200 $910.000 $888.000 $1,590.430 $1,504.000 $1,504.000 $1,500.000 $1,990.000 $1,670.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 6,509.200 $100.000 $50.150 $58.360 $73.930 $70.520 $100.000 $80.000 $75.000
PRIME COAT (MC-30)
GAL 4,686.600 $6.000 $5.010 $6.780 $5.010 $6.800 $6.000 $11.000 $6.000
ASPH (MULTI OPTION)
GAL 27,840.300 $4.100 $4.210 $4.510 $3.980 $4.260 $4.500 $11.000 $5.500
AGGR(TY-PB GR-3 SAC-B)
CY 260.400 $100.000 $207.120 $172.190 $100.000 $140.910 $175.000 $132.000 $137.000
AGGR(TY-PB GR-4 SAC-B)
CY 528.000 $130.000 $104.500 $146.420 $100.000 $141.120 $105.000 $130.000 $130.000
FLOWABLE BACKFILL
CY 6.950 $240.420 $333.000 $342.230 $584.000 $250.000 $600.000 $321.000 $430.000
CMP (GAL STL 24 IN)
LF 32.000 $105.000 $199.420 $253.180 $375.000 $325.000 $200.000 $104.000 $148.000
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 8.000 $1,774.150 $3,552.000 $3,208.570 $4,000.000 $2,500.000 $2,500.000 $3,004.000 $3,200.000
CLEAN EXIST CULVERTS
EA 4.000 $3,000.000 $1,554.000 $2,642.720 $1,025.000 $2,500.000 $4,000.000 $2,928.000 $1,560.000
MOBILIZATION
LS 1.000 $164,662.480 $455,000.000 $409,083.620 $243,400.000 $188,053.560 $185,000.000 $170,564.000 $234,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,155.340 $2,775.000 $2,788.120 $12,673.000 $6,400.000 $5,000.000 $6,972.000 $4,250.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 784.000 $40.740 $19.980 $25.710 $24.490 $24.490 $10.000 $32.000 $27.000
CONSTRUCTION EXITS (REMOVE)
SY 784.000 $12.000 $5.550 $11.140 $11.720 $11.720 $5.000 $16.000 $13.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 36.200 $133.150 $38.850 $160.670 $85.000 $96.000 $100.000 $164.000 $125.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,448.000 $5.420 $7.770 $6.820 $7.090 $7.090 $8.000 $9.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,448.000 $5.000 $1.110 $1.320 $1.030 $1.030 $1.000 $1.000 $1.500
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 264.000 $113.870 $43.620 $97.280 $90.000 $120.000 $150.000 $120.000 $137.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 440.000 $195.000 $114.570 $152.580 $120.000 $120.000 $200.000 $175.000 $176.000
DRIVEWAYS (CONC)
SY 55.000 $115.000 $166.500 $260.130 $211.000 $190.000 $200.000 $129.000 $247.000
DRIVEWAYS (BASE)
SY 93.000 $34.290 $48.210 $51.340 $10.520 $23.000 $50.000 $54.000 $57.000
ALUMINUM SIGNS (TY A)
SF 50.000 $80.000 $27.750 $28.770 $40.000 $25.000 $40.000 $40.000 $75.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $700.000 $971.250 $931.330 $1,200.000 $875.000 $1,200.000 $993.000 $1,060.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $950.000 $1,276.500 $1,220.080 $1,250.000 $1,150.000 $1,250.000 $926.000 $1,225.000
REMOVE SM RD SN SUP&AM
EA 6.000 $110.000 $166.500 $170.080 $125.000 $150.000 $125.000 $185.000 $275.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $32.070 $11.100 $23.080 $25.000 $10.000 $25.000 $26.000 $95.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 4.000 $103.330 $216.450 $217.330 $125.000 $195.000 $125.000 $146.000 $120.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,457.000 $0.900 $1.110 $1.210 $2.000 $1.630 $1.000 $1.000 $3.000
PAVEMENT SEALER 6"
LF 43,015.000 $0.260 $0.440 $0.670 $0.220 $0.400 $0.250 $0.500 $0.350
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 32,446.000 $0.630 $1.110 $1.060 $0.630 $1.000 $0.700 $1.000 $0.800
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 3,707.000 $0.550 $1.170 $1.140 $0.820 $1.050 $0.900 $1.000 $0.800
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 6,862.000 $0.580 $1.110 $1.060 $0.780 $1.000 $0.900 $1.000 $0.800
REFL PAV MRKR TY II-A-A
EA 273.000 $4.490 $11.100 $4.920 $5.800 $10.000 $6.500 $7.000 $5.600
TRAFFIC BUTTON TY W
EA 6,336.000 $4.600 $6.660 $4.120 $2.200 $6.000 $2.500 $4.000 $3.600
TRAFFIC BUTTON TY Y
EA 2,153.000 $2.440 $6.660 $4.280 $2.200 $6.000 $2.500 $4.000 $3.600
TRAFFIC BUTTON TY B
EA 1,093.000 $2.240 $6.660 $4.500 $2.200 $6.000 $2.500 $8.000 $6.700
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,405.000 $6,105.000 $10,607.730 $25,000.000 $12,252.900 $7,000.000 $8,595.000 $10,700.000
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $14,000.000 $13,597.500 $10,332.870 $10,000.000 $14,000.000 $4,000.000 $14,557.000 $9,100.000
TMA (STATIONARY)
DAY 44.000 $270.000 $138.750 $216.650 $250.000 $284.270 $325.000 $287.000 $475.000
TMA (MOBILE OPERATION)
DAY 26.000 $300.000 $49.950 $599.770 $500.000 $365.660 $30.000 $344.000 $550.000
Totals: $2,174,751.081 $1,757,673.607 $1,864,651.202 $1,885,923.772 $1,889,149.044 $1,900,747.500 $2,217,456.550 $2,475,755.000