MATAGORDA FM 2031 (0604-01-043)

Items: 36

County: MATAGORDA
Length: N/A
Highway: FM 2031
District: YOAKUM
Control Number: 0604-01-043
DBE Goal: N/A
Project: STP 2019(175)HES
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $593,324.55
Date: 11/07/2018 (7 years ago)
Contract Number: N/A
Type: WIDEN PAVED SURFACE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$593,324.55
Over/Under Est: 0.12% $683.32
Over/Under Est: 14.62% $86,743.51
Amt Left: 14.49% $86,060.19
Over/Under Est: 69.48% $412,267.49
Amt Left: 69.29% $411,584.17
Delta: -47.87% -$325,523.98

Bid Items & Bid Tabulations

36 Total 0 of 36
MATAGORDA  |  FM 2031  |  YOAKUM  |  0604-01-043  |  11/07/2018  |  $593,324.55  |  STP 2019(175)HES  |  WIDEN PAVED SURF  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REXCO CONSTRUCTION SERVICES, INC.
BRANNAN PAVING CO., LTD.
JAMES CONSTRUCTION GROUP, L.L.C.
EXCAVATION (ROADWAY)
CY 208.000 $15.000 $13.750 $63.430 $100.000
SUBGRADE WIDENING (ORD COMP)
STA 55.620 $800.000 $289.000 $423.040 $1,200.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 556.000 $23.000 $21.870 $24.080 $70.000
BLADING
HR 20.000 $120.000 $85.000 $100.000 $120.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
AC 2.550 $2,000.000 $1,818.000 $1,500.000 $1,800.000
CELL FBR MLCH SEED(TEMP)(WARM)
AC 0.640 $2,000.000 $1,818.000 $2,500.000 $1,800.000
CELL FBR MLCH SEED(TEMP)(COOL)
AC 0.640 $2,000.000 $1,818.000 $2,500.000 $1,800.000
VEGETATIVE WATERING
MG 69.400 $20.000 $45.080 $10.000 $50.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 3,039.000 $65.000 $73.540 $90.460 $140.000
CEMENT
TON 175.000 $150.000 $145.180 $141.170 $168.000
CEMENT TREAT (EXIST MATL) (6")
SY 19,158.000 $2.000 $1.220 $1.320 $2.000
ASPH (RC-250)
GAL 3,461.000 $3.000 $3.730 $5.210 $3.470
AGGR(TY-E GR-5 SAC-B)
CY 124.000 $100.000 $117.490 $136.100 $170.000
AGGR(TY-PE GR-3 SAC-B)
CY 204.000 $100.000 $120.400 $145.700 $160.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 6,922.000 $3.000 $3.410 $4.750 $3.300
MOBILIZATION
LS 1.000 $50,000.000 $87,910.000 $44,450.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $1,007.500 $5,926.000 $705.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 20.000 $50.000 $45.450 $30.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $10.000 $10.100 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,400.000 $2.500 $1.970 $2.750 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,400.000 $1.000 $0.510 $0.500 $0.500
DRIVEWAYS (SURF TREAT)
SY 2,266.000 $25.000 $21.000 $26.070 $50.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 9.000 $450.000 $449.450 $344.660 $300.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $500.000 $752.450 $388.550 $400.000
REMOVE SM RD SN SUP&AM
EA 11.000 $50.000 $65.650 $97.070 $60.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 11,124.000 $0.400 $0.420 $0.240 $0.240
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 1,391.000 $0.400 $0.450 $0.240 $0.240
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,570.000 $0.400 $0.450 $0.240 $0.240
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,090.000 $1.000 $1.370 $1.500 $0.470
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,124.000 $0.300 $0.420 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,391.000 $0.350 $0.450 $0.440 $0.440
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 2,570.000 $0.300 $0.450 $0.410 $0.410
REFL PAV MRKR TY II-A-A
EA 101.000 $3.500 $3.790 $4.730 $4.730
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,000.000 $7,575.000 $4,800.000 $3,600.000
TMA (STATIONARY)
EA 1.000 $5,000.000 $3,500.000 $5,000.000 $13,000.000
TMA (MOBILE OPERATION)
DAY 10.000 $500.000 $250.000 $250.000 $500.000
Totals: $593,324.550 $594,007.872 $680,068.065 $1,005,592.040