Show Job Controls
Bid Cobra

MATAGORDA BS 35-H (0179-14-008)

Items: 54

County: MATAGORDA
Length: N/A
Highway: BS 35-H
District: YOAKUM
Control Number: 0179-14-008
DBE Goal: N/A
Project: STP 2017(204)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $1,711,640.20
Date: 07/11/2017 (8 years ago)
Contract Number: N/A
Type: OVERLAY AND PAVEMENT WIDENING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,711,640.20
$1,611,272.54
Over/Under Est: -5.86% -$100,367.66
Over/Under Est: 6.27% $107,404.32
Amt Left: 12.89% $207,771.98
Over/Under Est: 25.71% $440,087.90
Amt Left: 33.54% $540,455.56
Delta: -18.29% -$332,683.58

Bid Items & Bid Tabulations

54 Total 0 of 54
MATAGORDA  |  BS 35-H  |  YOAKUM  |  0179-14-008  |  07/11/2017  |  $1,711,640.20  |  STP 2017(204)  |  OVERLAY AND PAVMT WIDENING  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, L.L.C.
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
REMOVING CONC (PAV)
SY 82.000 $20.000 $42.000 $32.480 $40.000
EXCAVATION (ROADWAY)
CY 806.000 $15.000 $10.000 $25.860 $31.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 1,212.000 $20.000 $13.000 $32.160 $34.000
BLADING
HR 40.000 $150.000 $78.000 $85.500 $110.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,744.000 $0.400 $0.750 $0.750 $0.900
CELL FBR MLCH SEED(TEMP)(WARM)
SY 686.000 $0.300 $1.000 $1.950 $1.200
CELL FBR MLCH SEED(TEMP)(COOL)
SY 686.000 $0.300 $1.000 $1.950 $1.200
VEGETATIVE WATERING
MG 23.200 $15.000 $43.000 $19.980 $45.000
FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)
CY 1,866.000 $55.000 $90.500 $82.190 $106.000
CEMENT
TON 102.000 $150.000 $157.000 $147.000 $162.000
CEMENT TREAT (NEW BASE) (10")
SY 6,717.000 $3.500 $2.000 $2.280 $4.900
ASPH (RC-250)
GAL 1,238.000 $4.250 $3.150 $8.760 $4.200
AGGR(TY-E GR-5 SAC-B)
CY 44.000 $85.000 $137.000 $186.800 $179.000
AGGR(TY-PE GR-3 SAC-B)
CY 118.000 $85.000 $147.000 $166.090 $145.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 3,996.000 $3.250 $2.400 $3.010 $4.350
D-GR HMA TY-D PG64-22
TON 576.000 $80.000 $80.000 $103.710 $90.000
D-GR HMA TY-D SAC-B PG70-22
TON 10,198.000 $85.000 $78.000 $74.940 $90.000
D-GR HMA TY-D PG70-22
TON 1,134.000 $82.000 $80.000 $77.220 $90.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 100.000 $75.000 $126.000 $105.450 $113.000
CEM STABIL BKFL
CY 52.000 $50.000 $33.000 $156.250 $116.000
TRENCH EXCAVATION PROTECTION
LF 32.000 $10.000 $27.000 $39.940 $3.300
CONC BOX CULV (8 FT X 4 FT)
LF 232.000 $450.000 $372.000 $855.110 $555.000
RC PIPE (CL III)(24 IN)
LF 80.000 $70.000 $66.000 $102.610 $110.000
SET (TY I)(S= 8 FT)(HW= 5 FT)(3:1) (C)
EA 8.000 $9,000.000 $5,460.000 $10,144.530 $12,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,150.000 $1,970.000 $2,123.550 $1,850.000
ADJUSTING MANHOLES
EA 1.000 $1,500.000 $260.000 $1,624.950 $300.000
REMOV STR (BOX CULVERT)
EA 1.000 $5,000.000 $2,254.000 $6,496.570 $3,600.000
REMOV STR (SMALL)
EA 2.000 $500.000 $602.000 $1,624.150 $285.000
REMOVE STR (RAIL)
LF 50.000 $20.000 $22.500 $40.600 $14.000
MOBILIZATION
LS 1.000 $155,000.000 $150,000.000 $160,300.320 $325,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,000.000 $5,000.000 $1,892.050 $5,985.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 60.000 $75.000 $30.000 $47.000 $36.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $10.000 $10.000 $13.100 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 900.000 $3.000 $4.500 $3.570 $5.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 900.000 $2.000 $1.500 $1.000 $1.800
DRIVEWAYS (ACP)
SY 533.000 $30.000 $25.000 $46.080 $25.000
DRIVEWAYS (SURF TREAT)
SY 80.000 $25.000 $34.000 $46.080 $10.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $3.000 $2.500 $5.000 $10.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $250.000 $500.000 $225.000
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 4.000 $50.000 $50.000 $125.000 $210.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 5,820.000 $0.250 $0.140 $0.180 $0.200
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 38,200.000 $0.200 $0.140 $0.180 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 38,200.000 $0.200 $0.140 $0.180 $0.200
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,746.000 $2.000 $0.440 $1.550 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,480.000 $1.250 $0.440 $1.550 $1.000
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 5,820.000 $0.350 $0.280 $0.340 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 38,200.000 $0.300 $0.280 $0.340 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 38,200.000 $0.350 $0.280 $0.340 $0.400
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 260.000 $10.000 $7.900 $10.000 $12.000
PREFAB PAV MRK TY C (W) (18") (SLD)
LF 108.000 $12.000 $12.000 $14.000 $17.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 44.000 $15.000 $17.000 $20.000 $24.000
REFL PAV MRKR TY I-C
EA 292.000 $5.000 $4.000 $4.000 $5.000
REFL PAV MRKR TY II-A-A
EA 479.000 $3.000 $4.000 $4.000 $5.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $5,500.000 $4,059.380 $3,000.000
Totals: $1,711,640.200 $1,611,272.540 $1,819,044.526 $2,151,728.100